2025 INSC 207
SUPREME COURT OF INDIA
(HON’BLE SURYA
KANT, J. AND HON’BLE UJJAL BHUYAN, JJ.)
M/S. TOMMORROWLAND
LIMITED
Petitioner
VERSUS
HOUSING AND URBAN
DEVELOPMENT & ANR.
Respondent
Civil
Appeal No. 2531 of 2025 (Arising out of SLP (C) No. 34338 OF 2016)-Decided on
13-02-2025
Civil, Specific Performance
(A) Specific Relief
Act, 1963, Section 34 – Specific Performance - Suit
for declaration –
Allotment of Whether Respondent No. 1/HUDCO was in breach of its reciprocal
contractual obligations qua the Appellant? – Held that Respondent No. 1 was in
breach of several obligations as contemplated in the Allotment Letter, viz.
failure to execute documents for securing approval under the ULCR Act and the
IT Act; failure to execute the sub lease agreement in favour of the Appellant
and; failure to secure the approval of the revised layout plan for the
construction of the hotel.
(Para 29, 42)
(B)
Specific Relief Act, 1963, Section 34 – Suit for declaration - Refund of the
forfeited amount - Whether
the Appellant is entitled to a refund of the forfeited amount under Clause
5(vi) of the Allotment Letter? – Clause 5 (vi) of the Allotment Letter, which
deals with the monies paid by the Appellant, provides that Respondent No. 1
will execute all required documents to obtain approval from the Competent
Authority under the ULCR Act and also from the Appropriate Authority
as envisaged in Chapter XX C of the IT Act, failing which, Respondent No.
1 will refund the amount paid without any interest. That being the case, it is
imperative to maintain the sanctity of the terms of the agreement between the
parties. It is a settled position of law that a commercial document ought not
to be interpreted in a manner that arrives at a complete variance with what may
originally have been the intention of the parties. As a result, we hold that
Respondent No. 1 is liable to refund the amount of Rs. 28,11,31,939 (First
instalment of Rs. 27.04 Crores along with interest for three months amounting
to Rs. 1,04,81,939/- and Rs. 2.5 Lakhs towards maintenance corpus) deposited by
the Appellant pursuant to the Allotment Letter.
(Para 45 and 47)
(C)
Specific Relief Act, 1963, Section 34 – Civil Procedure Code, 1908, Section 34
- Suit for declaration - Refund of the forfeited amount – Interest claim -
Whether the Appellant is entitled to interest on refund of the forfeited
amount? – Held that Appellant is not entitled to any interest on the amount to
be refunded in terms of the Allotment Letter - The Appellant, of course, can
seek award of interest under Section 34 of the CPC, which inter alia
provides that “the court may, in the decree, order interest at such rate as the
Court deems reasonable to be paid on the principal sum adjudged from the date
of the suit to the date of the decree” - Appellant wanted to avoid the
jurisdiction of the High Court before whom they had failed to prove their bona
fides by not depositing the stipulated sum - Such demeanour not only raises
grave suspicions on the Appellant’s propriety, but also amounts to sheer abuse
of the process of law and a waste of precious judicial time - Even in the Second Suit, upon an objection raised
by the Union of India when the High Court directed the Appellant to deposit
requisite court fees, the Appellant abandoned the relief of possession of the
suit land to avoid payment of ad-valorem court fees - This again casts serious
aspersions on the bona fides and financial capabilities of the Appellant - The
material on record sufficiently indicates that the Appellant did not approach
the Court with clean hands and instead attempted to hoodwink the judicial
process by creating a facade to subterfuge their inability to meet their
contractual obligations - The intent of the Appellant throughout appears to be
that of prolonging the litigation to cloak its impecuniousness - Find the
instant case to be fit to justify a deviation from the established standards -
Appellant is not entitled to any discretionary relief of interest
under Section 34 of CPC.
