Indian Judgements

Indian Judgements

Arbitration Interest Dispute: When Contractual Silence Doesn’t Bar Justice

This appeal arose from a judgment and order of the Gauhati High Court dated 08.03.2019, which allowed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996.

The District Judge, Sivasagar, had previously allowed the judgment and order dated 15.11.2007 in Misc. Arb Case No.26 of 2005, under Section 34 of the 1996 Act, setting aside an arbitral award dated 21.11.2004.

The original arbitral award of 21.11.2004 passed a total amount of dollar 6,56,272.34 in favour of the claimant (M/S G & T BecKfield Drilling Services (P) Ltd) against the respondent (Oil & Natural Gas Corporation Ltd.).

The arbitral tribunal also awarded interest at 12% per annum from 12.12.1998 on the total amount and an award for interest on the said amount made accordingly.

Costs of Rs.5 lakhs were awarded to the claimant, while counter-claims were dismissed.

The appellant (ONGC) was aggrieved by the award because the agreement did not allow payment of interest on the claim (Clause 18.1).

The District Judge allowed the application and set aside the award on two grounds: (a) it was non-reasoned, and (b) it violated Section 31(3) of the 1996 Act; and (b) the objection under Section 16(2) was neither rejected nor considered by the arbitral tribunal at the time of making the final award.

The High Court set aside the District Judge’s order, but limited the interest extent to 12% per cent per annum and affirmed the arbitral award in toto. A notice was issued regarding the extent of interest, stating that the amount was subject to payment by the respondent within a period of four weeks.

Law Involved

Section 31(7) of the Arbitration and Conciliation Act, 1996, which deals with the power of an arbitral tribunal to award interest.

Section 31(7) has two clauses:

Clause (a) deals with interest for the period between the date on which the cause of action arose and the date on which the award is made. It states that the arbitral tribunal may include interest at such rate as it deems reasonable, on the whole or any part of the money. However, the arbitral tribunal’s power to award interest is subject to the agreement between the parties.

Clause (b) deals with interest post-award and mandates an 18% per annum rate if the award does not direct otherwise.

The crucial aspect was Clause 18.1 of the agreement, which stated: “Corporation agrees to arrange remittance of payment under this contract within 30 days from the date of receipt of invoice from contractor duly certified by the authorized representative of the Corporation subject always to Corporation’s right to require contractor to furnish it with satisfactory evidence of the validity and prior payment by Contractor of all labor and material incurred by Contractor and charged to Corporation. Should corporation question any item or items of an invoice, it may withhold payment of the amount in dispute until such matter is resolved between the parties, but the amount not in dispute is to be paid within above period. No interest shall be payable by ONGC on any delayed payment / disputed claim”.

Previous judgments such as State of Orissa v. G.C. Roy, Union of India v. Ambica Construction, Ambica Construction v. Union of India, Reliance Cellulose Products Limited v. Oil And Natural Gas Corporation, Sayeed Ahmed & Co. (supra), THDC First (supra), Jaiprakash Associates Ltd. (THDC Second), and Ferro Concrete Construction (India) Pvt. Ltd. v. State of Rajasthan, were referred to for interpreting the power to award interest, especially when there is a contractual bar.

Reasoning

The learned counsel for the appellant contended that Clause 18.1 prohibited payment of interest on any delayed or disputed claim, making the award of interest illegal.

The respondent argued that Clause 18.1 does not prohibit pendente lite interest, but rather the arbitral tribunal has discretion to award interest from the date the statement of claim is affirmed before it.

The Court observed that Clause 18.1 expressly states, “No interest shall be payable by ONGC on any delayed payment / disputed claim”.

The Court referenced previous judgments, particularly Sayeed Ahmed & Co. (supra), THDC First (supra), and THDC Second (supra), which established that if the agreement explicitly bars the grant of interest, the arbitral tribunal cannot award pendente lite interest.

