Indian Judgements

Indian Judgements

Electricity: Indian Railway is Consumer, Not deemed distribution licensee

Whether the Indian Railways can be recognized as a deemed distribution licensee under the Electricity Act, 2003, and whether it is exempt from paying Cross-Subsidy Surcharge and Additional Surcharge when procuring power through open access for its own consumption.

Appeals dismissed. The Supreme Court upheld the Appellate Tribunal for Electricity (APTEL) order, ruling that the Indian Railways acts as a consumer because it utilizes the power entirely for captive self-consumption. It remains fully liable to pay the cross-subsidy and additional surcharges like any other open-access consumer.

Details

1. Factual Background

  • The Open Access Dispute: In March 2015, the Indian Railways (Appellant) sought connectivity from the Maharashtra State Electricity Transmission Co. Ltd. (MSETCL) to procure 100 MW of power via inter-state open access. MSETCL refused and directed the Railways to secure a clear order from the appropriate commission confirming its regulatory status.

PDF+ 1

  • Petition before CERC: The Railways petitioned the Central Electricity Regulatory Commission (CERC), pointing to a May 2014 advisory letter from the Ministry of Power which noted that the Railways qualifies as a deemed licensee under the third proviso to Section 14 of the Electricity Act, 2003. The Railways asserted that as a deemed distribution licensee (DDL), it had an absolute right to open access without paying any surcharges.
  • CERC and State Commission Rulings: On November 5, 2015, the CERC ruled in favor of the Railways, observing that Section 11(g) of the Railways Act, 1989 authorized it to establish distribution installations for its operations. However, when multiple distribution companies (DISCOMs) appealed, a split arose among various State Electricity Regulatory Commissions (SERCs)—five out of eight state regulators determined that the Railways was not a DDL under the law.

2. Lower Tribunal’s Ruling

The batch of cases was consolidated by the Appellate Tribunal for Electricity (APTEL). On February 12, 2024, APTEL issued its final judgment rejecting the Railways’ claim. APTEL held that because the Railways consumes 100% of the energy it receives for its own infrastructure, it cannot be considered a distributor. It ruled that the internal conveyance of power to locomotives and stations is simple self-consumption, making the Railways a consumer liable to pay standard open-access surcharges. The Railways appealed this decision to the Supreme Court.

3. Arguments Raised

  • On Behalf of the Appellant (Indian Railways): It was argued that Section 11 of the Railways Act is a complete code with a non-obstante clause that overrides the licensing structures of the Electricity Act. They maintained that since the Railways is a central government department, it satisfies the definition of an “Appropriate Government” and automatically assumes DDL status under Section 14. They argued that “distribution” simply means moving electricity from one point to another within their grid, and they should not be penalized with cross-subsidies intended for retail consumer networks.
  • On Behalf of the Respondents (DISCOMs & SERCs): The state regulators and power companies countered that under Section 2(19) of the Electricity Act, a “distribution system” requires a system of wires terminating at the installation of a distinct consumer. Because the Railways does not sell or retail electricity to external third-party consumers for a price, it fails the statutory test of a distributor. They warned that if the Railways—a massive high-revenue consumer—escapes paying surcharges, it would severely damage the financial health of state utilities and compromise their ability to provide heavily subsidized power to farmers and low-income households.

4. Key Legal Issues & Findings of the Supreme Court

A. The Functional Test of a Distribution Licensee

The Supreme Court held that under Sections 2(17) and 2(19) of the Electricity Act, 2003, distribution requires a two-pronged structural reality: operating a distribution system and supplying power to external consumers.

  • The Court noted that the term “distribution installation” in Section 11 of the Railways Act only permits the network to manage its internal engineering works.
  • Moving power across internal traction wires to move trains or light up stations is “conveyance for captive self-consumption,” not a commercial distribution or retail sale of electricity.
  • Unlike the Military Engineering Services (MES)—which serves as a DDL because it actually retails and bills electricity to separate residential and commercial premises inside cantonments—the Railways has no such client-base or trading relationship.

