The Supreme Court of India held that Power Grid Corporation of India Limited (PGCIL) was entitled to recover transmission tariff on a non-PoC basis for two Line-In Line-Out (LILO) assets commissioned in January 2015 up to 27.10.2016, when the generating company commissioned its Dedicated Transmission Line (DTL). Setting aside the Appellate Tribunal for Electricity (APTEL) orders, the Court restored the Central Electricity Regulatory Commission (CERC) order and ruled that delay in upstream lines to Salem and Madhugiri did not negate actual evacuation and use of the LILOs while the generator delayed its DTL.
Background and Procedural History
- The dispute involved PGCIL’s tariff claim for two LILOs on both circuits of the Tuticorin JV–Madurai 400 kV D/C (Quad) transmission line at the Tuticorin Pooling Station, commissioned on 04.01.2015 and 08.01.2015, for the period up to 27.10.2016 when the generating company (Moxie Power Generation Ltd., formerly Coastal Energen Pvt. Ltd.) commissioned its DTL directly to the Tuticorin Pooling Station.
- Under the 24.02.2010 Bulk Power Transmission Agreement (BPTA) (amended 08.09.2011) and Standing Committee on Power System Planning in Southern Region (SCPSPSR) meetings, the generator was to build its DTL to the Tuticorin Pooling Station, while PGCIL was to establish the Tuticorin Pooling Station and LILOs of both circuits of the Tuticorin JV–Madurai line (Part-A) and upstream lines toward Salem and Madhugiri (Part-B).
- Power generation commenced on 23.12.2014 and was evacuated through a temporary LILO on the Tuticorin JV–Madurai line and supplied to distribution licensee TANGEDCO.
- By order dated 29.07.2016, the CERC accepted the Commercial Operation Dates (CODs) of 04.01.2015 and 08.01.2015 and directed liability for the LILO transmission charges on the generating companies (including Coastal Energen) until their DTL became commercially operational, while declining to condone time over-run at that stage subject to truing-up.
- APTEL overturned the CERC’s view on usage and COD (and on review remanded the COD issue), holding that the LILOs had no “beneficial use” before the upstream Salem–Madhugiri lines were operationalized and that Regulation 4(3)(ii) of the CERC Tariff Regulations, 2014 required redetermination/review of COD. PGCIL appealed to the Supreme Court.
Key Issues
- Whether PGCIL was entitled to transmission tariff (on a non-PoC basis) for the two LILOs from 04.01.2015/08.01.2015 until 27.10.2016, given their inclusion in the BPTA and statutory planning under Section 29(4) of the Electricity Act, 2003.
- Whether APTEL correctly interpreted Regulation 4(3)(ii) of the Tariff Regulations, 2014 in directing CERC to revisit the already-approved COD of the LILOs.
- Whether the generator’s delay in constructing its DTL warranted placing liability on the generating company for the period between commissioning of the LILOs and commissioning of the DTL on 27.10.2016.
Legal Analysis and Ruling
- Actual Use and Evacuation Through Pooling Station: Examining the evacuation arrangement and the generator’s own pleadings before APTEL, the Court found that power evacuated via the Tuticorin JV–Madurai line was routed through the LILOs and Tuticorin Pooling Station for onward transmission and supply to TANGEDCO. Delay in the upstream Tuticorin–Salem–Madhugiri transmission line did not prevent evacuation or use of the LILOs during the disputed period.
- Statutory Scheme, DTL Obligation, and COD: Under Section 10 of the Electricity Act, 2003, constructing the DTL was the generating company’s duty. Under Regulation 3(53) and Regulation 4 of the Tariff Regulations, 2014, COD was validly accepted by CERC based on RLDC trial operation certification, CEA safety certification, and scheme approvals, and Regulation 4(3)(ii) did not require reopening COD where regular service of the LILOs was not prevented.
- CERC’s Regulatory and Adjudicatory Powers: Relying on PGCIL v. Madhya Pradesh Power Transmission Co. Ltd., PTC India Ltd. v. CERC, and Energy Watchdog v. CERC, the Court held that CERC’s imposition of liability on the defaulting generator for the period prior to DTL commissioning (up to 27.10.2016) was valid and within jurisdiction.
- Reading of CERC Order: The Court noted that paragraph 72 of CERC’s order recorded TANGEDCO’s submission rather than CERC’s final finding, whereas paragraphs 73–77 placed liability on the generating company based on the 30th SCM and BPTA framework.
Disposition
- The Supreme Court answered the questions of law in favour of PGCIL, set aside the impugned APTEL orders in the appeals, restored the CERC order, allowed the appeals, and disposed of pending applications.
2026 INSC 1237
Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. (D.O.J. 18.11.2026)