(Para 48 to 60)
JUDGMENT
Surya Kant, J. :- Leave granted.
2.
The instant appeal preferred by M/s Tomorrowland Technologies Exports Limited
(formerly M S Shoes East Ltd.) is directed against the judgment dated
03.06.2016 (Impugned Judgment) passed by the High Court of Delhi (High Court)
in RSA No. 362/2014 whereby the concurrent findings returned by the courts
below have been set aside. Consequently, the Appellant’s suit seeking
declaratory relief has been dismissed for being not maintainable.
3. The
fulcrum of the dispute herein lies in respect of the forfeiture of the
Appellant’s payments by Respondent No. 1, namely the Housing and Urban
Development Corporation Limited (HUDCO), on account of non-performance of
contractual obligations by the Appellant. Before adverting to the respective
contentions of the parties, we deem it appropriate to briefly narrate the
factual background leading to the present appeal.
A.
FACTUAL BACKGROUND
4.
The sequence of events in the instant appeal commenced with the Ministry of
Urban Development, Government of India (MUD), i.e., Respondent No. 2 herein,
having decided in 1990 to develop an area of 71 acres of land located at
Andrew's Ganj, New Delhi, through Respondent No. 1. Bids were thus invited by
Respondent No. 1 for properties at Andrew’s Ganj inter alia offering:
(i) Land, which was to
be leased for 99 years, in order to establish a 5-star Hotel, along with an
already-built Car Park;
(ii) Nine Guest House
blocks, nine Restaurants, and 25 Shops already constructed by Respondent No. 1;
(iii) A Shopping
Arcade and;
(iv) A Cultural Centre to be built by the successful
bidder(s).
We
must underscore that the scope of the present appeal is restricted only to Item
No. (i) specified hereinabove, i.e. ‘land, which was to be leased for 99 years,
in order to establish a 5-star Hotel, along with an already-built Car Park’
(Subject Property). We further clarify that the conclusions drawn in the
instant appeal will have no bearing on the ongoing disputes in respect to the
other bids.
5.
Reverting to the facts, the Appellant seems to have emerged as the highest
bidder for the Subject Property after the conclusion of the bidding process. As
a result, Respondent No. 1 issued the allotment letter dated 31.10.1994
(Allotment Letter), on such terms and conditions as specified therein,
including the following:
5. “The broad terms and conditions for the allotment
are as follows:-
The 5-star hotel
building shall be constructed within the parameters of the approved overall
Urban Design Form after obtaining required approvals from the concerned local
authority and the Delhi Urban Arts Commission. The height coverage in basement
and such related development controls shall be as per the operative norms of
the statutory authorities.
You shall make the
payment of premium, i.e., consideration of Rs. 64.10 Cores (Rs. Sixty Four
Crores and ten lacs only) for the allotment of the Hotel site and Rs. 14.00
crores for the allotment of car parking space. The payment shall be made in the
following manner/stages:
(A) Hotel Site (Rs.
64.10 Crores)
(i) Within 4 weeks of
the date of this allotment letter (i.e. before 28.11.94) - 40% (Rs.
25,64,00,000)
(ii) Before the end of
one year of the date of this allotment letter (i.e. before 31.10.95) - 30% (Rs
19,23, 00,000)
(iii) Before the end
of two years of the date of this allotment letter (i.e. before 31.10.96) - 30%
(Rs. 19, 23,00,000)
------------------------
Rs. 64,10,00,000
------------------------
(B) Car Parking Space
(Rs. 14.00 Crores)
(i) Within four weeks
of the date of issue of allotment letter (i.e. before 28.11.94) - 10%
(Rs.1,40,00,000)
(ii) Before the end of
one year of the date of issue of the allotment letter (i.e. before 31.10.95) -
40% (Rs. 5,60,00,000)
(iii) Within four
weeks of issue of letter by HUDCO intimating that the services were ready for
being handing over - 50% (Rs.7,00,00,000)
------------------------
Rs. 14,00,00,000
------------------------
The above payments
shall be made through demand drafts drawn in favour of HUDCO payable at New
Delhi.