B. The Boundaries of “Appropriate Government”

The Court addressed whether being part of the Central Government automatically vests the Railways with a status exempt from normal distribution rules. Applying the functional test from Steel Authority of India Ltd. (SAIL), the Court held that while the administrative and fiscal identity of the Railways is completely tied to the Central Government, this nominal status cannot bypass the core actions required by the specific electricity statute. An entity cannot pick and choose a DDL status selectively to enjoy privileges (like avoiding surcharges) while explicitly refusing to take on the public retailing duties required of a licensee.

C. Sesa Sterlite and the Mandatory Nature of Surcharges

The Court reaffirmed the principles of Sesa Sterlite Ltd. v. OERC. It held that Cross-Subsidy Surcharges (CSS) and Additional Surcharges (AS) are crucial socioeconomic tools designed to protect the electricity grid’s overall financial balance. Even if an entity holds a legal fiction of being a licensee, if it utilizes the open-access network solely to purchase power for its own final consumption, it is categorized as a consumer under a functionality test and must pay the designated surcharges.

D. Use of the Draft Electricity (Amendment) Bill, 2025 as Interpretative History

The Court analyzed the ongoing legislative proposals regarding the power grid. It observed that the Draft Electricity (Amendment) Bill, 2025 explicitly includes provisions to progressively phase out and eliminate cross-subsidies for the Railways within five years.

  • Following Vodafone International Holdings, the Court ruled that the introduction of a new amendment to grant an exemption is clear proof that no such privilege exists under the current law.
  • If the existing 2003 Act already exempted the Railways, the new remedial legislative action would be redundant. Furthermore, as a government arm, the Railways cannot “approbate and reprobate”—it cannot claim a judicial exemption under current laws while the executive branch introduces new bills to create that exact exemption in the future.

5. Final Direction

The Supreme Court dismissed all the appeals and upheld APTEL’s common judgment. The interim protection against surcharge collections was vacated. The Respondent DISCOMs were directed to compute and issue detailed, disaggregated outstanding calculations for the Cross-Subsidy Surcharge and Additional Surcharge. The Indian Railways must be given a reasonable opportunity to verify these accounts and settle the outstanding amounts, subject to final oversight by the respective regulatory commissions. No order was made as to costs.

2026 INSC 464

Indian Railways V. West Bengal State Electricity Distribution Company Limited & Ors. (D.O.J. 08.05.2026)

2026 INSC 464 click here to view full text of judgment

Next Story

Admissibility of Deceased Witness Testimony Against Absconding Accused

Supreme Court allowed the appeals filed by the State of West Bengal, ruling that the deposition of a deceased witness recorded in an earlier trial is admissible in a subsequent trial against an absconding accused, provided the requirements of Section 299 of the Code of Criminal Procedure (CrPC) are met. The Court clarified that the provision serves to preserve evidence when an accused deliberately absconds, preventing them from benefiting from the unavailability of material witnesses due to the passage of time. The Court set aside the High Court’s order, which had denied the admission of the victim’s testimony, confirming that the statutory preconditions—the accused absconding and no immediate prospect of arrest—were satisfied at the time the witness deposed.

  • Background: In a 2012 gang-rape case, the respondent and another accused were absconding while three others were tried and convicted. The victim, a key witness, testified in the first trial but passed away in 2015. After the respondent was arrested in 2016, the prosecution sought to admit the victim’s earlier deposition as evidence under Section 33 of the Indian Evidence Act read with Section 299 of the CrPC.
  • High Court Order: The High Court of Calcutta had rejected the application, observing that the prosecution had a duty to obtain a specific direction from the Trial Court to record evidence against the absconder during the first trial, and thus the earlier deposition could not be used against the respondent.
  • Interpretation of Section 299 CrPC: The Supreme Court held that Section 299 CrPC acts as an exception to the general rule requiring a witness to be examined in the presence of the accused. It does not mandate a formal, prior order from a Magistrate to record that the accused is absconding; rather, what is relevant is whether the conditions—that the accused is absconding and there is no immediate prospect of arrest—were established at the time the evidence was recorded.
  • Preventing Misuse of Process: The Court reasoned that taking a restrictive view of Section 299 would jeopardize the criminal justice system by incentivizing accused persons to wilfully abscond and await the death or unavailability of material witnesses.
  • Application to Facts: The Court noted that the respondent was a declared absconder when the victim’s testimony was recorded (2013), and he remained at large until his arrest in 2016. As the two essential conditions of Section 299(1) were met, the deceased victim’s evidence is admissible in the trial against the respondent.

