2025 INSC 297
SUPREME COURT OF INDIA
(HON’BLE
B.V. NAGARATHNA, J. AND HON’BLE PRASANNA B. VARALE, JJ.)
ZON
HOTELS PVT. LTD
Petitioner
VERSUS
GOA COASTAL ZONE
MANAGEMENT AUTHORITY
Respondent
Civil Appeal No(S). 9328 of 2022-Decided
on 19-02-2025
Environment
Law
National Green
Tribunal Act, 2010, Section 16 and 18 – Environment Law - Determination of environmental compensation
– Principles of natural justice –
Appellate order – Challenge as to - Authority while determining the
compensation has neither issued any Show Cause Notice to the appellant herein
nor has it given an opportunity of being heard – Held that the procedure
adopted by the first respondent herein was contrary to the settled principles
of natural justice - Further, when the said order dated 09.05.2022 was assailed
by the appellant before the NGT, the NGT, having found violation of the
principles of natural justice, ought to have remanded the matter to the first
respondent-authority for re- determination of environmental compensation after
giving an opportunity of being heard to the appellant herein - Instead, the NGT
took upon itself to determine the correctness or otherwise of the calculation
of environmental compensation arrived at by the first respondent-authority on
the premise that it was giving an opportunity to the appellant herein – Held
that the opportunity given by the NGT to the appellant herein in an appeal is
not the same quality of opportunity which the first respondent as an original
Authority would have granted to the appellant herein - NGT was not right in
sustaining the impugned order dated 09.05.2022 - Since the order of the NGT set
aside only on the issue of violation of principles of natural justice and not
on merits, the impugned order dated 09.05.2022 passed by the first
respondent-Authority to be construed as
a Show Cause Notice - Appellant granted three weeks’ time to reply to the
said order now construed as a Show Cause Notice - The appellant shall be heard
and there shall be a re- determination of the environmental compensation that
has to be paid by the appellant herein having regard to the direction dated
19.04.2022 issued by the High Court in PIL Writ Petition No.2530/2021.
(Para
11 and 12)
JUDGMENT
Nagarathna, J. :-
Admit.
2.
Being aggrieved by the order dated 14.10.2022 passed by the National Green
Tribunal, Western Zone Bench, Pune (“NGT” for the sake of convenience), in
Appeal No.19/2022 (WZ), the appellant is before this Court.
3.
We have heard learned counsel for the appellant and learned counsel for first
respondent and learned counsel for respondent Nos.2 and 3 and we have perused
the material on record.
4.
The controversy in this appeal is in a very narrow compass. The grievance of
the appellant is that pursuant to the direction issued by the High Court in PIL
Writ Petition dated 19.04.2022, the first respondent herein sought to compute
damages vis-a-vis the illegal construction put up by the appellant herein
and estimated the damages resulting from the illegal construction put up by the
appellant herein in monetary terms. The first respondent herein by order dated
09.05.2022 directed the appellant herein to pay a sum of Rs.2,04,19,560/-
(Ruees Two Crores, four lakhs nineteen thousand and five hundred and sixty
only) towards environmental compensation.
5.
Learned counsel for the appellant submitted that prior to the determination of the
environmental compensation directed to be paid by the appellant herein, there
was no opportunity given to the appellant herein inasmuch neither a Show Cause
Notice was issued to the appellant nor was an opportunity of hearing granted.
The impugned order dated 09.05.2022 is a unilateral, one-sided order which is
hit by the principles of natural justice.
6.
Being aggrieved by the said order, the appellant herein preferred an appeal
before the NGT, Western Zone. Although the NGT acknowledged the fact that the
appellant was not heard in the matter, nevertheless it did not remand the
matter to the first respondent-management authority for a re-determination of
the environmental compensation afresh. Instead, the NGT simply sustained the
said order on the premise that it (NGT) was giving an opportunity of being
heard to the appellant herein. Learned counsel for the appellant submitted that
an Appellate Authority hearing a lis in the form of an appeal is totally
different from the original authority which would determine
the environmental compensation which is in the nature of an exercise of
administrative powers. Learned counsel submitted that the order dated
09.05.2022 which was passed by the first respondent-management authority was in
total violation of the principles of natural justice. The NGT, therefore, ought
to have remanded the matter to the Management Authority for re- determination
of the environmental compensation that was liable to be paid by the appellant
herein after giving an opportunity of being heard and filing objections to the
said determination.
