2025 INSC 219
SUPREME COURT OF INDIA
(HON’BLE ABHAY
S. OKA, J. AND HON’BLE UJJAL BHUYAN, JJ.)
SAHAKARMAHARSHI
BHAUSAHEB THORAT ...
Petitioner
VERSUS
THYSSEN KRUPP
INDUSTRIES INDIA P.LTD
Respondent
Civil
Appeal No. 3194 OF 2014-Decided on 14-02-2025
Arbitration
Arbitration Act, 1940,
Section 30 - Indian Contract Act, 1872, Section 74 – Arbitration award –
Challenge as to – Performance
guarantee – Claim for liquidated
damages - Compensation for breach of contract where penalty stipulated for - High
Court set aside the second award to the extent of a claim of Rs.68.15 lakhs -
It was held that this claim was based on speculative and imaginary calculations
- As regards the claim of Rs.2.09 lakhs and Rs.18.64 lakhs, the High Court
recorded that the respondent has accepted the liability - Clause 21.1 provided
that on the failure of the respondent to replace the defective or underrated
equipment within a reasonable time, the appellant had the option to replace the
same at the respondent's cost - Under clause 21, it was provided that the responsibility
of the seller for rectification/replacement shall extend to the actual cost of
rectification/replacement of defective items of the continuous fermentation
plant and machinery - Claim made before the Arbitral Tribunal by the appellant
shows that the claim for the sum of Rs.107.54 lakhs was not based on clause 21
of the agreement - It is not the appellant's case that the respondent was
called upon to replace the plant and machinery, and as the respondent failed to
do so within a reasonable time, the appellant replaced the plant and machinery
by themselves - The claim was on account of a refund of the amount spent by the
appellant on the plant - There is a clause for liquidated damages under which a
claim was allowed by the Arbitral Tribunal, which the respondent accepted - Option
under clause 21 of the agreement was not availed by the appellant - The
agreement provided for liquidated damages in clause 15 on account of
non-performance of the guarantees set out in clause 8 - Assuming that the
entire plant and machinery was a failure or scrap, the appellant had the right
to replace the same and claim the cost from the respondent - However, that was
not done by the appellant - The appellant got liquidated damages as provided in
the agreement on account of breaches committed by the respondent - The claim
for damages of the appellant will remain confined to what is expressly provided
under the Agreement in view of Section 74 of the Contract Act - The
appellant retained the plant and machinery and did not take the benefit of
clause 21 – Held that rightly held by the High Court, the appellant was
not entitled to the claim of Rs.68.15 lakhs as it was claimed in the statement
of claim as the refund of the amount spent by the appellant on the acquisition
of plant and machinery - Find absolutely no error in the view taken by the High
Court, and accordingly, the appeal liable to be dismissed.
(Para
23 to 30)
JUDGMENT
Abhay S. Oka, J.:-
FACTUAL
ASPECTS
1.
The issues involved in this appeal are limited, but the litigation has a
chequered history. An agreement was executed on 17th November 1992 by and
between the appellant and the respondent. Under the said agreement, the
respondent agreed to design, procure, manufacture and supply to the appellant
machinery and equipment for a continuous fermentation process based on the
Encillium process, patented by the National Chemical Laboratory, Pune (for
short, ‘the NCL’). The agreement contained an arbitration clause. The total
consideration was of Rs. 93,20,000/-. One of the clauses in the agreement
was that the fermentation plant that was to be supplied by the respondent must
have a guaranteed minimum yield of 280 litres of alcohol per metric tonne of
Molasses. According to the appellant's case, when the agreement was entered
into, the existing yield in their factory was 245 litres per metric tonne of
Molasses. Under the agreement, the plant and machinery were to be supplied
within a period of five and half months from the effective date of the
agreement, i.e., by 15th May 1993, for a total consideration of Rs.93.20 lakhs.
2.
