2025 INSC 215
SUPREME COURT OF INDIA
(HON’BLE
SANJIV KHANNA, CJI. AND HON’BLE SANJAY KUMAR, J. AND HON’BLE K.V. VISWANATHAN,
JJ.)
M/S ABCI
INFRASTRUCTURES PVT LTD
Petitioner
VERSUS
UNION OF INDIA
Respondent
Civil
Appeal No. OF 2025 (Arising out of Special Leave Petition (Civil) No. 25394 of
2023)-Decided on 14-02-2025
Civil,
Tender
Indian Contract Act,
1872, Section 20 – Tender - Error in bid amount – Forfeiture bid security - Whether BRO was justified in
accepting the bid of Rs.1,569, and on the failure of the Appellant to execute
the agreement asking for forfeiture vide encashment of bank guarantee of
Rs.15,04,64,000/? – Held that the present case does not fall under any exception,
for the error or mistake in quoting a price of Rs.1,569/-, does not require any
argument and cannot be debated as it is self-evident - A contract of this
nature for an estimated value of more than Rs.1,500 crores spread over 48
months requiring construction of roads and tunnels of the length of more than 4
kilometres in a hilly terrain can never be executed for a mere Rs.1,569/- -
Submission of BRO agreed to that the
Appellant was at fault and had made the mistake, of having failed to add the
required zeros in the financial bid - The claim BRO encashing the bank
guarantee by citing delays caused by issuing a second notice held to be baseless, as BRO was aware of the
Rs.1,569/- error - Instead of declaring the bid non est due to the clear
mistake, BRO asked the appellant to justify the bid, cancelled the notice,
declared the Appellant a defaulter, invoked the bank guarantee, and issued a
fresh notice inviting bids - BRO’s claim
that the delay was entirely due to the Appellant’s mistake is flawed, ignoring
BRO’s own lapses - The alleged two-month
delay by the Appellant held to be incorrect - The error, submitted on
03.06.2023, became apparent only when financial bids were opened on 24.08.2023
- The Appellant promptly acknowledged the mistake on 25.08.2023 - A fresh tender was issued, and financial bids
opened on 09.01.2024 revealed the lowest bid of Rs.1,290 crores, lower than the
earlier Rs.1,351 crores – Appellant directed to pay Rs.1 crore to BRO, as a
consequence of their error - Upon receiving this payment, BRO shall return the
Appellant’s original bank guarantee or demand draft of Rs.15.04 crores within
one week - Impugned judgment set aside, and the appeal is allowed in the
aforesaid terms.
(Para
10 to 17)
JUDGMENT
Sanjiv Khanna, Cji. :- Leave granted.
2.
This is an avoidable litigation. No doubt, there was a mistake on the part of
the Appellant – M/s ABCI Infrastructure Private Limited, albeit, instead of
taking a pragmatic approach, Respondent No. 2 - Border Road Organisation[Hereinafter, “BRO.”] under the Ministry
of Defence, Union of India, adopted an obdurate and overly legalistic stance,
causing a delay in the project's execution.
3.
We begin by briefly discussing the facts of the case:
o On 23.02.2023, BRO
invited bids for the design and construction of two-lane twin tunnels,
approximately 4.1 kilometres long, at Shinkun La Pass, including civil,
electrical, and mechanical work, with approaches connecting the Darcha-Padam
Highway to NHDL specifications in Himachal Pradesh and Ladakh. The estimated
cost of the project was Rs.15,04,64,00,000/- (Rs. 1,504.64 crores). The project
was to be completed within 48 months. The bid security amount was
Rs.15,04,64,000/- (Rs. 15.04 crores)
o Ten bidders,
including the Appellant, had submitted their online Technical and Financial
Bids on 03.06.2023. The Appellant, like others, had furnished a bank guarantee
of Rs.15,04,64,000/-.
o On 05.06.2023,
technical bids were opened and seven bidders, including the Appellant, were
declared technically qualified.
o On 24.08.2023, the
financial bids of seven bidders, including the Appellant, were opened and the
results were declared.
o The Appellant was
ranked as L-1 bidder, with the bid price of Rs.1,569/- (Rupees One thousand
five hundred and sixty-nine only). According to the Appellant, they had quoted
a bid price of Rs.1,569 crores. However, due to what they claim was a system
error, the quoted amount appeared as just Rs.1,569.
o The Appellant claims
that they discovered the mistake on 24.08.2023 when the financial bids were
opened and announced, and therefore, on the next day, 25.08.2023, they informed
the authorities that their actual bid was Rs.1,569 crores, not Rs.1,569. They
attributed the error to a typographical mistake or a critical technical issue
with the server. While we would not accept the plea of system error, the figure
quoted was clearly unrealistic, a patent error and a mistake given the scale
and nature of the work tendered. Though the mistake was bald-faced, what
followed is incomprehensible, with BRO, insisting on accepting the bid, in
spite of letters from the Appellant wanting to withdraw from the tender.
