This writ petition arose from a challenge to land acquisition notifications issued under the repealed Land Acquisition Act, 1894, for a 45-meter-wide road project in District Lucknow. The petitioner company sought to quash the Section 4(1) notification dated December 27, 2013, and the Section 6 declaration dated January 23, 2015, arguing that because all mandatory publications and public notices occurred after January 1, 2014—the date the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 came into force—the entire acquisition process was conducted under a repealed statute and was therefore ab initio void. The Lucknow Bench of the Allahabad High Court held that paper dates hold no legal weight and that land acquisition proceedings only legally initiate upon the completion of all mandatory public notices and Gazette publications. Because these prerequisites were fulfilled after the 1894 Act stood repealed, the initial proceedings were a nullity in the eyes of the law. However, balancing the public purpose of constructing a public road against the procedural illegality, the Court chose not to quash the acquisition entirely, opting instead to protect the petitioner’s rights by ordering a complete redetermination of compensation based on current market rates under the modern 2013 Act.
- Core Legal Question: The central issue before the Court was whether land acquisition proceedings under the Land Acquisition Act, 1894, had validly commenced prior to January 1, 2014, and whether notifications published after the repeal of the 1894 Act rendered the acquisition proceedings legally unsustainable.
- Paper Decisions vs. Actual Publication: The Court ruled that merely keeping a notification dated December 27, 2013, on file or bearing a retrospective date has no legal significance; an acquisition does not “initiate” until it is officially notified in the Gazette, newspapers, and announced via public notice in the locality.
- Mandatory Requirements under Section 4(1): Citing precedents such as Deepak Aggarwal and Raja Ram Jaiswal, the Court reiterated that the last date of publication of the Section 4(1) notice marks the true starting point of acquisition. Because all publications for the petitioner’s land occurred in January and February 2014—post-repeal—the proceedings lacked statutory backing under the old enactment and could not be saved by Section 24 of the 2013 Act or Section 6 of the General Clauses Act.
- Rejection of Delay Defense: The respondents argued that the petition suffered from laches since proceedings began in 2013/2014. The Court rejected this, noting that the fundamental illegality could not be cured by the passage of time, the 12-year delay in completing the road project was attributable to the authorities, and the petitioner remained in actual physical possession.
- Relief and Final Directions:
- The Court declined to entirely quash the acquisition proceedings because the land was designated for a public road.
- To remedy the severe prejudice caused to the landowner by applying a 2014 valuation under a repealed law, the Court ordered that compensation be redetermined and paid to the petitioner in accordance with the provisions and rates of the modern 2013 Act as of the date of the judgment.
- The authorities were directed to recalculate and pay the revised compensation within three months, prohibiting any dispossession of the petitioner until full payment is made, and mandating the completion of the acquisition process within six months.
J.O. (Web) 2026 ALL 133
Lohia Developers (India) Pvt. Ltd. v. State of U.P. and Others (D.O.J. 03.07.2026)
J.O. (Web) 2026 ALL 133 click here to view full text of judgment