According to the appellant, there was a delay of about 24 weeks in the delivery
of the machinery. The appellant's case was that four trial runs were conducted
on the machinery supplied by the respondent. The yield was much less than the
guaranteed yield of 280 litres per metric tonne of Molasses. The maximum yield
in trial runs was 237.68 litres per metric tonne of Molasses. Therefore, on 19th
October 1994, the appellant issued a legal notice to the respondent claiming a
sum of Rs. 237.83 lakhs as damages. As expected, the respondent disputed the
said claim. That is how the appellant invoked the arbitration clause by
appointing its nominee arbitrator.
3. According to the appellant's case, a
memorandum of understanding dated 24th July 1995 (for short, ‘the MOU’) was
executed by and between the parties without prejudice to their rights and
contentions. It provided for conducting one more trial run for 15 days after
necessary modifications were made in the machine as suggested by the NCL. The
modifications were to be made by the respondent at its own cost. By the MOU,
the quantum of liquidated damages under clause 15 of the agreement was increased
to 20% of the contract value, i.e. Rs. 18.64 lakhs, which would be payable if
the machine failed to give guaranteed performance. According to the appellant's
case, the fifth trial run conducted in August 1995 generated a yield of 224.54
litres per metric tonne of Molasses.
4.
The appellant filed a statement of claim before the Arbitral Tribunal, claiming
damages of Rs.233.75 lakhs. Broadly, the following claims were made:-
a) For a delay of 24
weeks in the supply of plant and machinery
- Rs.4.66 lakhs, which
is 5% of the contract price
b) Liquidated damages
equivalent to 20% of the contract value – Rs.18.64 lakhs;
c) On account of the failure of guaranteed
performance of steam and power consumption - Rs. 9.30 lakhs at 10% of the
contract value;
d) Loss caused due to
short production – Rs. 48.45 lakhs;
e) The amount spent by
the appellant on payment of the price to the respondent, civil work, and
supervision – Rs. 107.54 lakhs; and,
(f) Interest at the
rate of 18% on the claim amount of Rs. 107.54 lakhs from May 1993 till 31st
August 1995 – Rs.45.16 lakhs --
Total 233.75 lakhs.
5.
The Arbitral Tribunal, by an award dated 20th June 1999, granted the following
amounts to the appellant:
a) Liquidated damages
for delay in delivery of the plant and machinery – Rs.2.09 lakhs
b) Refund of the price
paid and incidental amount spent over the plant – Rs. 107.54 lakhs
c) Past interest –
Rs.28.74 lakhs
d) Compensation for
actual loss suffered in the yield of alcohol -
Rs. 21.42 lakhs --
Total Rs.159.79 lakhs.
e) Costs of Rs.1.50
lakhs
6. Both parties challenged the award by filing
objections under Section 30 of the Arbitration Act, 1940 (for short,
‘the 1940 Act’). By a judgment dated 6th May 2000, the learned Civil Judge set
aside the Award and remanded the same for fresh adjudication by the Arbitral
Tribunal. Both the parties challenged the order of the Civil Judge before the
High Court. By judgment dated 20th October 2000, the High Court held that the
claim of Rs.107.54 lakhs was beyond the jurisdiction of the Arbitral Tribunal.
However, the High Court upheld the claim for liquidated damages for the delay
in delivery of Rs.2.09 lakhs, compensation for actual loss suffered in the
yield of alcohol of Rs.21.42 lakhs, and arbitration cost of Rs.1.5 lakhs.
7.
The appellant filed an appeal before this Court against the judgment of the
High Court. By a judgment and order dated 7th May 2002, this Court set aside
the order of the High Court and restored the order of the Civil Court. This
Court held that the claim of Rs.107.54 lakhs and interest raised by the
appellant was certainly arbitrable before the Arbitral Tribunal and was not
beyond the scope of reference. In short, the order of remand passed by the
Civil Court was restored by this Court.