(iii) No interest will
be charged on payments made before the due dates stated above. In case of
default, interest shall be charged @ 16% p.a. for three months if the payment
is made after the due date. Additional penal interest @ 3% p.a. shall also be
charged on the interest for three months. Any delay beyond three months would entail
cancellation of allotment and/or forfeiture of the total amount deposited to
date.
(iv) You will be
required to complete the construction of the Hotel Site within three years of
the date of handing over possession of the Hotel Site on licence basis for
construction of the Hotel building as per terms and conditions contained in the
proforma of Agreement to Sub- lease, two copies of which are enclosed with this
allotment letter. In the event of non- completion of construction within the
stipulated time, HUDCO may consider granting extension if exceptional and
unavoidable circumstances have prevented you to complete construction within
the stipulated time. The decision of HUDCO regarding the existence of the
exceptional and unavoidable circumstances will be final and binding upon you.
In case the construction is not completed within the prescribed period or the
extended period as decided by HUDCO, HUDCO will have the right to take over the
land along with the unfinished building with materials, fixtures, if any, on
the site without payment of any compensation to you. Since the underground car
parking space will be made available to you in the adjacent building, you may
provide underground linkage from the hotel with the parking space. However,
cost of such linkages shall be borne by you.
(v) You shall not have
any right to sell, transfer, assign or otherwise parting with the possession
without the prior permission of Lessor/ HUDCO. You may also at the discretion
of HUDCO, be permitted to raise loan only for construction of the building and
equipment, to mortgage the premises subject to such terms and conditions
including recovery of 50% unearned increase in the value of this land as will
be laid down in the lease documents and subject to the first charge of HUDCO
for the unpaid cost of land for the hotel as well as other dues payable
hereunder.
(vi) Hudco will
execute all required documents for obtaining approval of the competent
authority under the Urban Land (Ceiling and Regulation) Act, 1976 and
also of the Appropriate Authority in terms of Chapter XX C of the Income
Tax Act. If these approvals are not accorded Hudco will refund the amount paid
without any interest and you shall not be entitled to claim any compensation
for damages.
(vii) You shall pay
annual ground rent at the rate of 2-1/2% of the premium for land for the Hotel
site land the proportionate cost of land underneath the car parking space from
the date of handing over of possession of the Hotel site and the car parking
space to you. The ground rent shall be revised periodically in accordance with
the terms and conditions of the sub lease deed.
(viii) Initially, the
Hotel site will be on a licence under an Agreement to Sub-lease and upon
fulfilment of the terms of the said agreement including payment of all dues,
perpetual sub- lease will be executed. The terms and conditions of the
perpetual sub-lease shall be as per the proforma duly approved by the Govt. of
India, a copy of which will be sent to you in due course.
(ix) Upon the receipt
of the first instalment of the premium both for the Hotel site as well as the
car parking space as indicated in para 5(ii) and also after receipt of
approvals as indicated in para 5(vi), the Agreement to Sub-lease will be made
available to you for execution for the Hotel site and upon its execution, the
possession of Hotel Site will be handed over to you for raising construction.
(x) All costs for the
preparation of required documents, stamp duty, registration charges and other
levies of any kind whatsoever will have to be borne by you. Property taxes and
other municipal levies shall borne by you from the date of possession of the
site(s)”.
[Emphasis
supplied]
6.
The Appellant duly deposited the first instalment of Rs. 27.04 Crores along
with interest at the rate of 16.48% for three months, amounting to Rs.
1,04,81,939, as per Clause 5(A) of the Allotment Letter. In addition, the
Appellant also deposited a sum of Rs. 2.5 Lakhs towards the maintenance corpus.
As such, the total amount paid by the Appellant was admittedly Rs.
28,11,31,939.