o BRO, guided by the
Evaluation Committee, instead of accepting the obvious, vide letter dated
26.08.2023, called upon the Appellant to justify the quoted amount of Rs.1,569
by providing a detailed price analysis, including the scope of work, completion schedule,
risk allocation, safety requirements, and proof of capability to complete the
project, by 31.08.2023.
o On 30.08.2023, the
Appellant reiterated that their intended bid was Rs.1,569 crores, not Rs.1,569,
attributing the error to a technical or typographical mistake.
o On 07.09.2023, the
Appellant sent another letter stating they should not be considered the L1
bidder, and the bank guarantee of Rs.15,04,64,000 may be returned to them
without encashment.
o On 12.09.2023, the
Appellant again wrote emphasizing that the bid was an error and that the bid
security should not be forfeited.
o Vide letter
16.09.2023, BRO, unmoved, wrote to the Appellant’s bank, the State Bank of
India, stating that the Appellant had been declared a defaulter, and their bid
security was to be forfeited. The bank was asked to encash the bank guarantee
and remit Rs.15,04,64,000 to BRO.
o The Appellant filed
a writ petition before the High Court of Himachal Pradesh at Shimla, which
stands dismissed by the impugned judgment dated 07.10.2023.
4.
The short question before us is whether BRO was justified in accepting the bid
of Rs.1,569, and on the failure of the Appellant to execute the agreement
asking for forfeiture vide encashment of bank guarantee of Rs.15,04,64,000.
5.
A mistake may be unilateral or mutual, but it is always unintentional. If it is
intentional, it ceases to be a mistake. Mistakes or errors, though avoidable,
are committed inadvertently. They have varied consequences in law. As per
Section 20 of the Indian Contract Act, 1872[Hereinafter,
“Contract Act.”] whereby both
parties to an agreement are under a mistake as to matter of fact essential to
an agreement, the agreement is void. The explanation to Section 20 says that an
erroneous opinion as to the value of the thing which forms the subject matter
of an agreement is not deemed to be a mistake as a matter of fact. This will
not be a case covered by Section 20 of the Contract Act. However,
this is not the first time that this question has arisen either before this
Court or Courts outside of India. In West Bengal State Electricity
Board v. Patel Engineering Company Limited and Others[(2001) 2 SCC 451.], this Court referred to paragraph 84 of
American Jurisprudence (2nd Edition, Volume 64 at page 944), which reads:
“As a general rule,
equitable relief will be granted to a bidder for a public contract where he has
made a material mistake of fact in the bid which he submitted, and where, upon
the discovery of that mistake, he acts promptly in informing the public
authorities and requesting withdrawal of his bid or opportunity to rectify his
mistake particularly when he does so before any formal contract is entered into.”
6.
Thereafter, reference was made to two decisions of the Supreme Court of the
United States in Moffett, H. and C. Co. v. Rochester[178 U.S. 373 (1900).] and Hearne v. New England Marine Ins. Co. [22 L. Ed. 395.] wherein it is observed
that where the mistake is apparent and the party promptly informs the other as
soon as it is discovered but before entering into a contract, equitable orders
may be passed. However, the mistake should be clear, explicit, and undisputed.
Further, a mistake on one side may be a ground for rescinding but not for
reforming a contract where the minds of the parties have not met, yet there is
no contract and hence none to be rectified. Relief may not be granted where it
is inequitable. While accepting this legal position, this Court
in West Bengal State Electricity Board (supra) has propounded the
following exceptions to the general principle on a person seeking relief in
equity on account of mistake:
“ 27. ……..
(1)Where the mistake
might have been avoided by the exercise of ordinary care and diligence on the
part of the bidder; but where the offeree of the bid has or is deemed to have
knowledge of the mistake, he cannot be permitted to take advantage of such a
mistake.
(2) Where the bidder
on discovery of the mistake fails to act promptly in informing to the authority
concerned and request for rectification, withdrawal or cancellation of bid on
the ground of clerical mistake is not made before opening of all the bids.
(3) Where the bidder
fails to follow the rules and regulations set forth in the advertisement for
bids as to the time when bidders may withdraw their offer; however where the
mistake is discovered after opening of bids, the bidder may be permitted to
withdraw the bid.”
7.
This judgment also refers to a decision of the Superior Court of New Jersey in
Spina Asphalt Paving Excavating Contractors, Inc. v. Borough of Fairview. [304 NJ Super 425.] The said case is
related to the rectification of mistakes in the bid specifications. Relief
granted in the said case was upheld by the Superior Court with the caution that
generally an error in the statement of a price would not be treated as
immaterial and it is only when the case of error was patent and the true intent
of the bidder obvious that such an error might be disregarded.