The Supreme Court noted that where the agreement contains an express bar on interest, the tribunal lacks the power to grant interest for the pre-reference or pendente lite period.

The Court distinguished cases where the agreement is silent on interest from those where it explicitly prohibits it. If the agreement is silent, the tribunal can award interest. However, if the agreement stipulates that no interest is payable, the arbitral tribunal cannot award interest for the aforesaid period.

The Court found that Clause 18.1 constituted a clear and unambiguous bar on the payment of interest by ONGC on any delayed payment or disputed claim. Therefore, the arbitral tribunal, by awarding interest, had exceeded its jurisdiction because the agreement between the parties expressly prohibited the grant of pendente lite interest.

Holding

The Supreme Court found merit in the appeal.

The Court concluded that the arbitral tribunal erred in awarding pendente lite interest because Clause 18.1 of the agreement expressly barred such interest.

Consequently, the Supreme Court dismissed the appeal. This implies that the High Court’s decision to affirm the interest award in toto, despite the contractual bar, was overturned. The original setting aside of the interest award by the District Judge, based on the contractual prohibition, would effectively be upheld regarding the interest component.

The case was presided over by Justice Pamidighantam Sri Narasimha and Justice Manoj Misra. The judgment was delivered on September 02, 2025.

Oil And Natural Gas Corporation Ltd. Vs M/s G & T Beckfield Drilling Service Pvt. Ltd.

Supreme Court: 2025 INSC 1066: (DoJ 02-09-2025)

2025 INSC 1066 Download Supreme Court File

Next Story
Next Story

Delayed Death: When ‘Attempted Murder’ Becomes More

Maniklall Sahu, the appellant, along with three co-accused, trespassed into the house of Rekhchand Verma, assaulted him with sticks and fisticuffs, and flung him from a terrace. The injured person, Rekhchand Verma, initially survived but was in a critical condition. He eventually succumbed to his injuries approximately nine months after the incident, dying on 8th November 2022 due to septicaemia and pneumonia, leading to cardiorespiratory arrest. The trial court had initially convicted the appellant under Section 302 of the Indian Penal Code (IPC) for murder. However, the High Court altered this conviction to Section 307 IPC for attempt to murder, sentencing the appellant to 7 years of rigorous imprisonment and a fine of Rs. 1,000/-. The appellant subsequently filed this appeal challenging the Section 307 IPC conviction.

Law Involved The primary legal provisions under consideration are Sections 299, 300, 302, and 307 of the Indian Penal Code (IPC).

Section 307 IPC (Attempt to Murder): This section deals with acts done with the intention or knowledge that it might cause death, and if death occurs, the act would be murder.

Section 299 IPC (Culpable Homicide): Defines culpable homicide.

Section 300 IPC (Murder): Specifies when culpable homicide amounts to murder, including acts done with the intention of causing death, or causing bodily injury sufficient in the ordinary course of nature to cause death, or knowing the act is so imminently dangerous that it will most probably cause death.

Section 302 IPC (Punishment for Murder): Prescribes the punishment for murder. The core legal question revolves around the “Application of Theory of Causation where death ensues after some delay” and whether the High Court correctly applied Section 307 IPC despite the victim’s eventual death.

Reasoning The Supreme Court critically analysed the High Court’s decision to alter the conviction from Section 302 IPC to Section 307 IPC, especially given the victim’s death.