7.
Subsequently, a dispute arose between the parties; purportedly on account of
the Appellant’s assertion: that in terms of the Allotment Letter, Respondent
No. 1 was obligated to execute certain documents after obtaining clearances
under the Income Tax Act, 1961 (IT Act) and the Urban Land (Ceiling
and Regulation) Act, 1976 (ULCR Act). Respondent No. 1 was further
obligated to execute an ‘agreement to sub-lease’ in favour of the Appellant.
The Appellant thus claimed that as per the terms and conditions of allotment,
the second and third instalments would have become due in favour of Respondent
No. 1, only in the event that the abovementioned documents were duly executed
by the latter.
8.
Thereafter, the Appellant sent letters to Respondent No. 1 requesting
compliance with the reciprocal contractual obligations enshrined in the Allotment
Letter. That being said, it is imperative to caveat at this juncture that
Respondent No. 1 was bereft of a perpetual lease to be executed in its favour
by MUD, and as such, was not in a position to execute the ‘agreement to
sub-lease’ in favour of the Appellant. Regardless thereto, Respondent No. 1
insisted on payment of the second and third instalments, and further sought to
threaten the Appellant that non-compliance with the payment schedule would
result in cancellation of the allotment in its favour.
9.
At this point, it is also relevant to bring on record that Ansal Properties
& Industries Limited (Ansals), who being the successful bidders for the
establishment of a Shopping Arcade (as enumerated in Item No. (iii) of
Paragraph 4), were allotted land in this regard as well as access to utilise
certain portion of the aforementioned Car Parking, which indubitably would have
to be shared with the Appellant. Pertinently, the Ansals also delayed the
payment of further instalments on the similar ground that the Car Park was
allegedly illegal/unauthorised. Pursuant thereto, the Ansals appear to have
been granted an interest-free extension of instalment payments by Respondent
No. 1.
10.
In these circumstances, the Appellant filed Suit No. 275/1996 before the High
Court (First Suit), seeking mandatory injunction against Respondent No. 1 to
extend the dates for payment of the second and third instalments until
Respondent No. 1 fulfilled its reciprocal obligations. The Appellant further
sought a permanent injunction to restrain Respondent No. 1 from cancelling its
allotment.
11.
The High Court passed a conditional status quo order on 31.01.1996 in the First
Suit, in terms whereof, the Appellant was directed to deposit Rs. 15 Crores by
08.04.1996, failing which such an order would stand automatically vacated. It
is not in dispute that the Appellant failed to deposit the aforesaid amount
even within the extended period. As a result, the status quo order stood
vacated.
12.
This followed an order by Respondent No. 1 issued on 02.05.1996, whereby the
allotment was cancelled and the entire amount of Rs. 28,11,31,939 was
forfeited.
13.
Respondent No. 1 thereafter invited fresh bids in November, 1996 for the
development of the Subject Property, this time disclosing in the bid that a
lease in its favour for the said land was yet to be executed. Additionally,
Respondent No. 1 also filed an application in the pending First Suit seeking
its dismissal on the ground that the proceedings had become infructuous, owing
to the cancellation of the allotment.
14.
The Appellant being aggrieved by the cancellation of their allotment filed a
fresh suit bearing Suit No. 1/1997 (Second Suit), changing the forum from the
High Court to Tis Hazari Courts, Delhi (Civil Court). In the Second Suit, the
Appellant sought a declaration that the cancellation of allotment by Respondent
No. 1 was illegal, null and void. They also consequently sought possession of
the Subject Property.
15.
Interestingly, the Appellant moved an application before the High Court for the
withdrawal of their First Suit, on the plea that the Second Suit had been filed
before the Civil Court on the basis of a fresh cause of action. The High Court
rejected the aforesaid application on 22.04.1997, citing that there were
several factual aversions made by the Appellant. Eventually, the First Suit was
dismissed as withdrawn unconditionally, upon the statement made by the
Appellant’s counsel before the High Court.