8. In West
Bengal State Electricity Board (supra), the private party, the bidder did
not succeed for several reasons, including the factum that the error was not
obvious and self-evident. Further, the correction of such mistakes after one and
a half months after the opening of the bids would have violated the express
clauses relating to the computation of the
bid amount. Thus, waiver of the rule or conditions in favour of the one bidder
would have created unjustifiable doubts in the minds of others impairing the
rule of transparency and fairness and providing room for manipulation for
awarding contracts.
9.
The decision in West Bengal State Electricity Board (supra) was
referred to and followed where a relief to the bidder was apparent before this
Court in M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines
and Geology, BBSR & Ors. [2024 INSC
520.] This decision observes that while the Court must exercise a lot
of restraint in exercising the power of judicial review in contractual commercial
matters, the doctrine of proportionality nevertheless applies when the error or
mistake is writ large and equity merits the grant of some
relief. Reference was made to the decision in Coimbatore District
Central Cooperative Bank v. Coimbatore District Central Cooperative Bank
Employees Association and Another[(2007)
4 SCC 669.] where discussing the question of proportionality or
punishment imposed on the striking workmen it is observed:
“18. “Proportionality”
is a principle where the court is concerned with the process, method or manner
in which the decision-maker has ordered his priorities, reached a conclusion or
arrived at a decision. The very essence of decision-making consists in the
attribution of relative importance to the factors and considerations in the
case. The doctrine of proportionality thus steps in focus true nature of
exercise—the elaboration of a rule of permissible priorities.
19. de Smith states
that “proportionality” involves “balancing test” and “necessity test”. Whereas
the former (balancing test) permits scrutiny of excessive onerous penalties or
infringement of rights or interests and a manifest imbalance of relevant
considerations, the latter (necessity test) requires infringement of human
rights to the least restrictive alternative. [Judicial Review of Administrative
Action (1995), pp. 601-05, para 13.085; see also Wade & Forsyth:
Administrative Law (2005), p. 366.]
20. In Halsbury's Laws
of England (4th Edn.), Reissue, Vol. 1(1), pp. 144-45, para 78, it is stated:
“The court will quash
exercise of discretionary powers in which there is no reasonable relationship
between the objective which is sought to be achieved and the means used to that
end, or where punishments imposed by administrative bodies or inferior courts
are wholly out of proportion to the relevant misconduct. The principle of
proportionality is well established in European law, and will be applied by
English courts where European law is enforceable in the domestic courts. The
principle of proportionality is still at a stage of development in English law;
lack of proportionality is not usually treated as a separate ground for review
in English law, but is regarded as one indication of manifest
unreasonableness.”
Accordingly,
in the said case the Appellant was directed to make a payment of Rs.3 crores
within the stipulated period and on the said payment the security deposit
in the form of a bank guarantee of over Rs.9 crores was directed to be
refunded.
10.
The present case does not fall under any exception, for the error or mistake in
quoting a price of Rs.1,569/-, does not require any argument and cannot be
debated as it is self-evident. A contract of this nature for an estimated value
of more than Rs.1,500 crores spread over 48 months requiring construction of
roads and tunnels of the length of more than 4 kilometres in a hilly terrain
can never be executed for a mere Rs.1,569/-.
11.
At the same time, we agree with BRO, that the Appellant was at fault and had
made the mistake, of having failed to add the required zeros in the financial
bid. The plea of a system glitch should not be accepted, as others had
successfully uploaded their bids without a problem.
12.
BRO justified encashing the bank guarantee by citing delays caused by issuing a
second notice inviting bids. This claim is baseless, as BRO was aware of the
Rs.1,569/- error. Instead of declaring the bid non est due to the clear
mistake, BRO asked the appellant to justify the bid, cancelled the notice,
declared the Appellant a defaulter, invoked the bank guarantee, and issued a
fresh notice inviting bids.
13.
Thus, BRO’s claim that the delay was entirely due to the Appellant’s mistake is
flawed, ignoring BRO’s own lapses. Mistakes, including by authorities, should be
resolved through corrective steps. A practical approach could have avoided the
delay, which was caused by BRO’s refusal to acknowledge the Appellant’s genuine
error and the unwarranted cancellation of the bid.
14.
The alleged two-month delay by the Appellant is incorrect. The error, submitted
on 03.06.2023, became apparent only when financial bids were opened on
24.08.2023. The Appellant promptly acknowledged the mistake on 25.08.2023.
15.
A fresh tender was issued, and financial bids opened on 09.01.2024 revealed the
lowest bid of Rs.1,290 crores, lower than the earlier Rs.1,351 crores. Thus,
while delayed, the contract was awarded at a lower cost.
16.
In view of the aforesaid discussion, we direct the Appellant to pay Rs.1 crore
to BRO, as a consequence of their error. Upon receiving this payment, BRO shall
return the Appellant’s original bank guarantee or demand draft of Rs.15.04
crores within one week.
17.
The impugned judgment is set aside, and the appeal is allowed in the aforesaid
terms. There would be no order as to costs.
------