This enforcement petition under the Arbitration and Conciliation Act, 1996 was filed by Metso India Pvt. Ltd. (Decree Holder) against M/s McNally Bharat Engineering Co. Ltd. (Judgment Debtor) to execute the arbitral award dated May 5, 2018. Concurrently, the Judgment Debtor had challenged the same arbitral award under Section 34 of the Act in O.M.P. (COMM) 362/2018. During the pendency of these proceedings, the Judgment Debtor underwent Corporate Insolvency Resolution Process (CIRP), and a resolution plan was approved by the NCLT.
Given that the Decree Holder failed to lodge its claim before the Resolution Professional, the coordinate challenge petition (O.M.P. (COMM) 362/2018) was dismissed as infructuous on August 3, 2026, on the ground that the underlying debt stood extinguished under Section 31 of the Insolvency and Bankruptcy Code (IBC). Consequently, relying on that judgment, the High Court of Delhi dismissed the present enforcement petition as well, noting that no further orders were called for, and disposed of all pending execution applications.
- Factual Background and Enforcement Origin:
- The Decree Holder (Metso India Pvt. Ltd.) sought enforcement of the arbitral award dated May 5, 2018, secured against the Judgment Debtor (MBECL).
- Parallelly, the Judgment Debtor challenged the award under Section 34 of the Act in M.P. (COMM) 362/2018.
- Intervening Insolvency Developments:
- MBECL was admitted into CIRP, and a resolution plan was successfully approved by the NCLT.
- Because the Decree Holder did not submit its claim to the Resolution Professional during the insolvency process, the underlying arbitral claim stood extinguished by operation of law under Section 31 of the IBC.
- Court’s Analysis and Order:
- In the connected matter (M.P. (COMM) 362/2018), the High Court ruled that the unsubmitted claim was extinguished and the Section 34 petition was rendered infructuous.
- In view of the judgment passed in the connected matter on August 3, 2026, the court held that no further orders or execution steps could survive.
- The enforcement petition (OMP (ENF.) (COMM.) 270/2018) was accordingly dismissed, along with all pending applications.
2026 DHC 6219
Metso India Pvt. Ltd. v. M/s McNally Bharat Engineering Co. Ltd. (D.O.J. 03.08.2026)