Indian Judgements

Indian Judgements

Reversing Acquittal on Uncorroborated Dying Declaration Impermissible: SC Sets Aside Life Sentence

The Supreme Court allowed the criminal appeal filed by the appellant (mother-in-law) challenging the Bombay High Court’s judgment that had reversed her acquittal by the Sessions Court and convicted her under Section 302 of the Indian Penal Code, 1860 (IPC) for the murder of her daughter-in-law, sentencing her to rigorous imprisonment for life. The Supreme Court held that the High Court erred in accepting a single, uncorroborated dying declaration while discarding two other inconsistent dying declarations and failing to examine a crucial material witness (the first responder/police patil). The Court further ruled that convicting the appellant alone of murder under Section 302 of the IPC—when the original charge was framed jointly against all family members under Section 302 read with Section 34 of the IPC, and co-accused were acquitted—amounted to making out a new case against the appellant without an independent charge, and that Section 106 of the Evidence Act cannot relieve the prosecution of its initial burden of proof. Consequently, the Supreme Court set aside the High Court’s judgment and restored the appellant’s acquittal.

1. Factual Background & Sessions Court Trial

  • The Incident: On 10.04.2005, the victim Sunitabai suffered severe burn injuries (approx. 90%–94%) at her matrimonial home and succumbed to her injuries on 15.04.2005 due to septicemia.
  • Charges: The victim’s husband, father-in-law, mother-in-law (appellant), and brother-in-law were prosecuted and charged under Sections 498A, 342, 406, and 302 read with Section 34 of the IPC for dowry harassment and joint murder.
  • Sessions Court Verdict: The Sessions Court acquitted all the accused of all charges, noting material inconsistencies among the three recorded dying declarations, failure of the prosecution to examine key witnesses (like the neighbor/first responder Vishwas Desle/Patil), and lack of evidence regarding seized items like ropes.

2. High Court Reversal

  • On an appeal by the State, the High Court upheld the acquittal of the other co-accused and the charges under Sections 498A, 342, and 406, but reversed the acquittal of the appellant (mother-in-law, aged 60) for the substantive offence under Section 302 of the IPC.
  • The High Court discarded two dying declarations (Exhibits 44 and 48) but accepted a third dying declaration recorded in the medico-legal case papers (Exhibit 56) by relying on the defense statement that the appellant was alone with the victim inside the house.

3. Supreme Court’s Legal Findings & Analysis

  • Defect in Framing of Charges & Constructive Liability:
    • The appellant was originally charged along with others under Section 302 read with Section 34 of the IPC (common intention), with no separate, independent charge under Section 302 simpliciter.
    • Citing the Constitution Bench precedent in Krishna Govind Patil v. State of Maharashtra, the Supreme Court held that when co-accused charged under Section 34 are acquitted, convicting a single accused under the substantive provision without an independent charge creates a legally impossible position and makes out a new case for the prosecution that prejudices the accused.
  • Inconsistent Dying Declarations and Lack of Corroboration:
    • Applying established principles for multiple dying declarations (as outlined in Abhishek Sharma v. State), the Court noted that when multiple statements are inconsistent, the accepted statement requires reliable independent corroboration.
    • The prosecution failed to examine Vishwas Desle (also known as Vishwas Patil), the Police Patil who was the first person to reach the spot, extinguish the fire, and admit the victim to the hospital. His non-examination created a major gap in corroborating Exhibit 56 in the face of 94% burn injuries.
  • Misapplication of Section 106 of the Evidence Act:
    • The High Court improperly shifted the burden onto the appellant simply because she was present at home. The Supreme Court reiterated that Section 106 cannot be invoked to make up for the prosecution’s failure to discharge its initial burden of proof, and the onus does not shift until a prima facie case is established.
  • Procedural Flaw on Sentence Hearing:
    • The Supreme Court also noted that the High Court violated Section 386(a) of the Code of Criminal Procedure by failing to afford the appellant an opportunity of being heard on the quantum of sentence upon reversing her acquittal.