16.
In the meantime, Leela Hotels Limited (Leela) emerged as the highest bidder in
the fresh bid invited for the Subject Property, followed by allotment. Leela’s
allotment, however, was contingent on the outcome of the pending suit filed by
the Appellant. It is also relevant to note that the Respondent No. 2/MUD
executed the perpetual lease deed in favour of Respondent No. 1 on 04.07.1997.
17.
The Appellant, meanwhile, impleaded Respondent No. 2 as one of the defendants
in the Second Suit. The Respondent No. 2, in turn, filed an application
under Order VII Rule 11 of the Code of Civil Procedure, 1908 (CPC),
seeking rejection of the plaint based on the assertion that the Appellant had
allegedly not paid the requisite court fee. Though the Civil Court rejected
that application, the High Court thereafter, on revision, allowed the objection
raised by Respondent No. 2, holding that the Appellant was liable to pay court
fees based on the market value of the Subject Property.
18.
The Appellant, mirroring the characteristics of a chronic defaulter, this time
decided to evade the liability of paying the court fee by abandoning the relief
of delivery of possession. Resultantly, the Appellant restricted the relief in
the Second Suit only to a declaration that the cancellation of the allotment by
Respondent No. 1 was null and void.
19.
The Civil Court eventually decreed the Second Suit vide judgment dated
03.07.2010, inter alia, holding that: (i) Respondent No. 1 was guilty of
committing a breach of the terms of allotment; (ii) the Appellant was
discriminated against and was denied parity with the Ansals; and (iii) a
declaration under Section 34 of the Specific Relief Act, 1963 (SR
Act) to the effect that the cancellation letter was null, void, and inoperative
is warranted on account of the concealment and gross misrepresentation of facts
by Respondent No. 1.
20.
Respondent No. 1 unsuccessfully laid challenge to the judgment and decree dated
03.07.2010, as the First Appellate Court dismissed the Regular First Appeal
vide judgment dated 18.07.2014, reiterating the same grounds.
21.
Still aggrieved, Respondent No. 1 preferred a Regular Second Appeal before the
High Court, which was allowed vide the Impugned Judgment dated 03.06.2016.
Notably, the High Court overturned the concurrent findings of the courts below,
and has inter alia observed that the Appellant admittedly did not have
sufficient funds and, thus, wanted to prolong the litigation. The High Court
further held that:
“39. … the suit filed
by the Appellant suffered from a fatal defect of not claiming possession as a
further relief in terms of proviso to Section 34 of the Specific
Relief Act, and therefore the decree seeking only declaration to the effect
that the cancellation letter dated 02.05.1996 was bad in law could not have
been passed by the courts below”.
Additionally, the High
Court went on to observe that the grant of declaration under Section 34 of the
SR Act, being a discretionary relief, cannot be bestowed upon a party who
indulges in ‘sharp’ practices. Hence, this appeal.
B.
CONTENTIONS ON BEHALF OF THE APPELLANT
22.
Shri Tejinder Singh Dhindsa, learned Senior Counsel, representing the Appellant
has painstakingly taken us through the voluminous material placed on record. He
contended that the High Court has committed grave error in upsetting the
concurrent finding of fact arrived at by the courts below.
23.
Shri Dhindsa advanced the following submissions on behalf of the Appellant to
challenge the Impugned Judgment:
a) At the time of
allotment of the Subject Property, Respondent No. 1 failed to disclose that it
had no subsisting lease in its favour to execute the sub-lease in favour of the
Appellant. As such, it is a clear case of misrepresentation on the part of
Respondent No. 1.
b) After payment of
the first instalment by the Appellant, Respondent No. 1 was obligated to
execute the ‘agreement to sub-lease’ in favour of the Appellant and further
execute documents for obtaining statutory approvals under the ULCR Act and IT
Act. However, Respondent No. 1 failed to execute these documents in the absence
of a perpetual lease in its favour. There was, thus, no contractual obligation
on the Appellant to pay further instalments.
