This judgment arises from a consumer dispute over the cancellation of a flat allotted by the Delhi Development Authority (DDA) under the Expandable Housing Scheme, 1996, where the Supreme Court considered whether a revision petition before the National Commission should be allowed to proceed despite a delay. Holding that “sufficient cause” should be interpreted pragmatically and cumulatively to advance substantial justice—especially after excluding the COVID-19 limitation period and where earlier forums reached conflicting views—the Court set aside the orders of the High Court and the National Commission. Consequently, the delay was condoned and the revision petition was restored to the National Commission for decision on its merits.
- Background of the Dispute: Smt. Bachhi Devi (predecessor-in-interest of the respondents) was allotted Flat No. 286, Sector B-4, Pocket 6, Narela, Delhi, following a draw of lots on 21.03.1997 under DDA’s Expandable Housing Scheme, 1996. DDA issued demand-cum-allotment letters between 12.01.2000 and 20.01.2000 and later cancelled the allotment on 20.10.2003 for non-payment after issuing a show cause notice on 09.08.2001, while the allottee maintained she did not receive the demand letter.
- Earlier Consumer Proceedings: The District Forum dismissed the allottee’s consumer complaint on 11.08.2015, finding that the demand letter had been sent to the correspondence address provided and cancellation was justified. On 09.04.2021, the State Commission allowed the appeal, holding that the demand-cum-allotment letter was not duly served and directing DDA to allot an alternative flat at original allotment rates.
- Refusal to Condone Delay & High Court Order: DDA filed Revision Petition No. 1621 of 2022 before the National Commission on 02.12.2022 with a reported delay of 512 days, attributing the remaining 95-day delay (after COVID-19 limitation exclusions) to administrative procedures, change of counsel, and obtaining a certified copy. The National Commission declined to condone the delay on 07.06.2024, and the High Court dismissed DDA’s Article 227 challenge on 23.10.2024 for lack of due diligence.
- Supreme Court’s Reasoning: Relying on established precedents (Collector, Land Acquisition, Anantnag v. Mst. Katiji and N. Balakrishnan v. M. Krishnamurthy) as well as the COVID-19 limitation exclusion order (Suo Motu Writ Petition (Civil) No. 3 of 2020), the Court observed that internal administrative steps and counsel changes must be viewed cumulatively rather than in isolation. Finding no deliberate delay or intent to gain undue advantage—and noting the divergent conclusions of the District Forum and State Commission—the Court held that the National Commission and High Court took an overly restrictive approach.
- Final Decision: The appeal was allowed, the orders of the High Court (23.10.2024) and the National Commission (07.06.2024) were set aside, the delay was condoned, and Revision Petition No. 1621 of 2022 was restored to the National Commission for hearing and disposal on merits with all contentions left open.
2026 INSC 1254
Delhi Development Authority vs. Sudarshan Manjhi & Ors. (D.O.J. 20.11.2026)