Legislative Continuity: The Court noted that the legislature has maintained this principle in Section 335 of the recently enacted Bharatiya Nagarik Suraksha Sanhita, 2023, reinforcing the intent to ensure evidence is preserved against those who evade trial.

2026 INSC 718

The State of West Bengal v. Kader Khan – (D.O.J. 17.07.2026)

2026 INSC 718 click here to view full text of judgment

Next Story

Insolvency and Bankruptcy: Finality of Resolution Plans and Extinguishment of Sub-judice Claims

Supreme Court allowed the appeals filed by the Successful Resolution Applicant (Appellant-SRA), ruling that upon the approval of a Resolution Plan under the Insolvency and Bankruptcy Code, 2016 (IBC), all claims—including those pending adjudication (sub-judice)—that are not specifically provided for in the plan stand extinguished. The Court held that the “clean slate” doctrine is fundamental to the IBC, preventing unresolved or contingent claims from resurfacing and undermining the revival of the corporate debtor. Consequently, the Court set aside the High Court orders and dismissed the civil suit and arbitration proceedings initiated by operational creditors, affirming that they are bound by the terms of the approved Resolution Plan.

  • Background: The Appellant-SRA challenged Bombay High Court orders that allowed a civil recovery suit and arbitration proceedings to continue against the corporate debtor (Bhushan Steel Limited) despite the approval of its Resolution Plan. The respondents, operational creditors, sought to pursue claims that were pending at the time of the Corporate Insolvency Resolution Process (CIRP).
  • Treatment of Claims: During the CIRP, the Resolution Professional admitted the respondents’ disputed claims at a notional value of Rupee One (1) each. The approved Resolution Plan stipulated that because the liquidation value was NIL, no amounts were due to operational creditors; however, a settlement fund was provided for those with admitted claims.
  • The “Clean Slate” Doctrine: The Court emphasized that a successful resolution applicant must start on a “clean slate,” free from “hydra-headed” surprise claims. Once a Resolution Plan is approved under Section 31(1) of the IBC, it becomes binding on all stakeholders, and claims not incorporated therein are deemed extinguished, withdrawn, or abated.
  • Finality of the Plan: The Court noted that the Final List of Creditors attained finality, and the respondents could not seek to reopen or question the commercial wisdom of the Committee of Creditors after the plan’s approval. The Court found no merit in the allegations of fraud, noting that no proceedings had been initiated under Rule 11 of the NCLT Rules to challenge the plan’s integrity.
  • No Express Carve-out: Upon a harmonious reading of the Resolution Plan, the Court concluded there was no express “carve-out” protecting sub-judice claims from extinguishment. The plan explicitly mandated that all legal proceedings relating to the period prior to the effective date stand extinguished, except to the extent of the specific settlement amount provided.
  • Observation on MSMEs: In an “Afterword,” the Court observed that the current insolvency framework does not adequately account for the position of small operational creditors and MSMEs, who are often placed at the bottom of the repayment waterfall. The Court suggested that the Legislature and Law Commission examine this to ensure a more balanced repayment mechanism.
  • Outcome: The Court allowed the appeals, set aside the contrary High Court orders, and dismissed the pending civil suit and arbitration proceedings, enforcing the finality of the Resolution Plan.

2026 INSC 717

M/S Tata Steel Ltd. v. Varsha & Anr. (D.O.J. 17.07.2026)

2026 INSC 717 click here to view full text of judgment

Next Story

Excluding Nominated Members from Local Authority Elections

The Supreme Court upheld the High Court of Karnataka’s decision to exclude nominated members of Town Panchayats from participating in Legislative Council elections for Local Authorities’ Constituencies. The Court ruled that under the constitutional framework established by the 74th Amendment (Part IX-A), nominated members, who serve only in an advisory capacity, lack the democratic mandate of elected representatives. Consequently, their inclusion in the electoral roll was declared unconstitutional, and the Court affirmed the direction to conduct a recount of votes after segregating the invalid votes cast by these nominated members.