c) The High Court
erroneously held that the Second Suit filed by the Appellant suffered from a
fatal defect of not claiming possession as a further relief in terms of the
proviso to Section 34 of the SR Act. The High Court in this regard overlooked
the fact that possession could be sought from Respondent No. 1 only after the
execution of the sub-lease agreement, which was admittedly not done at the time
of filing of the Second Suit. For this reason, the Appellant gave up the
consequential relief of possession in the Second Suit, and it would be unfair
to non-suit the Appellant on this ground.
d) After the Subject
Property was allotted to Leela under the subsequent bidding process, a dispute
arose between Respondent No. 1 and Leela on account of failure of the former to
disclose that the revised layout plan was yet to be approved by the Competent
Authority. The said dispute was adjudicated by an Arbitrator directing refund
of the entire sum paid by Leela, along with 20% interest. That Award attained
finality, except that the rate of interest was reduced to 18% by this Court.
The Appellant being similarly placed, therefore, deserved to be treated at par
with Leela.
e) The treatment meted out to the Appellant
was discriminatory when juxtaposed with the Ansals, who were granted repeated
interest-free extensions for paying the second and third instalments, in
regards to the shared Car Parking. Conversely, the Appellant was compelled to
pay instalments as per the payment schedule and was threatened with
cancellation of the allotment in the event of default.
f) The forfeiture of
the amount paid by the Appellant towards the first instalment was done on account
of misconstruction and selective reading of the mutual obligations emanating
from the Allotment Letter and not on account of any actual loss suffered by
Respondent No. 1.
24.
Alternatively, Shri Dhindsa submitted that since considerable time has passed
following the allotment and its cancellation, it would be in the interests of
justice and equity to entertain the Appellant’s limited relief for return of
Rs. 28,11,31,929 along with the applicable rate of interest.
25.
Ms. Meenakshi Arora, learned Senior Counsel appearing on behalf of Respondent
No. 1, contrarily opposed the Appellant’s prayer inter alia and vehemently
contended that not only did they fail to comply with the terms and conditions
of the Allotment Letter but that the Appellant had disqualified itself from any
relief on account of its deceitful, unfair and unethical conduct.
26.
Ms. Arora canvassed the following grounds in support of her submissions:
a) The Appellant
defaulted on the payment schedule stipulated in the Allotment Letter, resulting
in a breach of contractual obligations. As a result, Respondent No. 1 exercised
its contractual right by cancelling the allotment in favour of the Appellant
and forfeited the deposited amount, as envisaged in Clause 5(iii) of the
Allotment Letter. The operation of the aforementioned Clause is not interlinked
or contingent on any other clause of the Allotment Letter and therefore, non
payment of the instalment is bound to entail cancellation of the allotment and
forfeiture of the deposited amount.
b) The Second Suit
filed by the Appellant was barred under Order II Rule 2 of the CPC,
considering the cause of action of both the suits was one and the same, and
also because the Appellant relinquished a portion of the claim which they could
have sought in the First Suit itself.
c) The Second Suit was
also barred in view of Clause (3) of Rule 1 of Order XXIII of the CPC,
since in the First Suit which was unconditionally withdrawn by the Appellant,
the High Court did not grant any liberty therein to institute a fresh suit.
d) The Appellant in
the Second Suit, while seeking declaratory relief of the cancellation of
allotment being null and void, abandoned the consequential relief of possession
in order to avoid paying court fees. Such a recourse defies the proviso to
Section 34 of the SR Act, which mandates that consequential relief be sought
along with a declaratory decree. Hence, the High Court has rightly held that
the Second Suit was non- maintainable.
