2025 INSC 294
SUPREME COURT OF INDIA
(HON’BLE
SANJAY KAROL, J. AND HON’BLE MANMOHAN, JJ.)
PUSHPA JAGANNATH
SHETTY
Petitioner
VERSUS
SAHAJ ANKUR REALTORS
Respondent
Civil
Appeal No. 3160 OF 2023-Decided on 28-02-2025
Consumer
Consumer Protection
Act, 1986, Section 24A – Consumer - Limitation - According to the impugned order,
six months are required to be counted from the date of the indemnity cum
undertaking, i.e. 10th January 2015 - The flats in escrow were to be given
requisite permissions, which could not be obtained within a period of six
months; hence, the cause of action arose on 10th July 2015 - The complaint case
came to be filed on 19th February 2019, as such, the same was held by NCDRC to
be barred by limitation – Held that the application before the Commission was
filed on 6th February 2019,
hence the matter shall be governed by the Act, 1986 - Section
24-A of the Act prescribes the limitation period to be two years - The
proviso thereto also provides for the possibility of the
commission condoning delays beyond this point, but when doing so, it is to
record its reasons - Parties have agreed to keep the papers in escrow with a
third party - Specific talks/parlays were ongoing inter se the parties and the
escrow, about the implementation of the terms of the agreement - The escrow, in
response to the appellants' communication dated 16th November 2018, has
responded vide communication dated 14th December 2018, appraising the instant
respondent of the instant appellants’ concerns about the non-implementation of
the contractual obligations - Only in the absence of any response, did the
appellants set up their claims in terms of the complaint preferred before the
NCDRC on 6th February 2019 – Held that considering the consistent efforts back
and forth, inter se the parties, with regard to the implementation of the terms
of the contract, there was no question of dismissal of the complaint on the
issue of limitation - It was a continuing cause of action, and, only when
escrow expressed helplessness that the complainant was forced to file the
complaint –NCDRC held to have committed an error on the face of record -
Finding the view taken by it to be ex-facie erroneous, the impugned order liable
to be quash and set aside - Complaint filed by the appellant held to be within
time - The same is restored to its status and number - Parties directed to
appear before the NCDRC on 17th March 2025.
(Para
6 to 12)
ORDER
1.
This appeal is under Section 67 of the Consumer Protection Act, 2019
and is directed against the judgment dated 14th March 2023 passed in Consumer
Case No.238 of 2019 by the National Consumer Disputes Redressal Commission, New
Delhi[hereinafter NCDRC] .
2.
The short facts giving rise to the present appeal are that the respondents are a partnership firm that owned the
building named "Madhav Baug" in the village of Andheri, Mumbai. The
complainants were tenants in two flats on the ground floor in Building-A. The
former decided to demolish this building and construct a new one and, in
furtherance thereof, executed, a Permanent Alternate Accommodation Agreement
dated 20 th September 2013, allotting Flat No. 801,
carpet area 700 sq. ft. on the 8th floor of the B-Wing of the new building. The
agreement provided 24 months from the date of the issue of the commencement
certificate, along with a grace period of 6 months to complete such
construction. The proposed redevelopment however could not be completed in the
stipulated time, as such, on 10th January 2015, the
respondents executed an “Indemnity- cum-Undertaking” to allot two flats
numbered 301 and 302 having carpet area of 650 sq. ft. and 667 sq. ft. in
B-Wing, free of cost, if necessary approvals could not be obtained within 6
months. This agreement further provided that if the respondents failed to give
either of the two options to the appellants, they would be entitled to
compensation for 1317 sq. ft. carpet area at market value plus 25% additional
value thereon.
3.
Vacant possession of the old flats was handed over in December 2014 and
necessary monetary consideration for alternative accommodation stood
transferred to the appellants within time. The contractual period of 24 months
expired in December 2016. The respondent continued payment of rent of alternate
accommodation of the appellants at the applicable rates till January 2019.
Balance of the dislocation compensation i.e. Rs.2,50,000/-,
remained pending thereafter. Several letters were exchanged, and meetings were
held between the parties. The appellants wrote a letter dated 13 th August 2018 to Mr. Mahesh Jani, the solicitor and escrow
agent, asking him to hand over the papers of the flats in escrow to them. In a
meeting held on 26th September 2018, the respondents were informed by Mr. Jani
that if the approved layout plan was not produced, the flats put in escrow
could be released to the appellants on 11 th
October 2018. Further time was sought on two occasions, but the flats in
escrow were finally released to the appellants on 17 th
December 2018.
