2025 INSC 464
SUPREME COURT OF INDIA
(HON’BLE B.V. NAGARATHNA, J. AND
HON’BLE SATISH CHANDRA SHARMA, JJ.)
M/S. PARSVNATH FILM
CITY LTD.
Appellant
VERSUS
CHANDIGARH
ADMINISTRATION & OTHERS
Respondent
THE SECRETARY,
INFORMATION TECHNOLOLGY, CHANDIGARH ADMINISTRATION
Appellant
VERSUS
M/S. PARSVNATH FILM
CITY LTD. & OTHERS
Respondent
Civil Appeal No.6162 OF 2016 With
Civil Appeal No. 10490 OF 2017-Decided on 20-03-2025
Arbitration
Arbitration and
Conciliation Act, 1996, Section 34 and 37 – Arbitration award – Setting aside
by High Court in appeal -
Reasoning of the impugned judgment to set aside the Arbitral Award and the
order of the Additional District Judge proceeded on a wrong basis and has
wrongly set aside the arbitral award - Development Agreement was executed
between the parties on 02.03.2007 - The entire project was based on a 'Right to
Participate Model', where the entire cost of development of the Project with
all related infrastructure and utilities was to be done under
'Develop-Build-Finance-Maintain-Operate' methodology - Article 3.3 of the
Agreement provided for the development period which was "a total period of
36 (thirty six) months (including 30 [thirty] months of construction period)
starting from the Agreement date" - As noted by the Arbitral Tribunal and
the District Court, the appellant had been requesting the respondents for the
demarcation of the project site since 21.02.2007 - However, the demarcation
plan was issued only on 17.07.2008, i.e. after an unreasonable delay of 16.5
months just before half the period of 36 months was complete - The appellant
could not have anticipated that there would be a delay of such duration in the
mere issuance of a demarcation plan - There was a clear and unreasonable delay
attributable to the respondents in handing over encumbrance free land to the
appellant - About 22 months had passed since the development agreement was
signed between the parties, and the development period would have completed in
another 14 months, had the respondents completed their obligations on time - In
such a scenario, the appellant cannot be held to have shown unwillingness to
carry on with the work, as held in the impugned judgment - Appellant would have
had to engage the services of different professional agencies beforehand - All
such subcontracts would have been frustrated due to the delay attributable to
the respondents - It was only when no progress took place despite a month
having passed since the meeting that the appellant declared the development
agreement to have been frustrated - Time was of the essence in this project -
Therefore, each day's delay in executing the project after signing of the
Development Agreement had commercial consequences and struck at the heart of
the Development Agreement - As the delay here extended to more than 16 months,
the impugned judgment could not have termed the issues between the parties as
trivial and that the parties were ad idem in solving them – Held that the High
Court was not justified in setting aside the Arbitral Award dated 10.03.2012
and consequently, the order passed on the application filed under Section 34 of
the Act - Appellant entitled to the sum of Rs.47.75 crores, being the initial
deposit and Rs.46,20,715/- being the actual expenses incurred - However, the
rate of interest awarded at 12% per annum is on the higher side and modified at the rate of 8% per annum, while
retaining the other directions - Having regard to payment of interest has been ordered both with regard to initial
deposit as well as on the actual expenses, the award of compensation for loss
of Rs.47,75,000/- was not in order - Arbitral Tribunal's Award dated 10.03.2021
is modified in the aforesaid terms - Respondent(s) directed to deposit/pay the
amount on or before 30.06.2025 without driving the appellant for execution of
the said Award - If the amount is not paid to the appellant on or before
30.06.2025, the interest shall be at the rate of 12% per annum instead of the
reduced rate of 8% per annum.
(Para
28 to 31)
JUDGMENT
Nagarathna J. :- Two appeals, namely, Civil
Appeal No.6162 of 2016 and Civil Appeal No. 10490 of 2017, are disposed of by
this common judgment. Civil Appeal No.6162 Of 2016
2. The appellant in Civil Appeal No.6162
of 2016, M/s Parsvnath Film City Limited (hereinafter "appellant") has
approached this Court against the impugned judgment of the High Court of Punjab
and Haryana at Chandigarh in FAO No.5816 of 2015 (O&M) partially allowing
the appeal filed by the respondents (i) Chandigarh Administration and (ii) the
Secretary, Information Technology, Chandigarh Administration under Section 37
of the Arbitration and Conciliation Act, 1996 (for short, "the Act").
The High Court, vide the impugned judgment, set aside the award of the Arbitral
Tribunal dated 10.03.2012 and the order of the Additional District Judge,
Chandigarh in Arbitration Case No.530 of 2013 dated 08.04.2015, thereby
sustaining the respondent's action in forfeiting 25% of the bid amount, i.e.
