2025 INSC 423
SUPREME COURT OF INDIA
(HON’BLE VIKRAM NATH, J. AND
HON’BLE PRASANNA B. VARALE, JJ.)
M/S FAIME MAKERS
PVT. LTD.
Appellant
VERSUS
DISTRICT DEPUTY
REGISTRAR, CO-OPERATIVE SOCIETIES (3), MUMBAI & ORS.
Respondent
Civil Appeal No.________OF 2025 (@
SLP(CIVIL) NO.26654 OF 2023) With Contempt Petition (C) No. 684 of 2024 IN SLP
(CIVIL) NO. 26654 OF 2023-Decided on 01-04-2025
Civil
Maharashtra
Ownership of Flats (Regulation of the Promotion of Construction, Sale,
Management and Transfer) Act, 1963, Section 5/11 – Quasi judicial order - Res
judicata -
Competent Authority had dismissed the first application filed by the respondent
No. 2-Society under Section 11 of the 1963 Act by order dated 22.02.2021, on
the finding that the issues involved were complicated and the respondent No.
2-Society ought to get the same sorted out by a competent Civil Court and only
thereafter apply afresh - A further finding recorded was that no conveyance of
sale could be directed - However, only conveyance of assignment of leasehold
rights could be granted, but that too after sorting out of the issues – The
said order not challenged and the same became final - Respondent No.2-Society
thereafter did not take any steps to approach the appropriate forum for sorting
out or resolving out the issues mentioned in the order dated 22.02.2021 and
instead, within a month, it moved a second application before the Competent Authority
on 24.03.2021, registered as Application No. 101 of 2021, seeking relief for
the unilateral assignment of leasehold rights in favour of respondent No.
2-Society – Contention on behalf of the appellant that the order dated
05.10.2021, passed by the Competent Authority allowing Application No. 101 of
2021, clearly amounted to a review of the first order dated 22.02.2021 - No
power was vested in the said authority by the Statute i.e. the 1963 Act as such
was without jurisdiction or authority of law – Held that there was no
unconditional liberty granted to respondent No.2-Society to apply for the
unilateral assignment of leasehold rights – The order dated 22.02.2021 is very
clear that complications had arisen because of various transactions inter se
parties at different points of time - Once a Competent Authority
(quasi-judicial in nature) settles an issue, that determination attains
finality unless it is set aside in accordance with law - The second application
filed by the respondent No.2-Society under Section 11 of the 1963 Act before
the Competent Authority, being Application No. 101 of 2021, deserves to be
dismissed - However, the liberty granted in the first order of the Competent
Authority dated 22.02.2021, while rejecting Application No. 53 of 2020, would
still be available to the respondent No.2-Society but only after getting the
complications resolved/sorted out before the appropriate Court/Forum - Impugned
order of the High Court liable to be set aside, the writ petition would stand
allowed, and the order dated 05.10.2021 passed by the Competent Authority
quashed.
(Para
7 to 16)
JUDGMENT
Vikram Nath, J. :- Leave granted.
2. The appellant has assailed the
correctness of the judgment and order dated 10.11.2023, passed by the High
Court of Bombay, whereby the appellant's Writ Petition No. 8186 of 2022,
assailing the correctness of the order dated 05.10.2021 passed by the District
Deputy Registrar, Co-operative Societies, Mumbai/ Competent Authority, was
dismissed. By the order dated 05.10.2021, the competent authority had allowed
Application No. 101 of 2021, filed by Prakash Apartment Co-operative Housing
Society Limited (respondent No.2-Society) under Section 5/11 of the Maharashtra
Ownership of Flats (Regulation of the Promotion of Construction, Sale,
Management and Transfer) Act, 1963[Hereinafter
referred to as the "1963 Act"], directing the execution and
registration of a unilateral deed of assignment with respect to 1321.36 square
meter area of land and the building situated thereon along with 198.20 square
meter on the recreational ground in the name of respondent No.2-Society.
3. Briefly stated, the facts relevant
for the present controversy are as follows:
3.1.