8. The award after remand (for short, ‘the
second award’) was made on 24th November 2002 by the Arbitral Tribunal. The
second award accepted the following claims:
a) Rs.2.09 lakhs as liquidated damages for delay in
supply of machinery;
b) Rs.18.64 lakhs as
damages for actual loss suffered in the yield of alcohol during five
performance trials;
c) Rs.68.15 lakhs as
damages for loss suffered due to non-performing machinery and equipment; and
d) Rs.10.63 lakhs
being the past interest leviable on damages of Rs.68.15 lakhs.
9.
Again, both the parties filed objections under Section 30 of the 1940
Act. By a judgment dated 6th November 2004, the Civil Court substantially
upheld the second award except for the direction to pay interest of Rs.10.63
lakhs on the ground that interest cannot be made payable on the amount of
damages till it is quantified.
10.
Being aggrieved by the judgment of the Trial Court, the respondent preferred an
appeal in which the appellant filed cross- objections. By the impugned judgment
dated 6th February 2012, the High Court allowed the appeal and dismissed the
cross-objections of the appellant. The High Court set aside the second
award to the extent of a claim of Rs.68.15 lakhs. It was held that this claim
was based on speculative and imaginary calculations. As regards the claim of
Rs.2.09 lakhs and Rs.18.64 lakhs, the High Court recorded that the respondent
has accepted the liability. On 13th April 2012, this Court issued a notice. The
appellant was directed to deposit the amount involved with the High Court
Registry by way of interim relief.
SUBMISSIONS
11.
Shri Vijay Hansaria, learned senior counsel appearing for the appellant, stated
at the outset that the appeal is confined to the rejection of Rs.68.15 lakhs
being damages for loss suffered due to non- performance of machinery and
equipment. The learned senior counsel submitted that even under the 1940 Act,
the scope of interference by the Civil Court was limited. He placed reliance on
the decision of Madnani Construction Corporation (P) Ltd. v. Union of
India & Ors. [(2010) 1 SCC 549]
12.
The learned senior counsel invited our attention to clauses 15.2 and 15.3 of
the contract. These clauses were applicable when the plant supplied or
commissioned and utilised by the purchaser yields below the minimum guarantee
of 280 litres per metric tonne.
13.
The learned senior counsel has invited our attention to the findings recorded
by the Arbitral Tribunal in the second award. He submitted that the respondent
never disputed the non-commissioning of the plant but stated that the machinery
and equipment supplied are complete without any defect or fault as per the
rated capacities mentioned in the parameters. The learned senior counsel
submitted that the claim of liquidated damages and breach of warranty were
separate and independent claims and were rightly granted by the Arbitral Tribunal.
The learned senior counsel, therefore, submitted that the appellant's claim, to
the extent of Rs.68.15 lakhs, deserved to be accepted.
14.
Shri Chander Uday Singh, learned senior counsel appearing for the respondent,
has also made detailed submissions. The learned senior counsel appearing for
the respondent submitted that the finding on the issue of the entitlement of
the appellant to the sum of Rs.68.15 lakhs has been correctly recorded by the
High Court. The learned senior counsel submitted that Section 74 of
the Indian Contract Act, 1872 (for short, ‘the Contract Act’) makes it
clear that where a contract contains a clause stipulating liquidated damages,
and the contract is broken, the party complaining of the breach is entitled to
receive such sum, not exceeding the mentioned amount. The learned senior
counsel also
urged that in view of Clause 21 of the
agreement, the claim made by the appellant that they were unable to use the
machinery cannot be accepted. The learned senior counsel submitted that the
High Court had already concluded the issue of the grant of the claim of
Rs.107.54 lakhs in the earlier round. He stated that no interference is called
for in the view taken by the High Court.
15.
The appellant's submission was that they could not use the supplied machinery
and that the machinery was no better than scrap because the fermentation
performance was lower than promised. To deal with the said submission, the
learned senior counsel for the respondent relied upon clause 21 of the
agreement. He submitted that the appellant did not call upon the respondent to
replace the machinery. At no stage is it claimed that the appellant had
replaced the machinery at the respondent's cost. He pointed out that in
paragraph 16 of the claim, the appellant stated that the agreement does not
provide any specific clause for the total failure of the plant. Therefore, as
per the Contract Act, the seller is liable for the actual damages. The
learned senior counsel appearing for the respondent submitted that what was
claimed by the appellant in the correspondence was a refund of the price. He
submitted that the applicability of Section 59 of the Sale of Goods
Act for a refund of the price or by way of damages is contrary to the
express terms of the agreement. He would, therefore, submit that the liability
of the respondent was restricted to Rs.18.64 lakhs as damages.
