The High Court of Delhi dismissed the appeal filed by M/s Bansal Construction Co. (Appellant) against the judgment dated July 30, 2021, of the Commercial Court, which had partially set aside an arbitral award. The High Court affirmed that the Arbitral Tribunal exceeded its jurisdiction by awarding claims that were expressly barred by the General Conditions of Contract (GCC) and the Special Tender Conditions (STC), specifically clauses prohibiting compensation for idle labor/machinery and pre-award interest.
Background
- Contractual Dispute: The appellant was awarded a railway work contract in 2004, which faced significant delays due to the respondent’s failure to provide necessary materials.
- Arbitration: Following a dispute over unpaid dues and damages, an Arbitral Tribunal awarded the appellant ₹22,44,464 across seven claims.
- Section 34 Petition: The respondent challenged this award in the Commercial Court. The District Judge set aside Claim Nos. 1, 4, 5, 7, and 8, and modified the post-award interest from 18% to 12%.
Key Findings of the High Court
The High Court analyzed the appellant’s challenges and upheld the District Judge’s decision based on the following:
- Claim No. 1 (Arbitration Costs): The Court rejected this claim, citing Clause 64(6) of the GCC, which mandates that parties bear their own arbitration costs.
- Claim No. 4 (Idle Labor/Machinery): The Court held this claim was rightly set aside. Clause 17A of the GCC allows for time extensions but explicitly bars compensation for delays. Furthermore, Clause 33 of the Special Tender Conditions prohibits claims for idle labor, idle machinery, or business losses.
- Claim No. 5 (Pre-award Interest): The Court affirmed the rejection of this claim. Clauses 16(3) and 64(5) of the GCC provide a specific, categorical bar against the grant of pre-award interest. Relying on precedents like Garg Builders v. BHEL and Union of India v. Bright Power Projects, the Court reaffirmed that an Arbitrator cannot award interest where the contract expressly prohibits it.
- Claim No. 7 (Loss of Profit): The Court rejected this claim because Clause 61(3) of the GCC prohibits compensation for loss of profit or advantage that would have been derived had the contract been completed.
- Claim No. 8 (Interest on Claim No. 4): As this claim was based on the disallowed Claim No. 4 and sought interest in violation of the contract’s bar on pre-award interest, the Court upheld its rejection.
Conclusion
The Court concluded that the Arbitral Tribunal acted contrary to the express terms of the contract. It emphasized that an arbitrator, being a creature of the contract, cannot award damages or interest that the contract explicitly prohibits. Consequently, the appeal was dismissed as being devoid of merit.