The subject land of the dispute comprises Survey No. 22, Hissa No. 1,
corresponding to C.T.S. No. 75/B, admeasuring 1,321.36 square meters, along
with 198.20 square meters in the Recreational Ground, totalling 1,519.56 square
meters, out of a larger parcel of 2,752.9 square meters, situated at Bandivali
Hill Road, Jogeshwari (West), Mumbai -400102, within the Village Bandivali,
Taluka Andheri.
3.2. The
larger property, which includes the subject land, was transferred to Byramjee
Jeejeebhoy Private Limited (hereinafter, "BJPL") through a Deed of Conveyance
dated 24.07.1951, executed between Nanabhoy Byramjee Jeejeebhoy and BJPL
3.3. On
29.10.1952, BJPL, as the lessor, executed an Indenture of Lease in favour of
Ramkishor Singh Kunjbihari (respondent No.3) as the lessee. Subsequently,
respondent No.3 granted development rights over the leased land to M/s Prakash
Builders (respondent No. 4).
3.4. Respondent
No.4 constructed an unauthorized building on the land, without approved plans,
comprising approximately 27 flats. These flats were sold to various purchasers,
who later formed respondent No.2-Society.
3.5. On
07.07.2010, BJPL executed a Deed of Conveyance in favour of the appellant,
whereby it sold its right, title, interest, and share in the larger
property—including the subject land—to the appellant. Consequently, the appellant
became the landowner as per the provisions of the 1963 Act.
3.6. On
06.09.2012, the legal heirs of the late Ramkishor Singh (respondent No. 3)
filed a suit against the appellant and BJPL. The dispute was eventually settled
through Consent Terms, wherein the parties agreed to divide the larger property
into two portions.
3.7. Pursuant
to the Consent Terms, a Deed of Surrender of Leasehold Rights was executed on
30.12.2012 between the appellant and respondent No.3. Through this deed, the
appellant surrendered 3,596 square meters of land from the larger property in
favour of respondent No. 3, while respondent No. 3 relinquished his leasehold
rights over 2,786 square meters in favour of the appellant. As a result, the
appellant became the owner of 2,768 square meters of land within the larger
property.
3.8. The
respondent No.2-Society applied for a Unilateral Certificate of Deemed
Conveyance under Section 11 of the 1963 Act before the Competent Authority
which was registered as Application No.53 of 2020.
3.9. By
an order dated 22.02.2021, the Competent Authority dismissed the respondent No.
2-Society's application, observing that the Society was eligible to seek the relief
of unilateral conveyance of assignment of leasehold rights. The application was
also rejected due to legal uncertainties and complications regarding the identity
of the land's promoter and on account of transfers. The order directed that the
parties should first seek appropriate relief from a competent Civil Court,
following which the Society was granted liberty to file a fresh application.
This order attained finality as it was not assailed before any superior
forum/Court.
3.10. Despite
the Registrar's directive, the respondent No.2-Society did not approach the
Civil Court to resolve the legal complications. Instead, on 24.03.2021, it
submitted a fresh application to the Competent Authority, seeking a Unilateral
Assignment of Leasehold Rights which was registered as Application No.101 of
2021.
3.11. On
05.10.2021, the Competent Authority passed an order granting the unilateral
assignment of leasehold rights in favour of the respondent No.2-Society.
3.12. Aggrieved
by this order, the appellant challenged it by filing Writ Petition No. 8186 of
2022 before the High Court of Bombay and by the impugned order dated 10.11.2023,
the High Court dismissed the appellant's writ petition, leading to the present
appeal.
4. We have heard Shri Dama
Seshadri Naidu, learned senior counsel appearing for the appellant and learned counsel
appearing for respondent No. 2-Society as also the intervenors.
5. Mr. Naidu, learned senior counsel
appearing for the appellant made the following submissions:
(i).
