The core of the case involves Parsvnath Film City Ltd. and the Chandigarh Administration, stemming from a terminated development agreement. The judgment outlines the history of the project, contractual obligations, and the various claims and counter-claims made by both parties, initially before an Arbitral Tribunal, then appealed through lower courts. Ultimately, the Supreme Court reverses the High Court’s decision, largely upholding the original arbitral award in favour of Parsvnath Film City Ltd., though with modifications to the interest rate and compensation amount.
Arbitration and Conciliation Act, 1996, Section 34 and 37 – Arbitration award – Setting aside by High Court in appeal – Reasoning of the impugned judgment to set aside the Arbitral Award and the order of the Additional District Judge proceeded on a wrong basis and has wrongly set aside the arbitral award – Development Agreement was executed between the parties on 02.03.2007 – The entire project was based on a ‘Right to Participate Model’, where the entire cost of development of the Project with all related infrastructure and utilities was to be done under ‘Develop-Build-Finance-Maintain-Operate’ methodology – Article 3.3 of the Agreement provided for the development period which was “a total period of 36 (thirty six) months (including 30 [thirty] months of construction period) starting from the Agreement date” – As noted by the Arbitral Tribunal and the District Court, the appellant had been requesting the respondents for the demarcation of the project site since 21.02.2007 – However, the demarcation plan was issued only on 17.07.2008, i.e. after an unreasonable delay of 16.5 months just before half the period of 36 months was complete – The appellant could not have anticipated that there would be a delay of such duration in the mere issuance of a demarcation plan – There was a clear and unreasonable delay attributable to the respondents in handing over encumbrance free land to the appellant – About 22 months had passed since the development agreement was signed between the parties, and the development period would have completed in another 14 months, had the respondents completed their obligations on time – In such a scenario, the appellant cannot be held to have shown unwillingness to carry on with the work, as held in the impugned judgment – Appellant would have had to engage the services of different professional agencies beforehand – All such subcontracts would have been frustrated due to the delay attributable to the respondents – It was only when no progress took place despite a month having passed since the meeting that the appellant declared the development agreement to have been frustrated – Time was of the essence in this project – Therefore, each day’s delay in executing the project after signing of the Development Agreement had commercial consequences and struck at the heart of the Development Agreement – As the delay here extended to more than 16 months, the impugned judgment could not have termed the issues between the parties as trivial and that the parties were ad idem in solving them – Held that the High Court was not justified in setting aside the Arbitral Award dated 10.03.2012 and consequently, the order passed on the application filed under Section 34 of the Act – Appellant entitled to the sum of Rs.47.75 crores, being the initial deposit and Rs.46,20,715/- being the actual expenses incurred – However, the rate of interest awarded at 12% per annum is on the higher side and modified at the rate of 8% per annum, while retaining the other directions – Having regard to payment of interest has been ordered both with regard to initial deposit as well as on the actual expenses, the award of compensation for loss of Rs.47,75,000/- was not in order – Arbitral Tribunal’s Award dated 10.03.2021 is modified in the aforesaid terms – Respondent(s) directed to deposit/pay the amount on or before 30.06.2025 without driving the appellant for execution of the said Award – If the amount is not paid to the appellant on or before 30.06.2025, the interest shall be at the rate of 12% per annum instead of the reduced rate of 8% per annum.
(Para 28 to 31)
M/S. Parsvnath Film City Ltd. V. Chandigarh Administration & Others
Supreme Court: 2025 INSC 464: (DoJ 20-03-2025)