Rs.47.75 crores.
3. The respondents have filed
Civil Appeal No. 10490 of 2017 against the same impugned judgment on the ground
that it did not allow the other claims raised by them, such as i) interest on
delayed payment of Annual Ground Rent; ii) forfeiture of Rs. Five crores paid
by the appellant towards the bid security; iii) recovery of performance security
shortfall of Rs. Five crores along with interest; and iv) recovery of other
miscellaneous expenses.
4. Respondent Nos.3-5 in both these
appeals are the members of the Arbitral Tribunal who have been added as only
proforma respondents.
5. The facts of the case relate
to the respondents deciding to establish a Multimedia-cum-Film City at
Chandigarh. To that end, it published an advertisement dated 29.03.2006
inviting "Expression of Interest for Multimedia-cum-Film City" as an
integrated project in Sarangpur, Chandigarh on a leasehold land admeasuring
thirty acres. The project involved setting up of state-of-the-art facilities
for
i) a
multimedia-cum-film centre;
ii) a multimedia
park;
iii) a multimedia
information-cum-entertainment centre; and iv) a multimedia college. The
expression of interest complete in all respects was to be submitted on or before
28.04.2006. Out of the fourteen companies which submitted the expression of
interest, six were selected, including the appellant herein. Consequent upon
technical presentations and submission of technical bids, four companies were
shortlisted, including the appellant herein. A copy of the Request for Proposal
and the Draft Development
Agreement was sent to the
appellant by the respondent on 24.11.2006.
6. On receipt of the same, a
pre-bid meeting was held on 08.12.2006 and various clarifications were sought on
the proposal, which were furnished by the respondents vide letter dated 15.12.2006.
Thereafter, the shortlisted companies, including the appellant, submitted their
respective bids, and since the offer of the appellant was the highest, the
respondents issued letter of acceptance in favour of the appellant on
18.01.2007. In that letter, the appellant was asked to take steps for execution
of the Development Agreement within a period of twenty days from the letter and
to also arrange the upfront amount.
7. By letter dated 21.02.2007, appellant
stated that they would sign the Development Agreement, but requested i) for
demarcation of the project site, as without the same, they could not proceed
with the work; and ii) preparation of the layout plan to be annexed with the Development
Agreement. Thereafter, on 01.03.2007, appellant furnished 25% of the bid
amount, i.e. Rs.47.75 crore, by way of Demand Draft.
8. On 02.03.2007, the appellant
expressed its readiness to sign the Development Agreement. However, as the final
demarcation was yet not settled, it requested that:
i) The
date of start of the development period be the date on which the final
demarcation plan is issued to them; and
ii) The
payment of next instalment due which was 75% of the bid price to be paid by the
appellant within 90 days of signing of the agreement should be read as 90 days
from the date the final demarcated plan was issued to them.
9. By a reply letter of the same
date, the respondent had agreed to both the requests, and thereafter both the
parties entered into the Development Agreement on the same date.
10. The provisions in the
Development Agreement relevant to the case at hand are:
"Article
1: DEFINITIONS AND INTERPRETATIONS. 1.1. Definitions
xxx
x(ix) Payment Schedule
Means
the schedule as set out in Schedule IV hereto for payment of consideration by
Developer to CA for right to participate in the development and operation of
the Project.
l)
Performance Security
Means
the security to be provided by the Developer for performance guarantee to CA in
the form of a Bank Guarantee of a Bank as per Article 10.12 hereof.
xxx
Article
2: CONDITIONS PRECEDENT
2.1 CA may,
in its sole option, terminate this Agreement and/or the Lease Agreement if the
following conditions ("Conditions Precedent") are not (in the
reasonable opinion of CA) achieved/fulfilled by the Developer before the expiry
of six(6) Months after the Agreement Date or such extended date as may be
permitted by CA:
2.1.1
If the Developer fails, refuses or is unable to provide the Bank Guarantee as
contemplated in Article 10.12.1 hereof; or
xxx
2.1.3
The Developer obtaining Approvals including environmental clearance from
Ministry Of Environment and Forests.
2.2 If
the Conditions Precedent are not fulfilled, the CA may agree to extend the time
period required to fulfil the Conditions Precedent. In the event that the
Condition Precedent in respect of the Approvals are not fulfilled, then the CA
may (in its sole discretion) provide the Developer the time required to enable
the Developer to obtain the Approvals, provided however that the Scheduled
Project Completion Date shall automatically stand extended commensurately.