4. Final Outcome

  • The Supreme Court concluded that the view taken by the Sessions Court was a possible, plausible view, and the presumption of innocence in favor of the appellant was strengthened by her acquittal.
  • The appeal was allowed, the High Court’s judgment dated 28.09.2017 was quashed, and the appellant was acquitted of the offence under Section 302 of the IPC, with directions to set her free forthwith.

2026 INSC 1196

Sau. Kamalbai Waman Patil v. The State of Maharashtra (D.O.J. 05.11.2026)

2026 INSC 1196 click here to view full text of judgment

Next Story

Limits on Section 37 Court Modifying Arbitral Awards

The Supreme Court of India held that a Division Bench exercising narrow jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, could not modify an arbitral award to 50% and reduce interest to 6% merely because additional work claims exceeded 70% of the original contract value and “shocked the conscience” of the Court. Setting aside the impugned Section 37 judgment, the Court restored the arbitral award dated 03.11.2003 in full.

Background and Procedural History

  • The contractor was entrusted with dredging/evacuation work for the approach channel and basin of a shore-based pilot station at Sagar Island, completed by 17.04.2001 when inaugurated by the Chairman of the Port Trust of Calcutta, despite delay due to force majeure conditions.
  • Additional dredging work became necessary due to force majeure weather, soil-data mismatch, siltation, and lack of protective walls, reflected in the Port Trust’s letter dated 19.07.2000.
  • An arbitral award was passed on 03.11.2003 regarding the additional work, which was affirmed under Section 34 of the Arbitration and Conciliation Act, 1996, by a Single Judge.
  • On the awarder’s appeal under Section 37, a Division Bench of the High Court of Calcutta recorded that the award was not based on “no evidence” or “insufficient evidence,” nor perverse, patently illegal, or contrary to the fundamental policy of Indian law, yet modified it to 50% of the quantified amount with 6% interest from 08.02.2002 because additional work claims exceeded 70% of the original contract value.
  • Cross-appeals were filed before the Supreme Court by the contractor (seeking restoration of the award) and the Port Trust (seeking complete setting aside or, alternatively, upholding the modified award).

Key Issues

  • Whether the High Court Division Bench acted within its Section 37 jurisdiction in modifying the arbitral award based on the quantum of additional work exceeding 70% of the original contract and “shocking the conscience” of the Court.
  • Whether the absence of a formal completion certificate or the public/government status of the awarder justified interference or partial severance.

Legal Analysis and Ruling

  • Narrow Scope Under Section 37: Relying on Ssangyong Engineering & Construction Co. Ltd. v. NHAI and Somdatt Builders-NCC-NEC (JV) v. NHAI, the Court held that “shocking the conscience” or conflict with basic notions of morality or justice requires substantive, blatant grounds—not mere invocation of phrases because additional work exceeded 70% of the original contract or re-adjudication of evidence/merits.
  • Evidentiary Basis and Non-Issuance of Completion Certificate: The Arbitrator relied on measurements and invoices for additional re-dredging work, and non-issuance of a completion certificate by the Port Trust did not bar recovery for work actually executed. Batliboi Environmental Engineers Ltd. v. HPCL was distinguished as concerning damages rather than valid invoices for additional work.
  • No Special Treatment for State Entities & Inseparability: Under Pam Developments Private Ltd. v. State of West Bengal, parties in arbitration must be treated equally without special leniency merely because the award debtor is a government/statutory entity. Under Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited, the invoices and measurements for additional dredging formed a single integrated character and could not be arbitrarily halved.

Disposition

  • The Supreme Court set aside the impugned Section 37 judgment, allowed the contractor’s appeal, restored the arbitral award, disposed of the Port Trust’s appeal, and disposed of pending applications.

