The dispute concerned the allotment of 2.9240 acres of land located in the Sitapur Industrial Area. H.P.C. intended to use this land for floriculture.
Allotment and Conditions: UPSIDC allotted the land to H.P.C. on 25 October 2002, after H.P.C. submitted an application and earnest money of Rs. 3,60,900/- on 15 October 2002. The allotment was conditional upon H.P.C.’s compliance with specific terms. These terms included:
Payment of approximately 10% of the total premium as initial earnest money.
The remaining 90% of the provisional premium to be paid in six equal half-yearly instalments, due on 1 January and 1 July each year, starting from 1 January 2003.
An interest rate of 13% per annum on the outstanding balance, with a 2% rebate for timely payments.
A critical condition: failure to make stipulated payments would lead to automatic cancellation of the allotment and forfeiture of the earnest money.
Defaults and Attempts at Resolution:
H.P.C. repeatedly defaulted on payments.
UPSIDC issued several notices between November 2003 and November 2005, demanding payment and warning of cancellation.
H.P.C. sought rescheduling of payments in December 2004, which UPSIDC approved in February 2005, allowing H.P.C. to pay Rs. 3,00,000/- in 10 instalments over 4 years with 12% interest.
Despite this, H.P.C. failed to pay the rescheduled instalments.
UPSIDC continued to demand the execution of the lease deed and possession of the land, even sending letters regarding demarcation and removal of alleged encroachments.
Cancellation: Due to H.P.C.’s continued non-compliance, UPSIDC issued a final notice in July 2006 and subsequently cancelled the allotment on 28 August 2006. UPSIDC noted that H.P.C. had only deposited the initial earnest money and no subsequent payments.
Law Involved
Conditional Allotment Terms: The core legal framework rested on the specific terms and conditions outlined in the allotment letter, particularly regarding payment schedules and the consequence of non-compliance, which included automatic cancellation and earnest money forfeiture.
Clause 6.5 of the UPSIDC Manual: This clause, which governs the procedure for addressing allottee defaults, was a key point of contention. It prescribes requirements for notifying defaulters.
Principles of Reciprocal Contractual Obligations: The High Court’s initial misinterpretation of Clause 6.5 touched upon the concept that performance by one party (payment by H.P.C.) might be contingent on performance by the other (demarcation/possession by UPSIDC).
Uttar Pradesh State Industrial Development Corporation Ltd. (Disposal of Land) Regulations, 1999: These regulations provide the legal basis for UPSIDC’s actions regarding land disposal.
Principles of Natural Justice: H.P.C. argued that the cancellation violated these principles, claiming it was arbitrary and lacked proper procedure.
Reasoning
High Court’s Erroneous Reasoning: The High Court initially ruled in favour of H.P.C., interpreting Clause 6.5 of the Manual as requiring UPSIDC to issue three legal notices to defaulters, which it believed UPSIDC failed to do. It also opined that physical possession and demarcation should have preceded demands for full payment, thereby suggesting a procedural flaw in the cancellation and disregard for reciprocal obligations.
Supreme Court’s Corrective Reasoning: The Supreme Court overturned the High Court’s decision, meticulously detailing H.P.C.’s continued failure to comply with payment obligations and the terms of allotment.
Persistent Default: The Court found that H.P.C. consistently failed to make payments as per the original and even the rescheduled plans, despite being granted extensions and assurances by UPSIDC. H.P.C. had only paid the earnest money and no other amounts.
Breach of Contract: The Supreme Court determined that H.P.C.’s actions constituted a clear breach of contract. The allotment was explicitly conditional, and non-compliance automatically triggered cancellation.
Rejection of Excuses: The Court dismissed H.P.C.’s arguments concerning non-demarcation and alleged encroachments as excuses for non-payment, noting that UPSIDC was ready to resolve these issues post-payment and that H.P.C. merely used them to delay the process. UPSIDC made it clear that possession would be handed over after the lease deed was executed and payments were made.
Procedural Adherence by UPSIDC: Contrary to the High Court’s finding, the Supreme Court noted that UPSIDC had, in fact, sent multiple communications and notices to H.P.C., including the final notice, giving them ample opportunity to comply. The cancellation was thus procedurally sound and in accordance with the law.
Misinterpretation of Clause 6.5: The Supreme Court clarified that the High Court’s interpretation of Clause 6.5 was erroneous. Clause 6.5 primarily relates to the delivery of possession after payment and registration of the lease deed, not as a precondition to payment demands.
Holding
The Supreme Court dismissed the appeals filed by H.P.C..
The cancellation of the land allotment by UPSIDC was upheld as justified and in accordance with the law.
While upholding the cancellation, the Supreme Court directed UPSIDC to refund any earnest money or payments received from H.P.C., along with interest.
The Court also issued a broader directive for the State Government of Uttar Pradesh and UPSIDC to ensure that future allotments of public resources are conducted with greater transparency and administrative accountability.
Kamla Nehru Memorial Trust And Another V. U.P.State Industrial Development Corporation Limited And Others
Supreme Court: 2025 INSC 791: (DoJ 30-05-2025)