OUR
VIEW
16.
There were three contracts between the parties. The first is the agreement
dated 17th November 1992 (for short, ‘the agreement’). Under the agreement, the
respondent undertook to design, procure, manufacture and supply to the
appellant machinery and equipment for modernisation with a continuous
fermentation process based on the Encillium process developed by the NCL. The
total price was Rs. 93.20 lakhs which the appellant paid. It was provided that
delivery of machinery and equipment would start from 1st December 1992 and be
completed within five and half months from the agreement's effective date.
Clause 8 of the agreement incorporated the performance guarantee. The first
part of the performance guarantee was regarding the specifications of the
machinery and equipment, and the second part of clause 8 provided that all the
machinery and equipment of the continuous fermentation plant would be brand
new. What is relevant is sub-clause C of clause 8, which reads thus:
“C. That the capacity
and efficiency of the machinery and equipment of continuous fermentation plant
shall be fulfilled after one month from the start of operation, all units work
to their rated capacities and efficiencies fermentation efficiency minimum 90%
yielding 280 litres of alcohol/ton of molasses (47% F.S) and with performance
specified in annexure B and D.”
17.
Clause 15 provided for the penalties and liquidated damages.
a. It provided that if
the respondent fails to deliver the machinery and equipment within a stipulated
time, the respondent shall pay the liquidated damages equal to 0.25% of the
contract price for every completed week of delay subject to a maximum of 5% of
the contract price for delay in delivery;
b. Rs.1 lakh as
liquidated damages for every one litre less production of alcohol than
guaranteed figures as specified in Annexure B;
c. 1% of the contract
price, which is equivalent to Rs.93,200/- for every 0.1 kg/1 litre more steam
consumption at any stage than guaranteed figures subject to a maximum of 3% of
the contract price.
d. Rupees 1,39,000/-
equivalent to 1.5% of the contract price will be payable as liquidated damages
for every 10 kwh more power consumption at any stage than guaranteed figures
subject to a maximum of 2% of the contract price.
e. The penalties/liquidated damages payable
against non-performance of fermentation section and penalties/liquidated
damages payable for guaranteed performance towards steam and power shall be
limited to a maximum of 10% of the contract price.
18.
At this stage, it is also important to note clause 21 of the agreement which
reads thus:
“21.1 For a period of
twelve months from the date of commission of the continuous fermentation plant
or eighteen months from the date of last supply whichever is earlier called the
maintenance warranty period the seller shall remain liable to rectify / replace
any parts thereof such as may be found to be defective or below the rated.
Capacity under proper use and maintenance arising due to faulty design,
materials, or workmanship. The purchaser shall give the seller notice in
writing stating the particulars of the defects or failures and the seller shall
there upon make good the failures and the seller shall there upon make good the
defective or underrated equipments or replace the same free of cost to make it
comply with the requirements of the continuous fermentation plant. If the
seller fail to do so within reasonable times so as to require the production
loss to the minimum as required by the purchaser, the seller the whole any
portion of the cost of the seller the whole or any portion of the machinery and
equipment, as the case may be, which is defective or underrated or fail to
fulfil the requirements of the agreement and may recover the actual cost
thereof from the seller adjust the same from any balance payment to be
made to the seller; or recovery by raising debit notes.
Such
rectification/replacement shall be carried out by the purchase wing in a short
time as possible and at a reasonable price and under advice to the seller. In
case of such rectification/ replacement by the purchaser, the seller shall be
liable to pay purchaser the whole cost of such rectification replacement done
and the defective equipment on being replaced shall be taken away by the seller
at their own cost. The purchaser shall have the right to operate the machinery
and equipment after the commission in date of the continuous fermentation plant
except that this shall not be considered to permit operation of any equipment
which may be materially damaged by such operation before any required
rectification or alteration have been carried out.