  • Background: The election to the Karnataka Legislative Council (Chikkamagaluru Local Authorities Constituency) was challenged because 12 nominated members from four Town Panchayats were included in the electoral roll and participated in the voting. The appellant, who won by a narrow margin of 6 votes, contended that the electoral roll’s finality should be respected.
  • Constitutional Interpretation: The Court held that while Article 171(3)(a) mentions “members” of local authorities, this must be interpreted through the lens of the 74th Constitutional Amendment. Article 243-R establishes that while nominated members may be appointed for their expertise, they are expressly barred from voting in municipal meetings, underscoring their advisory rather than representative role.
  • Democratic Representation: The Supreme Court emphasized that allowing nominated members to vote in Legislative Council elections would undermine the democratic nature of the electoral process, as they are not democratically elected. The Court affirmed that “members” in the context of electoral colleges refers to democratically elected representatives.
  • Finality of Electoral Rolls: While acknowledging the principle that electoral rolls typically attain finality, the Court distinguished this case by noting that the inclusion of the nominated members was void ab initio and unconstitutional. Therefore, the finality of the roll could not be used to validate an illegality that strikes at the core of the electoral college’s composition.
  • Secrecy of the Ballot: The Court rejected the argument that segregating these votes would violate the secrecy of the ballot. It maintained that the higher constitutional goal of preserving free and fair elections and ensuring the purity of the electoral process outweighs the requirement for absolute secrecy in this specific context.
  • Outcome: The Supreme Court dismissed the appeals and affirmed the High Court’s orders. The Court directed the authorities to proceed with the consequential actions based on the recount results already obtained, ensuring that the election outcome reflects only the valid votes cast by elected representatives.

2026 INSC 716

Pranesh M.K. v. Shanthegowda & Ors. – (D.O.J. 16.07.2026)

2026 INSC 716 click here to view full text of judgment

Next Story

Railway: Establishing Liability in Untoward Railway Incidents

The Supreme Court set aside the concurrent dismissal of a compensation claim by the Railway Claims Tribunal and the High Court of Madhya Pradesh. The Court held that when a passenger dies in an “untoward incident” (falling from a running train), the absence of a recovered ticket does not automatically negate the status of a bona fide passenger. Emphasizing the “no-fault liability” principle under Section 124A of the Railways Act, 1989, the Court ruled that once the claimant establishes the foundational facts through an affidavit, the burden shifts to the Railways. Technical lapses and the inability to recover personal belongings should not defeat the humanitarian and welfare objectives of the legislation.

  • Background: The appellant filed a claim for compensation following the death of her husband, who fell from a running train while traveling from Raipur to Ahmedabad. The Railway Claims Tribunal and the High Court previously rejected the claim, citing a lack of proof regarding the deceased being a bona fide passenger (specifically due to the missing ticket).
  • Legal Principle (No-Fault Liability): The Court reiterated that Section 124A of the 1989 Act is a beneficial, “no-fault” provision. It is designed to provide expeditious relief to victims of untoward incidents without requiring proof of negligence by the Railway Administration.
  • Burden of Proof: Relying on Union of India v. Rina Devi and Doli Rani Saha v. Union of India, the Court clarified that:
    • The mere absence of a ticket does not disprove that a person was a bona fide
    • The initial burden is on the claimant, which is sufficiently discharged by filing an affidavit stating the facts.
    • Once this is done, the burden shifts to the Railways to disprove the claim based on attending circumstances.
  • Operational Concerns: The Court highlighted the critical issue of chronic overcrowding in Indian Railways. It noted that while the Railway Manuals contain detailed safety and ticketing protocols, the execution often fails. The Court suggested that Railways should increase manpower to better manage safety and ticketing, which could simultaneously reduce such tragedies and provide employment.
  • Constitutional Perspective: The Court observed that using terms like “second class passenger” is outdated and potentially offensive to the spirit of the Constitution of India; it suggested that class designations should refer to the “coach” rather than the “passenger.”

Decision: The Supreme Court allowed the appeal and set aside the lower court judgments. It ordered the Railways to pay compensation of ₹8,00,000 to the appellant within four weeks, failing which the amount would attract interest at 8% from the date of the original claim filing.

2026 INSC 715

Lata v. Union of India & Anr. – (D.O.J. 17.07.2026)

2026 INSC 715 click here to view full text of judgment

Hi Judgments Online