This writ petition was filed by Smt. Urmil Makkar under Article 226 of the Constitution of India seeking directions to the Land Acquisition Collector (LAC) to forward her reference application dated February 3, 2025, to the Principal District Judge, South-West District, Dwarka Courts, New Delhi, for the adjudication and release of compensation. The subject land measuring 1 bigha situated in Village Pochanpur was originally notified for acquisition under the Land Acquisition Act, 1894, for the Dwarka Phase-II project. Although an award was passed in 2002, the acquisition proceedings were subsequently quashed by the High Court in 2015 because compensation had not been paid and the award was more than five years old. Following subsequent proceedings and a liberty granted by the Supreme Court allowing landowners to file compensation claims, the petitioner filed her reference application within the prescribed period. However, due to unexplained delays by the LAC in forwarding the application to the reference court, the petitioner approached the High Court.
- Fulfillment of Statutory Timelines: The Court noted that the petitioner’s reference application dated February 3, 2025, was filed well within the prescribed period authorized following the Supreme Court’s directives.
- No Justification for Delay: The bench held that there was no valid reason or justification for the LAC to keep the reference application pending.
- Direction to Transfer: The Court directed the LAC to officially send the reference application to the Principal District Judge, South-West District, Dwarka Courts, New Delhi, within a period of one month.
- Expeditious Adjudication: The Reference Court was instructed to adjudicate the petitioner’s application expeditiously.
- Accountability of Authorities: Expressing strong disapproval of administrative delays, the Division Bench directed the Office of the LAC to review all pending applications and forward them promptly, warning that the concerned officials would be held personally responsible for any future delays.