21.2 If it becomes
necessary for the seller to replace or renew any defective part of the
continuous fermentation plant and machinery under this clause the provisions of
the first paragraph of this clause shall apply to the parts of the machinery
and equipment so replaced or renewed until the expiration of one month from the
date of such replacement or renewal, or until the end of the aforesaid
maintenance period of twelve months whichever is later.
21.3 The rectification
or new parts will be delivered for purchasers distillery site. The seller shall
also bear the cost of rectification / replacement carried out on their behalf
by the purchaser as mentioned above at the continuous fermentation plant site.
At the end of the maintenance period, seller liability shall case. first
paragraph of this clause, the purchaser shall be entitled to benefit of any
guarantee given to the seller by the original supplier or the manufacturer of
such plant and machinery.
21.4 The responsibility of the seller for
rectification replacement under this clause shall extend to the actual cost of
rectification / replacement of the defective items of the continuous
fermentation plant and machinery and shall not in any way be deemed to be
limited to the amount of the performance guarantee.”
(emphasis
added)
19.
A supplementary agreement was executed on the same day in which the respondent
agreed to pay liquidated damages of Rs. 2 lakhs for every one litre less
production of alcohol subject to the maximum ceiling of 10% of the contract
price.
20.
The third agreement executed between the parties was styled as the MOU, under
which the respondent agreed to supervise the reaction and commissioning of the
machinery.
21.
Now, we come to the claim made by the appellant. Before we refer to the claim,
we must note that the real controversy remains confined to the claim granted by
the Arbitral Tribunal to the sum of Rs.68.15 lakhs towards the damages for loss
suffered due to non-performing machinery and equipment and, consequently, the
interest thereon.
22.
The case made out in the claim is that the respondent failed to commission the
plant successfully so as to give guaranteed performance as per the
agreement. Therefore, production loss continued. The following claims were
made:
a) Delay in supply of
plant and machinery beyond the period of five and a half months from the
effective date of contract – Rs.4.66 lakhs;
b) Damages on account
of the failure to provide guaranteed performance of continuous fermentation
plant – Rs.18.64 lakhs;
c) Failure of
guaranteed performance of steam and power consumption – Rs. 9.30 lakhs;
d) Actual loss of
production – Rs. 48.45 lakhs; and
e) Amount spent by the
appellant on account of acquiring the plant, including the cost of the plant
paid to the respondent, civil work and supervision charges – 107.54 lakhs.
f) Interest at the
rate of 18% on the claim amount of Rs.107.54 lakhs from May 1993 till 31st
August 1995 – Rs.45.16 lakhs.
Accordingly,
a total claim of Rs.233.75 lakhs was made. However, while making the prayer,
the loss suffered during the trials was not claimed.
23. In the impugned judgment, the High Court
has, in detail, considered the clauses in the agreement. The High Court
referred to the notice dated 19th October 1994 addressed by the appellant to
the respondent. In the said notice, the appellant claimed that a sum of
Rs.107.54 lakhs had been spent on the plant and that the plant was not giving
the required results as agreed, even optimum to the norms. Therefore, the sum
of Rs.107.54 was a loss to the appellant. The High Court rightly rejected the
appellant's contention that the claim for damages of Rs.107.54 has been
concluded against the respondent. The High Court rightly observed that if that
were so, this Court would not have confirmed the order of remand to the
Arbitral Tribunal even on the said issue.
24.
We have already quoted the relevant part of the agreement, particularly clause
8, which contains performance guarantees. Clause 15 is regarding
penalties/liquidated damages. Penalties/liquidated damages were stipulated for
the delay in delivering machinery and plant, failure to give the guaranteed
performance of continuous fermentation plant, failure to provide a guaranteed
performance with respect to steam, and failure to give a guaranteed performance
with respect to power. Even the rates of liquidated damages have been laid
down.