  1. Medical Evidence and Causation: The Court reviewed extensive medical evidence, which consistently showed that the deceased, Rekhchand Verma, suffered severe injuries, including a head injury, spinal cord injury leading to paraplegia, and multiple complications such as infected bedsores, septic shock, and bilateral pneumonia. Medical experts testified that these complications were a direct result of the initial injuries sustained during the assault and were sufficient in the ordinary course of nature to cause death. The Court highlighted that the injured person received medical treatment for nine months before his demise. The Court concluded that the injuries suffered were grievous and that the death was a consequence of these injuries, with complications like septicaemia and pneumonia not breaking the chain of causation.
  2. High Court’s Error: The Supreme Court determined that the High Court committed a serious error in bringing the case under the ambit of “attempt to commit murder” (Section 307 IPC) on the premise that the victim survived for about nine months, and his death was due to complications during treatment and not directly from the initial injuries. The Supreme Court stressed that if the injury was fatal and intended to cause death, or if death occurred after some delay due to septicaemia or other complications stemming from the injury, the offence would fall under the first limb of Section 300 IPC (murder) [36a]. Furthermore, if the injuries were sufficient in the ordinary course of nature to cause death and death occurred due to septicaemia or other complications, the act would amount to culpable homicide punishable under Section 302 IPC, falling under the third limb of Section 300 IPC [36b, 37c, 37d].
  3. Jurisprudence on Delayed Death: Drawing on various precedents, the Court reiterated that delayed death or intervening medical conditions (like septicaemia or pneumonia) do not automatically absolve an accused of murder charges if the initial injuries were the proximate cause of death. The Court concluded that the cause of death was indeed due to the injuries suffered, and the contention that the death resulted from a lack of proper treatment or was disconnected from the initial assault was unfounded.

Holding The Supreme Court dismissed Maniklall Sahu’s appeal . While the appellant’s conviction under Section 307 IPC (attempt to murder) as altered by the High Court stands affirmed due to the dismissal of his appeal, the Supreme Court clearly stated that the High Court committed a serious error in altering the conviction from Section 302 IPC to Section 307 IPC . The Supreme Court’s detailed reasoning underscored that given the medical evidence and the established chain of causation, the offence should have been considered murder or culpable homicide amounting to murder, punishable under Section 302 IPC, because the injuries were sufficient in the ordinary course of nature to cause death.

Maniklall Sahu Vs State of Chhattisgarh

Supreme Court: 2025 INSC 1107: (DoJ 12-09-2025)

2025 INSC 1107 Download Supreme Court File

Next Story

Tender Troubles: Supreme Court Upholds Bid Sanctity, Overturns Rectification

The case originated from an electronic bid (No. 7 of 2023-24) issued by the Superintending Engineer and Project Director, Project Implementation Unit – I, Public Works (Roads) Directorate, Government of West Bengal, on 17.10.2023. The tender was for collecting Road User Fee (RUF) from commercial vehicles for 1095 days. The earnest money deposit was fixed at Rs. 25,00,000.00. Seven bidders participated. The technical bids were evaluated, and four bidders were technically qualified, including Prakash Asphaltings and Toll Highways (India) Limited (appellant) and Mandeepa Enterprises (respondent No. 1).

Financial bids were opened on 08.12.2023. The appellant, Prakash Asphaltings, was found to be the highest bidder (H1) with a quoted amount of Rs. 91,19,00,000.00 for 1095 days. Respondent No. 1, Mandeepa Enterprises, was the lowest bidder (H4) with an offered amount of Rs. 9,72,999.00 per day.

Respondent No. 1 subsequently claimed a typographical error in their financial bid, stating they intended to quote Rs. 106,54,33,905.00 for the entire contract period instead of Rs. 9,72,999.00 per day. They requested the tendering authority to treat the figure of Rs. 9,72,999.00 as a typographical error and read it as Rs. 106,54,33,905.00. The tendering authority rejected this request on 20.12.2023, stating that correction of a financial bid after opening was not possible and would impeach the sanctity of the tender process.

Aggrieved, Respondent No. 1 filed a writ petition (WPA No. 29001 of 2023) before a Single Judge of the High Court, which was dismissed on 03.01.2024, as the Single Judge found no scope for interference. Respondent No. 1 then filed an intra-court appeal (MAT No. 93 of 2024). A Division Bench of the High Court allowed the appeal on 23.02.2024, observing that the error in quoting the figure by respondent No. 1 was inadvertent. The Division Bench directed the tendering authority to evaluate Respondent No. 1’s BOQ at Rs. 106,54,33,905.00 and offer other bidders the opportunity to match this figure. This civil appeal was directed against the Division Bench’s judgment and order.