2026 INSC 1238

M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata (D.O.J 18.11.2026)

2026 INSC 1238 click here to vbiew full text of judgment

Next Story

Transmission Tariff Liability for LILO Lines Before DTL

The Supreme Court of India held that Power Grid Corporation of India Limited (PGCIL) was entitled to recover transmission tariff on a non-PoC basis for two Line-In Line-Out (LILO) assets commissioned in January 2015 up to 27.10.2016, when the generating company commissioned its Dedicated Transmission Line (DTL). Setting aside the Appellate Tribunal for Electricity (APTEL) orders, the Court restored the Central Electricity Regulatory Commission (CERC) order and ruled that delay in upstream lines to Salem and Madhugiri did not negate actual evacuation and use of the LILOs while the generator delayed its DTL.

Background and Procedural History

  • The dispute involved PGCIL’s tariff claim for two LILOs on both circuits of the Tuticorin JV–Madurai 400 kV D/C (Quad) transmission line at the Tuticorin Pooling Station, commissioned on 04.01.2015 and 08.01.2015, for the period up to 27.10.2016 when the generating company (Moxie Power Generation Ltd., formerly Coastal Energen Pvt. Ltd.) commissioned its DTL directly to the Tuticorin Pooling Station.
  • Under the 24.02.2010 Bulk Power Transmission Agreement (BPTA) (amended 08.09.2011) and Standing Committee on Power System Planning in Southern Region (SCPSPSR) meetings, the generator was to build its DTL to the Tuticorin Pooling Station, while PGCIL was to establish the Tuticorin Pooling Station and LILOs of both circuits of the Tuticorin JV–Madurai line (Part-A) and upstream lines toward Salem and Madhugiri (Part-B).
  • Power generation commenced on 23.12.2014 and was evacuated through a temporary LILO on the Tuticorin JV–Madurai line and supplied to distribution licensee TANGEDCO.
  • By order dated 29.07.2016, the CERC accepted the Commercial Operation Dates (CODs) of 04.01.2015 and 08.01.2015 and directed liability for the LILO transmission charges on the generating companies (including Coastal Energen) until their DTL became commercially operational, while declining to condone time over-run at that stage subject to truing-up.
  • APTEL overturned the CERC’s view on usage and COD (and on review remanded the COD issue), holding that the LILOs had no “beneficial use” before the upstream Salem–Madhugiri lines were operationalized and that Regulation 4(3)(ii) of the CERC Tariff Regulations, 2014 required redetermination/review of COD. PGCIL appealed to the Supreme Court.

Key Issues

  • Whether PGCIL was entitled to transmission tariff (on a non-PoC basis) for the two LILOs from 04.01.2015/08.01.2015 until 27.10.2016, given their inclusion in the BPTA and statutory planning under Section 29(4) of the Electricity Act, 2003.
  • Whether APTEL correctly interpreted Regulation 4(3)(ii) of the Tariff Regulations, 2014 in directing CERC to revisit the already-approved COD of the LILOs.
  • Whether the generator’s delay in constructing its DTL warranted placing liability on the generating company for the period between commissioning of the LILOs and commissioning of the DTL on 27.10.2016.

Legal Analysis and Ruling

  • Actual Use and Evacuation Through Pooling Station: Examining the evacuation arrangement and the generator’s own pleadings before APTEL, the Court found that power evacuated via the Tuticorin JV–Madurai line was routed through the LILOs and Tuticorin Pooling Station for onward transmission and supply to TANGEDCO. Delay in the upstream Tuticorin–Salem–Madhugiri transmission line did not prevent evacuation or use of the LILOs during the disputed period.
  • Statutory Scheme, DTL Obligation, and COD: Under Section 10 of the Electricity Act, 2003, constructing the DTL was the generating company’s duty. Under Regulation 3(53) and Regulation 4 of the Tariff Regulations, 2014, COD was validly accepted by CERC based on RLDC trial operation certification, CEA safety certification, and scheme approvals, and Regulation 4(3)(ii) did not require reopening COD where regular service of the LILOs was not prevented.
  • CERC’s Regulatory and Adjudicatory Powers: Relying on PGCIL v. Madhya Pradesh Power Transmission Co. Ltd., PTC India Ltd. v. CERC, and Energy Watchdog v. CERC, the Court held that CERC’s imposition of liability on the defaulting generator for the period prior to DTL commissioning (up to 27.10.2016) was valid and within jurisdiction.
  • Reading of CERC Order: The Court noted that paragraph 72 of CERC’s order recorded TANGEDCO’s submission rather than CERC’s final finding, whereas paragraphs 73–77 placed liability on the generating company based on the 30th SCM and BPTA framework.