The Competent Authority had dismissed the first application filed by the
respondent No. 2-Society under Section 11 of the 1963 Act by order dated
22.02.2021, on the finding that the issues involved were complicated and the
respondent No. 2-Society ought to get the same sorted out by a competent Civil
Court and only thereafter apply afresh. A further finding recorded was that no
conveyance of sale could be directed. However, only conveyance of assignment of
leasehold rights could be granted, but that too after sorting out of the
issues. The said order dated 22.02.2021 was never assailed by the respondent
No.2-Society. Respondent No.2-Society thereafter did not take any steps to
approach the appropriate forum for sorting out or resolving out the issues
mentioned in the order dated 22.02.2021 and instead, within a month, it moved a
second application before the Competent Authority on 24.03.2021, registered as
Application No. 101 of 2021, seeking relief for the unilateral assignment of
leasehold rights in favour of respondent No. 2-Society. The submission was that
the second application was not maintainable without the issues being resolved
by the competent Civil Court as directed in the order dated 22.02.2021. The
second application for leasehold rights could have been filed only after the
issues resolved by the competent Civil Court. The second application was thus
barred by the principle of res judicata, and the Competent Authority, while allowing
the second application, committed a serious error in entertaining the same.
(ii).
The Competent Authority is a statutory authority and would fall within the
category of quasi-judicial authority as it decides the application as per the
statutory provisions after providing due opportunity of hearing to the
concerned parties, as such until and unless specifically provided by Statute,
it would not have power of review. The order dated 05.10.2021, passed by the
Competent Authority allowing Application No. 101 of 2021, clearly amounted to a
review of the first order dated 22.02.2021. No power was vested in the said
authority by the Statute i.e. the 1963 Act as such was without jurisdiction or
authority of law.
(iii).
Even on merits, the Competent Authority erred in granting the relief for
unilateral assignment of leasehold rights, as the constructions made were not
authorised, and no commencement certificate for raising the construction of
building in question was ever obtained, and as such no benefit could be
extended to the respondent No.2-Society under Section 11 of the 1963 Act for
the inaction of the builder in transferring the ownership rights in favour of
the members of the respondent No.2-Society.
(iv).
It was next submitted that even assuming for the sake of argument that
unilateral assignment of leasehold rights could be extended to the respondent
No.2-Society, there was no justification for granting the same for an area of
1,361 square meter, whereas the building in question was situtate, enclosed
within a boundary wall, covering only 870 square meters.
(v).
The High Court committed a manifest error by not correctly reading the first
order of the Competent Authority dated 22.02.2021. The High Court went on the
premise that the first order dated 22.02.2021 was little vague and confusing.
Which was not correct in as much the first order of 22.02.2021 was very clear
that the respondent No.2-Society needed to get the complications resolved by
the competent Civil Court and only thereafter apply afresh for assignment of
leasehold rights.
(vi).
On such submissions, it was prayed that the appeal deserves to be allowed, the
impugned orders deserve to be set aside, and the application No. 101 of 2021,
filed by respondent No.2-Society under Section 11 of the 1963 Act before the
Competent Authority, deserves to be rejected.
6. On the other hand, learned counsel
for the respondent No.2-Society has made the following submissions:
(i).
The High Court correctly appreciated and interpreted the first order dated 22.02.2021
to record a finding that the said order granted unconditional liberty to the
respondent No. 2-Society to file a fresh application for the assignment of
leasehold rights.
(ii).
It was next submitted that the second order dated 05.10.2021 would not amount
to a review, as it was dealing with an application seeking a distinct relief
from the first application, and in view of the liberty granted, there was no
question of any review. The second application was to be dealt with on its own
merits, independent of the first order rejecting the first application.
(iii).
It was also submitted that the issue relating to the demarcation of boundary,
with respect to the building in question covering only 870 square meter was
although raised before the High Court but was completely unsubstantiated, as no
supporting documents were filed in that regard. The report of the City Survey
Officer which was subsequent to the judgement of the High Court cannot be
looked into or relied upon by this Court in this appeal.
7. Having considered these submissions
and having perused the order dated 22.02.2021, we have no hesitation to hold
that there was no unconditional liberty granted to respondent No.2-Society to
apply for the unilateral assignment of leasehold rights. The order dated 22.02.2021
is very clear that complications had arisen because of various transactions
inter se parties at different points of time. The relevant facts have already
been noted in the earlier part of this judgment.
8. The relevant extract of the
order dated 22.02.2021, whereby the application was dismissed for the reasons
given therein, with liberty to apply afresh after sorting out the issues, is
reproduced hereunder:
"...