2.3 If
any of the Conditions Precedent have not been fulfilled or waived in writing by
the CA, then the CA may, at its sole option, without prejudice to its rights
hereunder and under Applicable Laws, terminate this Agreement whereupon the
amount paid towards Bid Price and Bid Security/ Performance Security (as the
case may be) by the Developer to CA shall forthwith stand forfeited.
XXX
2.5 The
Leasehold Right of the Developer shall be deemed to have begun only on
fulfilling the Conditions Precedent. Till then the Developer shall be deemed to
be acting as a trustee and custodian of the Leasehold Land for and on behalf of
the CA.
Article 3: GRANT OF RIGHTS TO THE
DEVELOPER 3.1 Grant of Leasehold Right
3.1.1 Subject
to the terms hereof, the CA. shall, before the expiry of 90 days after the date
of execution hereof, grant to the Developer Leasehold Right upon and in
relation to 30 acre of the Leasehold Land more particularly described in the
Schedule II hereto, for a period of 99 (ninety nine) years from the date of
signing the Leasehold Agreement as per the terms and conditions more
particularly set out in Schedule VII hereto.
3.1.2 The
right to access and use the Leasehold Land for a period of 99 (ninety nine)
years shall be made available to the Developer by the CA free from all
Encumbrances and occupations. ("Leasehold Right").
3.3
Development Period
3.3.1
The "Development Period" shall be a total period of 36 (thirty six)
Months (including 30 [thirty] Months of construction period) starting from the
Agreement Date. The Development Period includes (a) the period of 6 (six)
Months starting from Agreement Date within which the Developer shall obtain all
requisite Approvals including environmental clearance/s for the Project and (b)
construction period of 30 (thirty) Months starting after the said 6 (six)
Months period set out at (a) above within which the Project is to be completed
by the Developer.
If
delay is due to obtaining of environmental clearance then CA may in its sole
discretion, upon satisfactory reasons for such delay being provided by the
Developer allow extension by such further period as may be deemed necessary by
CA to accommodate the Developer's time-line to procure the said environmental
clearance. In case of such extension, the construction period of 30 (thirty)
months for development of the Project shall commence from the date of obtaining
of environmental clearances.
3.3.2
Provided further that in the event of any delay attributable to the CA in
handing over occupation of the Leasehold Land to the Developer, after payment
of entire Bid Price, the said period of 36 (thirty six) Months shall be
exclusive of the period of any such delay attributable to the CA. For the
avoidance of doubts, the Developer shall be obliged to procure from CA a letter
recording the date on which such hand over of Leasehold Land would have been
effectuated by CA.
xxx
ARTICLE
4: CONSIDERATION
4.1 As
and by way of consideration for the CA granting the Development Right, the
Developer shall pay to CA the following:
4.2
Annual Ground Rent
4.2.1
Annual Ground Rent (AGR) shall be the amount payable by the Developer to CA at
the rate specified in Schedule IV annually in advance from the date of signing
the Agreement till end of the Agreement Period. The Developer shall be required
to pay the AGR yearly in advance (from the date of signing the agreement).
xxx
4.3 Bid
Price
4.3.1
Bid Price means the total amount payable by the Developer to CA i.e. Rs.
191,00,00,000/- [Rupees One hundred and ninety one crores only], being the
consideration payable by the Developer for receiving the right to develop the
Leasehold Land consistently with the terms hereof CA acknowledges receipt of
amount of Rs. 47,75,00,000/- [Rupees Forty seven crore seventy five lac
only]... being a part of the Bid Price required to be paid upfront by the
Developer. The Developer shall pay the balance and outstanding Bid Price to CA
in accordance with the timelines specified in Schedule IV. Under no
circumstances, except provided in this Agreement, the Bid Price accepted shall
be altered and this is the essence of this Agreement.
xxx
5.2
Obligations of the CA
In
addition to any of its other obligations under this Agreement, during the
Development Period, the CA shall;
i)
grant to the Developer, the requisite permission(s) to develop the land
required for the development of the Project. The Leasehold Land shall be made
available to the Developer by Chandigarh Administration free from all
Encumbrances and occupations.
ii)
assist the Developer in obtaining Approvals required by the Developer in
accordance with this Agreement; and
iii)
make arrangement for provision of electricity supply, sewerage and drainages to
be brought to the periphery of the Leasehold Land.
xxx
5.4
Additional Conditions of Agreement 5.4.1 Leasehold Land Conditions
The
Developer shall be deemed to have carefully studied the work and site
conditions specifications, schedules and drawings and various other data and
shall be deemed to have visited the site of the work and to have fully informed
himself regarding the local conditions. Developer shall be deemed to have
carried out his own surveys and investigations and assessment of site
conditions.
xxx
10.11.5
Delay in completion of the Project
In case
of delay in achieving the completion of the construction of the Project within
36 (thirty six) Months from the Agreement Date and subject to satisfaction of
CA for the reasons of such delay, the Developer may be allowed extension of 6
(six) Months to complete the development of the Project. If development of the
Project is not completed within such extended period, then it shall be treated
as Developer's Event of Default.