Disposition

  • The Supreme Court answered the questions of law in favour of PGCIL, set aside the impugned APTEL orders in the appeals, restored the CERC order, allowed the appeals, and disposed of pending applications.

2026 INSC 1237

Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors. (D.O.J. 18.11.2026)

2026 INSC 1237 click here to view full text of judgment

Next Story

Grandson’s Birth Right in Father’s Partitioned Property

The Supreme Court of India held that property inherited by a Hindu male as a Class I heir under Section 8 of the Hindu Succession Act, 1956, and allotted to him in a partition among Class I heirs, becomes his exclusive individual property rather than joint family or coparcenary property vis-à-vis his own son. Consequently, a grandson born after the grandfather’s death has no birth right to seek partition of his living father’s share.

Background and Procedural History

  • The appellant, a minor represented by his mother and natural guardian, filed Original Suit No. 1698 of 1997 seeking partition and possession of a half share in 1,811 sq. ft. of land, pleading that it was joint family property of his grandfather, late N. Ramakrishnan, inherited along with his father (first defendant).
  • The first defendant’s sister, G. Lalitha, had filed partition suit C.S. No. 1728 of 1993 regarding N. Ramakrishnan’s property, resulting in a compromise decree dated 03.02.1994 under which the first defendant received 1,811 sq. ft. of land.
  • The appellant was born on 06.01.1994, after the 1993 suit was filed and before the 03.02.1994 compromise decree.
  • The first defendant executed sale deeds on 03.04.1997 and 17.04.1997 in favour of defendant nos. 2 and 3, who contested the suit claiming absolute ownership under the compromise decree and bona fide purchase. The appellant’s suit did not challenge the compromise decree or the sale deeds.
  • The Trial Court granted a preliminary decree for partition, which the First Appellate Court (High Court) set aside on 11.08.2010, holding that under Section 8 of the Hindu Succession Act, 1956, the first defendant took his share as an absolute owner and the appellant acquired no right by birth. The appellant appealed to the Supreme Court.

Key Issue

  • Whether the appellant could claim a half share and seek partition by birth in land allotted to his still-living father upon partition of property originally belonging to the appellant’s grandfather.

Legal Analysis and Ruling

  • Succession Under Section 8 of the Hindu Succession Act, 1956: Following CWT v. Chander Sen, Yudhisthir v. Ashok Kumar, and Radha Bai v. Ram Narayan, the Court reiterated that under Section 8, a male Hindu’s property devolves upon Class I heirs to the exclusion of others. A living son’s son (grandson) is excluded from Class I heirs, and a son inheriting property under Section 8 takes it in his individual capacity rather than as karta of his own Hindu Undivided Family vis-à-vis his son.
  • Effect of Partition and Tenancy in Common: Upon N. Ramakrishnan’s death prior to the 1993 suit, Class I heirs succeeded as tenants in common rather than joint tenants, and the compromise decree dated 03.02.1994 allotted exclusive shares to the heirs, ending joint coparcenary character in the allotted share.
  • Inapplicability of Pre-2005 Section 6 and Tamil Nadu Amendment (Section 29-A): Unamended Section 6 and Section 29-A inserted by the Hindu Succession (Tamil Nadu Amendment) Act, 1989 did not apply on the facts, as succession had opened upon N. Ramakrishnan’s death before the appellant was born, and the appellant was not a surviving coparcener at his grandfather’s death. Once the property became the first respondent’s exclusive individual property after partition, the appellant could not claim coparcenary rights by birth during his father’s lifetime.