7.
In the circumstances, learned counsel for the appellant submitted that the
impugned order of the NGT as well as the order dated 09.05.2022 may be set
aside and there may be a fresh compliance of the direction issued by the High
Court dated 19.04.2022.
8.
Per contra, learned counsel for the first respondent and learned counsel for
third respondent supported the impugned order(s) and contended that there is no
merit in the appeal; that the appellant herein could have approached the High
Court in Writ Petition No.2530/2021 if it had any grievance with regard to
order dated 09.05.2022; that it was the appellant which chose to file an appeal
before the NGT and the NGT, after giving an opportunity of hearing to the
appellant herein, has passed the impugned order; that there is no merit in this
appeal and hence, the same may be dismissed.
9.
We have considered the arguments advanced at the bar in light of the material
on record and particularly in light of order dated 09.05.2022 passed by first
respondent-Authority as well as the impugned order passed by the NGT.
10.
We find that the High Court by order dated 19.04.2022 observed as under:
“3. In so far as
prayer clause (c) is concerned, we direct the GCZMA as well as other
authorities who are involved in the demolition of such construction to file an
affidavit indicating the cost required for such demolitions. The GCZMA should
also make an estimate of the damages that such illegal constructions cause to the
environment in monetary terms, though we are conscious that such damage can
never be fully compensated only in monetary terms.
4. Respondent No.6 is
also granted an opportunity to file affidavit, if they choose to explain why
they should not be required to pay damages to the State for the illegal and
unauthorized constructions put up by them in an area effected
by CRZ notification.”
11.
On the basis of the aforesaid order, the impugned order dated 09.05.2022 was
passed by the first respondent-Authority. The Authority while determining the
compensation has neither issued any Show Cause Notice
to the appellant herein nor has it given an opportunity of being heard.
Therefore, the said determination made by the first respondent-authority
is unilateral and in the absence of hearing the appellant herein, we find that
the procedure adopted by the first respondent herein was contrary to the
settled principles of natural justice. Further, when the said order dated
09.05.2022 was assailed by the appellant before the NGT, the NGT, having found
violation of the principles of natural justice, ought to have remanded the
matter to the first respondent-authority for re- determination of environmental
compensation after giving an opportunity of being heard to the appellant
herein. Instead, the NGT took upon itself to determine the correctness or
otherwise of the calculation of environmental compensation arrived at by the
first respondent-authority on the premise that it was giving an opportunity to
the appellant herein.
12.
We hold that the opportunity given by the NGT to the appellant herein in an
appeal is not the same quality of opportunity which the first respondent as an
original Authority would have granted to the appellant herein. Therefore, we
find that the NGT was not right in sustaining the impugned order dated
09.05.2022 passed by the appellant herein. Since we are setting aside the order
of the NGT only on the issue of violation of principles of natural justice and
not on merits, we shall construe the impugned order dated 09.05.2022 passed by
the first respondent-Authority as a Show Cause Notice. Appellant herein is
granted three weeks’ time from today to reply to the said order now
construed as a Show Cause Notice. The appellant shall be heard and there shall
be a re- determination of the environmental compensation that has to be paid by
the appellant herein having regard to the direction dated 19.04.2022 issued by
the High Court in PIL Writ Petition No.2530/2021 extracted above.
13.
It is needless to observe that the said re-determination shall be made as
expeditiously as possible and in accordance with law.
14.
The appeal is allowed in-part and disposed of in the aforesaid terms.
15.
It is stated that a sum of Rs.60,00,000/- (Rupees
Sixty Lakhs Only) has been deposited by the appellant before the NGT, Western
Zone, the disbursal of the said amount shall be subject to the orders to be
made by the first respondent-Authority.
Pending
application(s), if any, shall stand disposed of.
------