10.12
Performance Security
10.12.1
In order to ensure that the Project is developed within the stipulated period
of 36 (thirty six) Months from the Agreement Date and the development of the
Project is as per the provision of this Agreement and to facilitate compliance with
the other applicable provisions of this Agreement, the Developer shall furnish
to the CA, Bank Guarantee from any Bank through its branch at Chandigarh for an
amount of Rs. 10 Cr. (Rupees Ten Crore only) within one Month from the date of
execution of this Agreement.
10.12.2
Failure of the Developer to provide the Performance Security in accordance with
this Agreement shall entitle the CA to forfeit the Bid Security amount paid and
to terminate this Agreement in accordance with the provisions of Article 14.1.1
without being liable in any manner whatsoever to the Developer.
xxx
10.12.6
The Developer undertakes that the Performance Security shall be payable
immediately on demand and without the assertion of any defences on part of the
Developer.
xxx
ARTICLE
12: EVENT/S OF DEFAULT AND TERMINATION
12.1
The Developer Event of Default
12.1.1
A "Developer Event of Default" shall be deemed to have occurred if
any of the following events has occurred, unless the same has so occurred as a
consequence of a Force Majeure Event:
xxx
ii) The
Developer fails, neglects, refuses, or is unable to pay the consideration in
accordance with the Payment Schedule indicated in Schedule IV.
xxx
iv) The
Developer repeatedly and persistently remains in breach of any of its
obligations under this Agreement; or
xxx
vi) The
Developer fails to comply with any of the terms and conditions of the Lease
Agreement.
ARTICLE
14: COMPENSATION
14.1
Compensation
14.1.1
Termination due to Developer Event of Default
If the
Termination is due to a Developer Event of Default, no compensation shall be
payable by the CA to the Developer. Bid Price along with Annual Ground Rent
paid by the Developer shall be forfeited. The Security Deposit provided by the
Developer shall be encashed by CA.
xxx
ARTICLE
20: DISPUTE RESOLUTION
XXX
20.3
Arbitrators
In the
event of a Dispute arising out of or in connection with this Agreement not
being resolved in accordance with the provisions of Article 20.2 above. either
Party shall be entitled to, by notice in writing ("Arbitration
Notice") to the other Party, refer such Dispute for final resolution by
binding arbitration in accordance with the Arbitration & Conciliation Act,
1996.
In case
the dispute is referred to arbitration under the Arbitration and Conciliation
Act, 1996 the arbitration shall be by a panel of three Arbitrators, one to be
appointed by each Party and the third to be appointed by the two arbitrators
appointed by the Parties. A Party requiring arbitration shall appoint an
Arbitrator in writing, inform the other Party about such appointment and call
upon the other Party to appoint its Arbitrator. If the other Party fails to
appoint its Arbitrator, the Party appointing Arbitrator shall take steps in
accordance with Arbitration and Conciliation Act, 1996, and subsequent
amendments thereto.
xxx
20.7
Enforcement Award
Any
decision or award resulting from arbitration shall be final and binding upon
the Parties. The Parties hereto hereby waive, to the extent permitted by law,
any rights to appeal or to review of such award by any court or tribunal. The
Parties hereto agree that the arbitral award may be enforced against the
Parties to the arbitration proceeding or their assets wherever they may be
found and that a judgement upon the arbitral award may be entered in any court
having jurisdiction thereof."
11. There were further
communications between the appellant and the respondent over the next few
months concerning the demarcation plan. Further, the appellant also requested,
vide letter dated 14.02.2008, the respondent to remove two HT lines of 11KV
each passing through the alignment where the project was to be set up. It was
only on 17.07.2008, i.e. after 16.5 months, that the demarcation plan was
provided to the appellant. Due to considerable delay, appellant claimed vide
letter dated 08.10.2008 to the respondent that their arrangements with various
other associates for implementing the project was frustrated; that the project
cost escalated; and that the market scenario had changed. Further, they claimed
that i) the two HT lines were yet to be removed; ii) necessary infrastructure
for the project was yet to be provided; and iii) the Zoning Plans were yet to
be released by the respondent.
12. Thereafter, a High Level
Committee was constituted by the respondent on 11.11.2008 where all the above issues
mentioned by the appellant were discussed. It was unanimously decided that the Administrative
Department would work out a proposal with regard to rescheduling of payments by
the appellant.