Law Involved

Clause 4(g) of the Notice Inviting Electronic Bid: This clause specifically states that any change in the template of the Bill of Quantity (BOQ) will not be accepted under any circumstances.

Clause 5B(v) of the Instructions to Bidders: This clause outlines that during bid evaluation, if bidders fail to submit supporting documents or original hard copies within the stipulated timeframe, their proposals will be liable for rejection.

Article 226 of the Constitution of India: Pertains to the High Court’s jurisdiction to issue writs.

Principles of Equity and Natural Justice in Tender Processes: The judgment refers to the importance of these principles in tender and contract awards, but also emphasises that these principles should be kept at a distance when there is a violation of rules.

Judicial Review of Administrative Action: The Court reiterated that judicial review in administrative action, particularly tenders, is limited to preventing arbitrariness, irrationality, bias, and mala fides. Courts should not interfere with a decision unless it is “unlawful” or “unsound”.

Public Interest: Tenders are a cornerstone of governmental procurement processes, aiming for competitiveness, fairness, and transparency in resource allocation. Adherence to rules and conditions and the sanctity of the tender process are paramount.

Reasoning The Supreme Court reasoned that the Division Bench’s interpretation was erroneous for several key reasons:

Sanctity of Tender Process: The Court held that allowing rectification of financial bids after they have been opened would impeach the sanctity and integrity of the entire tender process.

Strict Adherence to Tender Conditions: Clause 4(g) explicitly prohibits any change in the BOQ template under any circumstances. The Division Bench’s broad interpretation of “bona fide mistake” to allow rectification was held to be incorrect and would put “shackles on the functioning of the tendering authority”.

Nature of the Mistake: While Respondent No. 1 claimed an inadvertent mistake, it was effectively a unilateral or systematic computer typographical transmission failure, not one attributable to the tendering authority. Such a mistake, even if unintentional, cannot be a ground to allow post-bid modifications that would undermine the competitive bidding process.

Adverse Consequences to Public Exchequer: The Division Bench’s decision to re-evaluate Respondent No. 1’s bid at a significantly higher amount (Rs. 106,54,33,905.00) meant that the appellant, who was originally the H1 bidder, would be displaced. This would lead to a considerable loss of revenue to the state exchequer (approximately 15 crores) by not accepting the higher bid of the appellant and giving an opportunity to Respondent No. 1 to correct its bid post-opening.

Limited Scope of Judicial Review: The Court reiterated that interference by a writ court in ongoing tender processes is not permissible unless there is a clear violation of principles of natural justice, or the decision is arbitrary or mala fide. The Division Bench’s decision was deemed a clear violation of natural justice principles.

Non-Joinder of Party: The appellant (Prakash Asphaltings), as the highest bidder and a directly affected party, was not made a party respondent in the intra-court appeal before the Division Bench, which was viewed as prejudicial and a violation of natural justice.

Holding The Supreme Court allowed the civil appeal, thereby setting aside and quashing the judgment and order dated 23.02.2024 passed by the Division Bench of the High Court at Calcutta in MAT No. 93 of 2024. The Court sustained the order of the learned Single Judge dismissing the writ petition. Consequently, Prakash Asphaltings and Toll Highways (India) Limited (the appellant), being the H1 bidder, is to be awarded the contract in terms of the notice inviting electronic bid dated 17.10.2023. The Court also ruled that there shall be no order as to costs.