4.
Having received the said flats, the instant complaint case [Annexure A-10 of the Paper book] came to be filed on 6th February
2019 seeking the following reliefs, inter alia :
“a) That this Hon’ble
Court, Direct and Order the opposite party to allot Flat Nos.301 & 302 on the
third-floor admeasuring of 650 and 667 square feet carpet area, along with
Podium Car Parking, respectively in the “B” Wing of the proposed new buildings
with A Wing, B wing and C Wing to be developed on the property currently known
as “Madhav Baug” bearing C.T.S. Ns. 657 and 657/1 to 19 of Village Andheri,
Taluka Andheri situated at Andheri Kurla Road, Andheri (East) Mumbai – 400 069,
and have the Agreements in respect of the same, Registered with the
Sub-Registrar of Assurances, Mumbai, in the name of the Complainants.
AND/OR in the
Alternative, This Hon’ble Court direct and order the opposite party to pay to
the Complainants, a Sum of Rs.4,59,96,225/- (Rupees
Four Crores Fifty-Nine Lakhs Ninety-Six Thousand Two Hundred Twenty-Five only)
as market value and 25% compensation for the Flats and further interest thereon
at the rate of 12% Per annum till payment or realization from the date of
filing of this Complaint.
b) That this Hon'ble
Court, Direct and order the opposite party. The Opposite Party to be restrained
by an order and direction of this Hon'ble Curt not to create any third-Party
rights or encumber two flats Nos.301 and 302 respectively on the third-floor
admeasuring of 650 and 667 square feet carpet area, respectively in the “NB”
Wing of the proposed new buildings with A Wing, B wing and C Wing to be
developed of the property on the currently known as “Madhav Baug” bearing
C.T.S. Nos. 657 and 657/1 to 19 of Village Andheri, Taluka Andheri situated at
Andheri Kurla Road, Andheri (East), Mumbai – 400 069.
c) That this Hon’ble
Court, Direct and Orser the Opposite Party to pay the Complainant rent from
January 2019 onwards at the rate of 51,537/- per month till the final disposal
and hearing of this Complaint.
d) That this Hon’ble
Court, Direct and Order the Opposite Party to pay the arrears of Rupees
2,50,000/- which was due on 29th October 2017 along with interest at 12% per
annum to the Complainant.
e) That this Hon'ble
Court, Direct and Order the Opposite Party to pay Rupees Two Lakhs towards the
cost of this Complaint."
5.
The relevant extract of the consideration on merits by the NCDRC is as under:
“7. We have considered
the arguments of the consel for the parties and examined the record. The
complainants sought to enforce "Indemnity-cum-Undertaking" dated
10.01.2015, under which, the owner undertook to allot Flat Nos.301 & 302,
carpet area 650 sq.ft. and 667 sq.ft., in “B” wing,
free of cost, if the owner fails o obtain necessary approval of the plan within
six months from the date hereof as mutually agreed by the parties in writing. None
of the parties have produced any separate writing in respect of mutually agreed
date as such, six months period has to be counted from 10.01.2015. Cause of
action for enforcement of "Indemnity-cum-Undertaking" arose on
10.07.2015. This complaint was filed on 19.02.2019. The complaint is time
barred and no application for condonation of delay has been filed." As
such, the application for compensation was dismissed vide
the impugned order.
6.
In the facts above, the question that arises for our consideration pertains to
the calculation of limitation in preferring the complaint case. According to
the impugned order, six months are required to be counted from the date of the
indemnity cum undertaking, i.e. 10th January 2015. The flats in escrow were to
be given requisite permissions, which could not be obtained within a period of
six months; hence, the cause of action arose on 10th July 2015. The complaint
case came to be filed on 19th February 2019, as such,
the same was barred by limitation.
7.
The application before the Commission was filed on 6 th
February 2019, hence the matter shall be governed by the Consumer
Protection Act, 1986. Section 24-A of the Act prescribes the
limitation period to be two years. The proviso thereto also provides for the
possibility of the commission condoning delays beyond this point, but when
doing so, it is to record its reasons.