13. As no further action was
taken by the respondent despite the decisions made in the High-Level Committee
meeting, the appellant declared the development agreement to have been
frustrated and required the earnest money deposited to be returned to them with
interest, vide letter dated 10.12.2008.
However, as there was no response
from the respondent, it again sent a letter dated 01.12.2009 pointing out the
works that were yet to be undertaken by the respondent, and invoked Clauses
20.1 and 20.2 of the Development Agreement to request the respondent to settle
the issues amicably.
14. However, the respondent terminated
the Development Agreement on 16.12.2009 on grounds that i) non-obtaining of
environmental clearance; ii) failure of the appellant to file bank guarantee of
Rs.Ten crores towards the performance security; and iii) non-adherence to
payment schedule. It also forfeited the amount of Rs.47.75 crores which was earlier
paid by the appellant.
15. Aggrieved, the appellant
invoked the arbitration clause in Clause 20.3 of the Development Agreement. As
the respondent refused to appoint an arbitrator, the appellant approached the
High Court, and vide order dated 17.05.2010, the Arbitral Tribunal was
constituted.
16. The appellant raised the
following claims:
i) an amount
of Rs.47.75 Crores paid by the claimants to the respondents towards 25% of bid price;
ii)
interest @ 9% above the prevailing Prime Lending Rate ("PLR") of
State Bank of India on the amount of Rs.47.75 Crores from 01.03.2007 till the
date of refund;
iii)
compensation for all losses and damages suffered by the claimants due to
breaches of contract. Commissions and omissions of the respondents along with
interest thereon @ 9% above the prevailing PLR of State Bank of India;
iv) an
amount of Rs.3,00,00,000 incurred by the claimants for works carried
out/commissioned for the Project;
v)
Claim for compensation for loss of profit/loss of opportunity;
vi)
Claim for pre-suit, pendent-lite and future interest @ 9% above the prevailing
PLR of State Bank of India on the above sums/disputes from the date the same
were incurred till the date of payment thereof;
vii) Claim
for litigation costs (as per actual)
17. The following counter-claims were
raised by the respondents:
i) Declaration
that the termination of the Development Agreement was valid;
ii) Forfeiture
of the amount paid towards the bid price by the appellant to the respondents
was valid;
iii) Claim
for amount to be deposited by the appellant towards Annual Ground Rent as per
the Development Agreement; iv) Forfeiture of Rs.5,00,00,000/- paid towards bid security
by the appellant to the respondents along with interest @ SBI PLR + 9% from 1.4.2007
till 15.9.2010;
v)
Recovery of performance security of Rs. 5,00,00,000/-from the appellant to the
respondents due to nonperformance along with interest @ SBI PLR + 9% from
01.04.2007 till date of payment;
vi) Interest
on investment of Rs.4,50,00,000/- by the respondents in purchase of land for
Film City project remaining unproductive till date due to nonperformance of the
claimants;
vii)
Recovery of Rs.63,13,106/- spent as miscellaneous expenses for the said project
along with interest @ SBI PLR+ 9%p.a.;
viii) Claim
on account of costs of arbitration;
ix)
Claim for pre-suit, pendent-lite and future interest @ SBI PLR + 9% on the
amount found payable;
18. Based on oral and documentary
evidences and the arguments addressed by the learned counsel on both sides, the
Arbitral Tribunal held as follows:
i) That
on the date of signing of the Development Agreement, the final demarcation plan
was not ready, and that without it, the appellant could not have finalised the
layout plan for the project;
ii)
That there was a delay of sixteen and half months in the issuance of
demarcation plan by the respondents, and that the appellant cannot be held
responsible for this delay;
iii)
Respondents were not in a position to handover encumbrance-free land to the
appellant, as required by the Agreement, as even the respondents had
acknowledged that development could not commence without the removal of HT
lines;
iv)
That till the finalisation of the demarcation plan, the appellant had no means
to know whether or not the HT lines would be part of the project site;
v) That
a perusal of the minutes of the meeting dated 11.11.2008 would categorically
reveal that it was the respondents' own admitted case that they defaulted in
providing encumbrance-free land to the appellant;
vi)
That the provision concerning bank guarantee had to be read in context and that
it presupposes the fulfilment of all obligations by the respondents within the
period prescribed in the agreement. Since the respondents had not done so, the
development period could not be said to have started;
vii)
That the claimants were not responsible for the delay in obtaining
environmental clearance since the respondents had not provided the requisite
details;
viii) That
without serving a notice under Article 12.2 of the Development Agreement, the
respondents had no justification or contractual right to terminate the
contract;
ix)
Thus, the termination of the Development Agreement was illegal and de hors the
provisions of the contract. Therefore, all consequential effect had to be borne
by the respondents.