25. Then comes clause 21. Clause 21.1 provided
that on the failure of the respondent to replace the defective or underrated
equipment within a reasonable time, the appellant had the option to replace the
same at the respondent's cost. Under clause 21, it was provided that the
responsibility of the seller for rectification/replacement shall extend to the
actual cost of rectification/replacement of defective items of the continuous
fermentation plant and machinery.
26.
Careful perusal of the claim made before the Arbitral Tribunal by the appellant
shows that the claim for the sum of Rs.107.54 lakhs was not based on clause 21
of the agreement. It is not the appellant's case that the respondent was called
upon to replace the plant and machinery, and as the respondent failed to do so
within a reasonable time, the appellant replaced the plant and machinery by
themselves. The claim was on account of a refund of the amount spent by the
appellant on the plant, as is evident from paragraph 16 of the statement of
claim. Paragraph 16 reads thus:
“16. Purchaser had
spent Rs. 107.54 lakh on the said plant. It is absolutely clear now that it
will not give required results as agreed and all the investment goes waste. The
agreement does not provide any specific clause for the total failure of plant.
Therefore, as per contract act, seller is liable for actual damages. Since the
entire plant goes waste seller is liable to pay for total investment of
Rs. 107.54 lakhs and loss of interest at the rate of 18% per year from 1st May
1993 onwards.” The claim was not made in terms of Clause 21 of the Agreement.
The
claim was not on account of the breach of warranty. What is claimed is
virtually the refund of the amount spent.
27.
As stated earlier, there is a clause for liquidated damages under which a claim
was allowed by the Arbitral Tribunal, which the respondent accepted. Under
clause 21 of the agreement, the appellant had the choice of replacing the plant
and machinery and seeking the cost of the plant and machinery and the
installation cost from the respondent. However, the said option was not availed
by the appellant. The agreement provided for liquidated damages in clause 15 on
account of non-performance of the guarantees set out in clause 8. Assuming that
the entire plant and machinery was a failure or scrap, the appellant had the
right to replace the same and claim the cost from the respondent. However, that
was not done by the appellant.
28.
In view of what is stated in paragraph 16 of the claim filed by the
appellant, Section 74 of the Contract Act needs to be considered,
which reads thus: -
“74. Compensation for
breach of contract where penalty stipulated for.— When a contract has been
broken, if a sum is named in the contract as the amount to be paid in case of
such breach, or if the contract contains any other stipulation by way of
penalty, the party complaining of the breach is entitled, whether or not actual
damage or loss is proved to have been caused thereby, to receive from the party
who has broken the contract reasonable compensation not exceeding the amount so
named or, as the case may be, the penalty stipulated for.
Explanation.—A
stipulation for increased interest from the date of default may be a
stipulation by way of penalty.
Exception.—When any
person enters into any bail- bond, recognizance or other instrument of the same
nature, or, under the provisions of any law, or under the orders of the Central
Government or of any State Government, gives any bond for the performance of any
public duty or act in which the public are interested, he shall be liable, upon
breach of the condition of any such instrument, to pay the whole sum mentioned
therein.
Explanation.—A person
who enters into a contract with Government does not necessarily thereby
undertake any public duty, or promise to do an act in which the public are
interested.”
(emphasis
added)
29.
The appellant got liquidated damages as provided in the agreement on account of
breaches committed by the respondent. The claim for damages of the appellant
will remain confined to what is expressly provided under the Agreement in view
of Section 74 of the Contract Act. The appellant retained the plant
and machinery and did not take the benefit of clause 21. Therefore, as rightly
held by the High Court, the appellant was not entitled to the claim of
Rs.68.15 lakhs as it was claimed in the statement of claim as the refund of the
amount spent by the appellant on the acquisition of plant and machinery.
30.
In the circumstances, we find absolutely no error in the view taken by the High
Court, and accordingly, the appeal is dismissed.
------