Therefore, the petitioner has to appeal to the appropriate court in this
regard. As there is a legal complication in this case, the authority will not
be able to make a human transfer in the name of the applicant society. Due to
this, the applicant society should only demand assignment of leasehold claim
and also the competent court should resolve the legal issues related to the transfer
of the name of the respondent No.3 of the rate of income.
It is
not possible to transfer the leasehold right of the said property in the name
of the applicant Society unless these matters are settled. Therefore, I am
convinced that after the settlement of these matters, the applicant should be
allowed to re-apply for the human transfer of the leasehold rights of the said
property and the application submitted by the applicant Society should be rejected."
9. A plain reading of the above findings
of the Competent Authority in its order dated 22.02.2021 leaves no manner of
doubt that respondent No. 2-Society could approach the Competent Authority
afresh for the unilateral assignment of leasehold rights only after getting the
complications sorted out before the appropriate Court. The order clearly
indicates that the competent authority could not grant leasehold rights under
the existing set of facts until and unless the complications were sorted out.
10. There is no explanation from
the side of respondent No.2-Society with respect to the above findings of the
Competent Authority recorded in the order dated 22.02.2021, as to why the same
was not challenged before a superior forum. Once the said order has been accepted
by the parties and has attained finality, the Competent Authority would not
have jurisdiction to entertain a second application contrary to the findings
and directions given by the Competent Authority in the first order.
11. It has been settled by this
Court that the principle of res judicata applies to and binds quasi-judicial
authorities. This Court in Ujjam Bai vs. State of U.P. [1962 SCC OnLine SC 8] has taken the view that principles of res
judicata equally apply to quasi-judicial bodies. Whenever a judicial or
quasi-judicial tribunal gives a finding on law or fact, its findings cannot be
impeached collaterally or in a second round and are binding until reversed in
appeal or revision or by way of writ proceedings. The characteristic attribute
of a judicial act or decision is that it binds, whether right or wrong. Thus, any
error, either of fact or law, committed by such bodies cannot be controverted
otherwise by way of an appeal or revision or a writ unless the erroneous
determination relates to the jurisdictional matter of that body.
12. This position has been
further reinforced in Abdul Kuddus vs. Union of India and others[(2019) 6 SCC 604] which relies upon
Ujjam Bai (supra). In Abdul Kuddus (supra), this Court held that the opinion by
the Foreigners Tribunal is a quasi-judicial order. Therefore, it would be incorrect to hold that the opinion
of the Tribunal and/or the consequential order passed by the Registering
Authority would not operate as res judicata. Further, it was established that
any quasi-judicial Authority would not ordinarily have the power to
unilaterally take a contrary view taken by a coordinate or predecessor
authority at an early point in time.
13. From the foregoing
discussion, it is evident that once a Competent Authority (quasi-judicial in nature)
settles an issue, that determination attains finality unless it is set aside in
accordance with law.
14. In our opinion, the High
Court erred in giving a different interpretation to the above text of the first
order dated 22.02.2021. The High Court had extracted the above findings, conclusions,
and directions in its impugned order but still moves on to hold that unconditional
liberty was given to respondent No.2-Society, which in our opinion, was not
correct.
15. Without further burdening
this order by entering into the other issues, we are satisfied that the
impugned order cannot be sustained. The second application filed by the
respondent No.2-Society under Section 11 of the 1963 Act before the Competent
Authority, being Application No. 101 of 2021, deserves to be dismissed.
However, the liberty granted in the first order of the Competent Authority
dated 22.02.2021, while rejecting Application No. 53 of 2020, would still be
available to the respondent No.2-Society but only after getting the
complications resolved/sorted out before the appropriate Court/Forum.
16. Accordingly, the appeal is
allowed, impugned order of the High Court is set aside, the writ petition would
stand allowed, and the order dated 05.10.2021 passed by the Competent Authority
is quashed.
17. In view of the above
findings, the Contempt Petition (C) No. 684 of 2024 would not require any
further consideration. It is accordingly disposed of.
18. Pending applications, if any,
stand disposed of.
------