19. The Arbitral Tribunal awarded
to the appellant:
i) Rs.47.75
crores as refund of the amount paid by it towards 25% of the bid price;
ii) 12%
p.a. interest on the above sum of Rs.47.75 crores with effect from 01.03.2007;
iii) Rs.47,75,000
as compensation for all losses and damage suffered by the appellant; iv) Rs.46,20,715
for works carried out/ commissioned for the project; and v) 12% p.a. interest
with effect from 16.12.2009 till date of payment on awards (iii) and
(iv);
vi) Rs.50,00,000 towards litigation costs;
20. The Arbitral Tribunal also
dismissed the counter-claims of the respondents as they were predicated on the
same issues as noted above.
21. Aggrieved, the respondent filed
an application under Section 34 of the Act before the Additional District
Judge, Chandigarh in Arbitration Case No.530 of 2013 for setting aside the
award passed by the Arbitral Tribunal. However, the Court, vide order dated
08.04.2015 dismissed the application holding that it found no reason to
interfere under section 34 of the Act. It held that, based on records, the non-complying
of the requirements/conditions precedent and the non-adherence to the payment
schedule by the appellant was due to non-fulfilling of obligations on the part
of the respondents. It also considered the reasoning of the Arbitral Tribunal
and observed that the aspect of non-depositing of bank guarantee towards
performance security was never raised by the respondents by way of seeking the
same from the appellant, which also showed that such a demand was not raised as
the respondents were aware of the delay being due to their lapse. Further, it
noted that as the schedule of the payment was agreed to be revised, it cannot
be said that the condition regarding depositing of 75% of bid price was
defaulted by the appellant.
22. Aggrieved by the aforesaid
order, the respondent filed an appeal under Section 37 of the Act in FAO
No.5816 of 2015 (O&M) before the High Court of Punjab and Haryana. By the
impugned judgment dated 17.03.2016, the High Court partially allowed the
application, holding that the appellant had shown unwillingness to carry on
with the work and that the said frustration of the contract would not fall within
the provisions of section 56 of the Indian Contract Act, 1872, but would rather
fall under Section 39 of the said Act, which deals with the effect of refusal
of party to perform promise wholly. It observed that both the parties in the
meeting dated 11.11.2008 had put their hands together to solve the issue by
working out a proposal with regard to the rescheduling of the payments by the
appellant, but within a month of that meeting, the appellant frustrated the
agreement. That the respondents cannot be faulted in not issuing thirty days'
advance notice before termination of the contract as it was the appellant who
had shown unwillingness to carry on with the work. The Court further observed
that the award of the Arbitral Tribunal granting compensation of Rs.46,20,715
was wrong as the appellant had not even "used the spade or dug a pit"
and that such an award puts onerous obligation upon the respondents. It noted
that the appellant gave the bid after inspecting the site and was aware of the
HT lines and therefore must have raised the issue before submitting the bid or
ought to not have participated in the bidding. It held that the award of the
Arbitral Tribunal was against public policy and that the Objecting Court ought
not to have dismissed the application under Section 34 of the Act. It further
observed that the appellant appeared to have not shown any interest in carrying
out the work after submission of the bid, as the prices of the property had
fallen, otherwise, till 11.11.2008, both the parties were at ad idem in solving
the trivial issues. Therefore, it upheld the act of the respondent in
forfeiting the earnest money. However, it made no mention of the other claims
of the respondent.
23. Being aggrieved by the above
judgment dated 17.03.2016 passed by the High Court of Punjab and Haryana in FAO
No. 5816/2015 (O&M) in an appeal filed under Section 37 of the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as 'the Act' for the sake
of brevity) by which the order passed by the District Court in an application
filed under Section 34 of the Act was set aside and consequently, Award dated
10.03.2012 passed by the Arbitral Tribunal was also set aside, the claimant in
the Arbitral proceeding is before this Court.
24. We have heard Shri V. Giri,
learned senior counsel for the appellant(s) and Shri Krishna Kant Dubey,
learned counsel for the respondent(s) and perused the material on record.
25. It is noted that the Arbitral
Tribunal by its Award dated 10.03.2012 has firstly directed that the initial amount
deposited by the appellant herein being Rs.47.75 crores, which was 25% of the
total bid amount for Rs.191 crores, to be refunded with interest at the rate of
12% per annum w.e.f. 01.03.2007 till realisation. Secondly, a sum of
Rs.47,75,000/-has been awarded as compensation for actual loss. Thirdly, a sum of
Rs.46,20,715/- has been awarded towards actual expenses incurred by the
appellant herein with interest at the rate of 12% per annum from 16.12.2009,
that is, the date of termination till the date of realisation.