Disposition

  • The Supreme Court dismissed the appeal with no order as to costs and disposed of pending applications.

2026 INSC 1208

J. Rajesh (Minor) Thr. His Mother and Natural Guardian J. Gomathi v. M. Kumaran (Dead) Thr. LRs. & Ors. (D.O.J. 06.11.2026)

2026 INSC 1208 click here to view full text of judgment

Next Story

Balance Sheet Entries and Limitation in Civil Recovery Suits

The Supreme Court of India held that continuous reflection of unpaid dues in a defendant’s balance sheets can constitute a valid acknowledgment of liability under Section 18 of the Limitation Act, 1963, renewing limitation and preventing threshold rejection of a plaint under Order VII Rule 11 of the Code of Civil Procedure, 1908 (CPC). Setting aside the High Court’s order that had rejected the plaint as time-barred, the Court restored the recovery suit for trial while leaving all substantive merits open.

Background and Procedural History

  • The original plaintiff, Wazir Hussain, entered into a civil works contract dated 10.02.2000 with the respondent-society for construction work on a multi-story building in Mayur Vihar, Delhi, raising running bills between 2000 and 2003.
  • In 2014, he filed a suit under Order XXXVII CPC seeking recovery of Rs. 11,16,000/- along with Rs. 11,04,840/- interest (at 9% p.a.) and further interest until realization.
  • The defendant-society sought rejection of the plaint under Order VII Rule 11 CPC on grounds including limitation, absence of a cause of action, and non-maintainability over alleged embezzlement.
  • On 06.01.2020, the Trial Court dismissed the rejection application, holding that entries in the defendant’s balance sheets from 2004–2005 up to 2013 amounted to acknowledgment of debt starting fresh limitation periods, while leaving maintainability and bill genuineness for trial.
  • On 04.11.2024, the High Court of Delhi allowed the defendant’s revision petition and rejected the plaint as barred by limitation, finding that the bank statements did not establish acknowledgment beyond 2005 and noting that the plaintiff had not produced a balance sheet or other document showing acknowledgment. The plaintiff’s legal heir appealed to the Supreme Court.

Key Issue

  • Whether the suit could be rejected at the threshold as barred by limitation given the entries in the defendant’s balance sheets up to 2013.

Legal Analysis and Ruling

  • Acknowledgment Under Section 18 of the Limitation Act, 1963: Under Section 18(1), a signed written acknowledgment of liability made before the expiration of the prescribed limitation period starts a fresh period of limitation from the date of acknowledgment.
  • Precedent on Balance Sheets: Relying on Asset Reconstruction Company (India) Ltd. v. Bishal Jaiswal and Axis Bank Ltd. v. Naren Sheth, the Court noted that balance sheet entries can constitute an acknowledgment of liability under Section 18, subject to reading the entry within the context of the balance sheet as a whole, including accompanying notes or the auditor’s report.
  • Contextual Link to Plaintiff’s Claim: The 2004–2005 balance sheet and bank reconciliation statement expressly recorded three cheques issued to Wazir Hussain Contractor, connecting him to the records, and subsequent balance sheets continued carrying forward balances pertaining to 2004–2005 through 2013. Section 18 does not require naming the specific creditor or following a rigid format so long as the entry, read with surrounding circumstances, indicates a subsisting jural relationship.
  • Scope of Order VII Rule 11 CPC & No Condonation Needed: Whether the exact sum claimed was owed, and how cheques and carried-forward figures interrelate, are evidentiary matters for trial rather than grounds for conclusive determination at the Order VII Rule 11 stage. Because valid Section 18 acknowledgments automatically renewed limitation on each subsequent acknowledgment date, no condonation of delay application was required.

Disposition

  • The Supreme Court allowed the appeal, set aside the High Court’s order dated 04.11.2024, revived the suit before the Trial Court, and kept all questions on the merits open.