Prakash Asphaltings And Toll Highways (India) Limited Vs Mandeep Enterprises And Others

Supreme Court: 2025 INSC 1108: (DoJ 12-09-2025)

2025 INSC 1108 Download Supreme Court File

Next Story

“Speculative Investors” Barred from IBC Relief: Supreme Court Upholds Homebuyer Protections

Four appeals were heard together, arising from orders of the National Company Law Appellate Tribunal (NCLAT). The key appellants, Mansi Brar Fernandes and Sunita Agarwal, had entered into agreements with developers (Gayatri Infra Planner Pvt. Ltd. and Antriksh Infratech Pvt. Ltd., respectively) for property units. Both agreements included buy-back clauses and involved advance payments. The developers defaulted, and the appellants initiated proceedings under Section 7 of the Insolvency and Bankruptcy Code (IBC). The NCLAT reversed the admission of these applications, branding the appellants as “speculative investors” rather than genuine homebuyers or financial creditors.

Law Involved: The central legal framework is the Insolvency and Bankruptcy Code, 2016 (IBC), specifically Section 7, which governs the initiation of the Corporate Insolvency Resolution Process (CIRP) by financial creditors. The Insolvency and Bankruptcy Code (Amendment) Ordinance, 2019, and the subsequent Amendment Act, are also critical. These amendments introduced a threshold requirement for allottees to file a Section 7 application (requiring at least 10% of allottees or 100 allottees). The Court frequently referenced its earlier judgment in Pioneer Urban Land and Infrastructure Ltd v. Union of India, which distinguishes between genuine homebuyers and speculative investors. The judgment also emphasizes the Right to Shelter as a fundamental right under Article 21 of the Constitution and the role of the Real Estate (Regulation and Development) Act, 2016 (RERA).

Reasoning: The Supreme Court deliberated on the distinction between “speculative investors” and “genuine homebuyers” within the context of the IBC. It observed that the IBC is intended as a collective mechanism to revive viable projects and safeguard the fundamental right to shelter of genuine homebuyers, not as a recovery tool or a bargaining chip for individuals. The legislative intent behind recognizing allottees as financial creditors was to protect genuine homebuyers, while simultaneously preventing misuse by speculative investors seeking premature exits or exorbitant returns, which had burdened the real estate sector and the adjudicatory machinery.

The Court provided criteria to identify speculative investors, including: agreements that substitute possession with buy-back or refund options, insistence on refunds with high interest, purchase of multiple units (especially in double digits), demanding special rights or privileges, deviations from the RERA Model Agreement, and unrealistic interest rates or promises of returns. The transaction entered into by Mansi Brar Fernandes, involving a buy-back clause and the pursuit of commercial returns rather than possession, led the Court to conclude that she was indeed a speculative investor. Similarly, Sunita Agarwal’s agreement for an “investment” with a 25% per annum return over 24 months, coupled with a buy-back clause, indicated a speculative intent.

While affirming the NCLAT’s finding that the appellants were “speculative investors,” the Supreme Court clarified that the Insolvency and Bankruptcy Code (Amendment) Ordinance, 2019, was indeed applicable to the facts of the present case, correcting the NCLAT’s reasoning on this point [19, 20, 35, 36, 48(ii)]. The Court applied the doctrine of Actus Curiae Neminem Gravabit (an act of the Court shall prejudice no one) to address the procedural issues related to the Ordinance’s applicability and the delay it caused.

Holding: The Supreme Court affirmed the NCLAT’s findings that Mansi Brar Fernandes and Sunita Agarwal were “speculative investors” and therefore not entitled to initiate proceedings under Section 7 of the IBC [25, 34, 48(i)]. Consequently, the Court upheld the NCLAT’s orders setting aside the admission of their Section 7 applications by the NCLT [48(i)]. However, the Court clarified that the Ordinance/Amendment Act was applicable to the case, although this correction in reasoning did not alter the ultimate outcome given the appellants’ status as speculative investors [48(ii)]. The appellants remain free to pursue their remedies through other appropriate legal forums, without being barred by limitation [48(i)].

Mansi Brar Fernandes Vs Subha Sharma And Anr.

Supreme Court: 2025 INSC 1110: (DoJ 12-09-2025)

2025 INSC 1110 Download Supreme Court File

Hi Judgments Online