26. The said Award was affirmed
by the District Court in an application filed by the respondent herein under
Section 34 of the Act. It is the aforesaid Award which has now been set aside
in the appeal filed by the respondent herein under Section 37 of the Act and
hence this appeal has been filed.
27. It is also necessary to
observe that the counter claim of the respondent was rejected by the Arbitral
Tribunal as well as by the District Court and the High Court.
Reasons of High Court:
28. The reasoning of the impugned
judgment to set aside the Arbitral Award dated 10.03.2012 and the order of the
Additional District Judge, Chandigarh dated 08.04.2015 was on the basis that:
i. the
appellant refused to perform their promise wholly by showing unwillingness to
carry on with the work and that such unwillingness cannot fall within the four
corners of section 56 of the Indian Contract Act, 1872;
ii. the
appellant frustrated the agreement within just a month of the meeting dated
11.11.2018 wherein both the parties resolved to working out a proposal with
regard to the rescheduling of the payments;
iii.
the appellant must have raised the issue of HT lines before submitting the bid
or ought to not have participated in the bidding process;
iv. the
issues were trivial and both the parties were adidem in solving them;
Consequently,
the impugned judgment held the award to be against public policy and that the
award puts onerous obligation upon the respondents.
29. We hold that the impugned
judgment proceeded on a wrong basis and has wrongly set aside the arbitral
award. We say so for the following reasons:
29.1 Firstly, the Development
Agreement was executed between the parties on 02.03.2007. The entire project
was based on a 'Right to Participate Model', where the entire cost of
development of the Project with all related infrastructure and utilities was to
be done under 'Develop-Build-Finance-Maintain-Operate' methodology. Article 3.3
of the Agreement provided for the development period which was "a total
period of 36 (thirty six) months (including 30 [thirty] months of construction
period) starting from the Agreement date". Further, this development
period also included the period of six months within which the appellant had to
obtain all requisite approvals for the project. As regards delay in obtaining
environmental clearance, the Article allowed for extension due to delay on the
part of the appellant only on satisfactory reasons and subject to the
discretion of the respondents. Article 3.3.2 governed a scenario where delay in
handing over occupation of leasehold land to the appellant was attributable to
the respondents but such a scenario would come into effect only after payment
of the entire bid price. However, it obligated the appellant to procure a
letter from the respondents recording the date on which such handing over of
the leasehold land would be effected by the respondents. Further, Article
10.11.5 provided that if the project was not constructed within 36 months from
the agreement date, the appellant would be allowed an extension of six months
subject to the satisfaction of the respondents as regards the reasons for such
delay.
29.1.1 A reading of the above
provisions would indicate that time was of some essence to this project, unless,
if the delay was attributable to the appellant, then such delay was to be
acceptable to the respondents based on sufficient reason. If the delay was
attributable to the respondents, then such delay was to be excluded from the
period of 36 months, but the appellant was obligated to procure a letter from
the respondents indicating the date on which the handing over of the leasehold land
would be effected.
29.1.2 In the present case, as
noted by the Arbitral Tribunal and the District Court, the appellant had been
requesting the respondents for the demarcation of the project site since
21.02.2007. On the date of signing of the Development Agreement, i.e. on
02.03.2007 when the period of 36 months was to begin, the respondents even
agreed to the appellant's request that the date of start of the development
period be the date when the final demarcation plan was issued to them. However,
the demarcation plan was issued only on 17.07.2008, i.e. after an unreasonable
delay of 16.5 months. In other words, the demarcation plan was issued just
before half the period of 36 months was complete. The appellant could not have
anticipated that there would be a delay of such duration in the mere issuance
of a demarcation plan.
29.2 Secondly, the respondents
were obligated under Article 5.2 of the Development Agreement to grant the
appellant the leasehold land free from all encumbrances and occupations. On a
perusal of the minutes of the meeting dated 11.11.2008 held between the
appellant and the respondents, it could be observed that the respondents
acknowledged that the two HT lines had to be removed so as to provide
encumbrance free land to the appellant. It is relevant to note here that there
was no timeline provided for the same. Further, the minutes also provided that
the Senior Town Planner had to release the revised zoning plan since the
earlier zoning plan was not in accordance with the terms of the Agreement.