As
already observed, the parties have agreed to keep the papers in escrow with a
third party. In our view, this was done for the purpose of property
implementation of the terms of the agreement. It is not in dispute, as is also
evident from the record, that specific talks/parlays were ongoing inter se the
parties and the escrow, about the implementation of the terms of the agreement.
The escrow, in response to the appellants' communication dated 16th November
2018[Annexure A-7 of the Paperbook] , has responded
vide communication dated 14th December 2018, appraising the instant respondent
of the instant appellants’ concerns about the non-implementation of the
contractual obligations. The escrow, as is evident from the said communication[Annexure A-9 of the Paperbook] and had
inter alia conveyed as under –
1. Further to the
meeting held in our office on 12/10/2018,. It appears
that Miss. Atita Shetty and her family are not satisfied with the non- performance
of the promises made by you, that you will tender an approved plan of proposed
flat to be given to her and her family which you have failed and neglected to
do as per her letter dated 16/11/2018, and accordingly has asked us to handover
the escrow documents to her.
2. It was decided and
agreed to handover the escrow documents to Miss Atita Shetty on 7 th December, 2018 and the same was postponed to 14th
December 2018.
3. Unfortunately, at
the last moment you had called up in our office to cancel today's appointment,
we have fixed it on Monday viz., 17th December 2018. We will fix the
appointment on Monday viz., 17 th December 2018 and whether you attend or not,
nor we will postpone any further date and on 17 th December 018 we will hand
over the escrow documents to Miss Atita Shetty without fall, which kindly take
note.”
8.
Only in the absence of any response, did the appellants set up their claims in
terms of the complaint preferred before the NCDRC on 6th February 2019. Even
before the said forum, the instant respondents committed default in filing
their response and, as is evident from the order dated 1 st July 2019, were
subjected to payment of cost quantified at Rs.25,000/-. The focus of the
respondents herein was to get the complaint dismissed on merits. It appears
that the NCDRC has dismissed it on the grounds of limitation.
9.
In our considered view, considering the consistent efforts back and forth,
inter se the parties, with regard to the implementation of the terms of the
contract, there was no question of dismissal of the complaint on the issue of
limitation. It was a continuing cause of action, and, only when escrow
expressed helplessness that the complainant was forced to file the complaint.
10.
In our view, the stand of the NCDRC defeats the ends of justice. The initial
cause of action indeed arose in July 2015 after the six-month period expired,
however, the Court cannot be amiss to the fact that the parties had been
pursuing the matter with the respondent by way of letters, meetings, and even
with the escrow agent, who, in turn, did his own back and forth with the owner,
before finally releasing the flats in escrow in favour of the appellants.
Further, as can be seen from the reliefs extracted supra, what has been claimed
is the security of the title they received upon the respondent's default. The
complaint case has not been filed seeking the flats in escrow for which
the cause of action did arise on 10th July 2015, and hence the same
limitation cannot be applied to a subsequent situation, which is that the
appellants already have the flats with them. They only seek that the same be
registered in their name and not alienated to any third party henceforth.
11.
Limitation, while important as a feature of law, is not meant to defeat a
substantive right. Efforts, in earnestness, to secure possession of the flats
cannot be discounted in order to compute the applicable limitation. The NCDRC
ought to have taken a holistic view of the situation and then proceeded to
examine whether the relief as claimed may be granted in favour of the
appellants.
12.
As such, we hold the NCDRC to have committed an error on the face of record.
Finding the view taken by it to be ex-facie erroneous, we quash and set aside
the impugned order with particulars mentioned in paragraph 1 of this order. We
hold that the complaint filed by the appellant is within time. The same is
restored to its status and number. We direct the parties to appear before
the NCDRC on 17th March 2025. We request that the matter be decided
expeditiously and preferably within six months from today. Observations made
herein are only for the purpose of determining the issue of limitation, and as
such, save and except this limited issue, the Commission shall decide the
petition on its own merit. All other contentions are left open.
13.
The appeal is disposed of in terms as aforesaid. It is clarified that it shall
be open for either party to approach this Court should the need so arise.
Pending
application, if any, shall also stand disposed of.
------