However, for this action, the timeline provided was till 17.11.2008. Due to the
delay in granting even the zoning plan, the appellant had requested for certain
reliefs, including an interest amount of Rs.14 crore on the amount of Rs.47.75
crore from 01.03.2007 till 17.07.2008, i.e. the date of delivery of demarcation
plan. This was agreed to by the respondents as well. Further, it was
unanimously agreed that the Administrative Department would work out a proposal
with regard to the re-scheduling of payments by the appellant. However, there
was no definitive date provided therein. Despite such decisions being taken in
the above meeting dated 11.11.2008, there was no further action even till
10.12.2008. Such non-action led the appellant to declare the agreement to have
been frustrated.
29.2.1 If the above facts are
read keeping in mind Article 3.3.2 of the Development Agreement, it would be
clear that there was a clear and unreasonable delay attributable to the
respondents in handing over encumbrance free land to the appellant. Despite
raising this issue several times, the respondents could not provide a definite
date on which they would be able to deliver such encumbrance free land.
Clearly, about 22 months had passed since the development agreement was signed
between the parties, and the development period would have completed in another
14 months, had the respondents completed their obligations on time. In such a
scenario, the appellant cannot be held to have shown unwillingness to carry on
with the work, as held in the impugned judgment.
29.3 Thirdly, the project
envisaged by the respondents was commercial in nature. The appellant was
engaged after a process of competitive bidding. As there was a definite time
period provided for in the Development Agreement to complete the project, the
appellant would have had to engage the services of different professional
agencies beforehand. All such subcontracts would have been frustrated due to
the delay attributable to the respondents. Further, due to the delay, the
appellant would have to engage fresh services of these agencies, the cost of
which would only escalate with time. In these circumstances, the observations
in the impugned judgment to the effect that both the parties, in the meeting
dated 11.11.2008, resolved to working out a proposal with regard to the
rescheduling of the payments and that the appellant frustrated this revised
agreement within just a month of that meeting does not appear to be reasonable
to us. The meeting dated 11.11.2008 was held not only regarding rescheduling of
the payment. Rather, the conclusions arrived at in the meeting dated 11.11.2008
has to be viewed in the context of the terms of the Development Agreement and
the commercial nature of the project. It was only when no progress took place
despite a month having passed since the meeting that the appellant declared the
development agreement to have been frustrated.
29.4 Fourthly, we find it
unreasonable to agree with the observations of the impugned judgment that the
appellant should have raised this issue before submitting the bid or ought to
not have participated in the bidding process. Though, according to the Request
for Proposal, the bidders shall be deemed to have conducted a due diligence
exercise with respect to all aspects of the project, admittedly, the
respondents noted in the meeting dated 11.11.2008 that the two HT lines had to
be removed so as to provide encumbrance free land to the appellant. It was
resolved in that meeting that the matter would be taken up with the PSEB at the
highest level.
29.5 Fifthly, the issues involved
between the parties cannot be termed trivial. As noted earlier, time was of the
essence in this project. Therefore, each day's delay in executing the project
after signing of the Development Agreement had commercial consequences and
struck at the heart of the Development Agreement. As the delay here extended to
more than 16 months, the impugned judgment could not have termed the issues
between the parties as trivial and that the parties were ad idem in solving
them.
30. In the circumstances, we find
that the High Court was not justified in setting aside the Arbitral Award dated
10.03.2012 and consequently, the order passed on the application filed under
Section 34 of the Act. The reasons assigned for doing so in our view are not in
accordance with law. Consequently, we find that the appellant herein is entitled
to the sum of Rs.47.75 crores, being the initial deposit and Rs.46,20,715/-
being the actual expenses incurred. However, the rate of interest awarded at
12% per annum, we find, is on the higher side. In the circumstances, we modify
the rate of interest to 8% per annum, while retaining the other directions.
Having regard to payment of interest, we find that having regard to the fact
that payment of interest has been ordered both with regard to initial deposit
as well as on the actual expenses, the award of compensation for loss of
Rs.47,75,000/- was not in order. In the circumstances, we modify that portion
of the Arbitral Tribunal's award and hold that the appellant is not entitled to
Rs.47,75,000/- as compensation for loss. The Arbitral Tribunal's Award dated
10.03.2021 is modified in the aforesaid terms and as a result, the order passed
under Section 34 of the Act also stands modified mutatis mutandis.
Consequently, the impugned order passed under Section 37 of the Act is
set-aside.
31. As the Arbitral Award was
passed as early as on 10.03.2012, we direct the respondent(s) to deposit/pay
the amount on or before 30.06.2025 without driving the appellant herein for
execution of the said Award. If the amount is not paid to the appellant on or
before 30.06.2025, the interest shall be at the rate of 12% per annum instead
of the reduced rate of 8% per annum.
32. The appeal is allowed and
disposed of in the aforesaid terms. No costs.
Civil Appeal No. 10490/2017:
We find no merit in this appeal. The
same stands dismissed. No costs.
------