e) The Appellant
brazenly attempted to overreach the judicial process; indulge in forum shopping
and finagle the judicial process. This is writ large from: (i) the Appellant
dishonouring the High Court’s direction to deposit Rs. 15 Crores for
continuation of the order of status quo; (ii) the First Suit being withdrawn
due to forum non conveniens; (iii) the Second Suit being crafted with a view to
change the forum from the High Court to the Civil Court; (iv) the relief of
possession being abandoned to avoid payment of court fees as the entire lis was
speculative for the Appellant; and (v) non-payment of further instalments and
failure to perform reciprocal obligations such as securing statutory approvals.
f) Unlike the Appellant, the Ansals had
secured approval from the Income Tax authorities, whereas the Appellant did not
take any steps to do so, despite categorical assertions in the Allotment
Letter. Hence, no parity with the Ansals can be claimed when the Appellant
never demonstrated any willingness to honour their obligations.
27.
In essence, Ms Arora contended that the conduct of the Appellant throughout has
been to prolong the litigation and entangle Respondent No. 1 in vexatious
litigation. She thus maintained that the High Court has rightly reversed the
findings of the courts below or that the Appellant is not entitled to any
discretionary relief under Section 34 of the SR Act.
28.
Ms. Aishwarya Bhati, learned Additional Solicitor General of India, on behalf
of Respondent No. 2 reiterated the contentions put forth by Ms. Arora. She
further fairly submitted that if this Court fixes any liability on Respondent
No. 1 to refund the forfeited amount, it is inter-se the Respondents to comply
with such direction. Ms Bhati maintained that Respondent No. 1 has sufficient
assets to meet any liability imposed by this Court.
D.
ISSUES FOR CONSIDERATION
29.
In our considered view, the salient issues that arise for our consideration can
be summed up as follows:
(a) Whether Respondent No. 1/HUDCO was in
breach of its reciprocal contractual obligations qua the Appellant?
(b) If so, whether the
Appellant is entitled to a refund of the forfeited amount under Clause 5(vi) of
the Allotment Letter?
(c) If Issue (b) above
is answered in the affirmative, whether the Appellant is entitled to interest
on refund of the forfeited amount?
E.
ANALYSIS E.
1
Whether Respondent No. 1/HUDCO was in breach of its reciprocal contractual
obligations qua the Appellant?
30.
We have carefully perused the terms and conditions of the Allotment Letter and
find that there are several reciprocal obligations placed upon the Appellant
and Respondent No. 1.
31.
First, a bare reading of the relevant recitals in the Allotment Letter
extracted at Paragraph 5 above, leaves no room to doubt that Clause 5(vi)
obligates Respondent No. 1 to ‘execute all required documents for obtaining
approval of the competent authority under the Urban Land (Ceiling and
Regulation) Act, 1976 and also of the Appropriate Authority in terms
of Chapter XX C of the Income Tax Act’. In fact, in the event of failure
to do so this very Clause also necessitates that Respondent No. 1 ‘will refund
the amount paid without any interest and you shall not be entitled to claim any
compensation for damages’.
32.
Though Respondent No. 1 has, in this regard, attempted to wriggle out of its
obligations on the premise that it could only assist the Appellant in executing
the necessary documents, we do not find any merit in such submission. We say so
for the reason that had it not been obligatory on Respondent No. 1 to execute
the necessary documents under the first part of Clause 5(vi), the second part
thereof would not have mandated refund of the amount paid by the successful bidder.
It seems to us that since the failure to secure approval of the Statutory
Authorities and resultant execution of requisite documents has necessary
consequences of refund of the amount paid, the first part of Clause 5(vi) is
mandatory in nature. Respondent No. 1 therefore cannot be allowed to shirk its
responsibility and leave the Appellant at the mercy of the Statutory
Authorities for such approvals.
33.
That being the clear intent of the relevant terms and conditions of the
Allotment Letter as well as the supporting material placed on record, we are of
the considered opinion that Respondent No. 1 was in breach of its contractual
duty under Clause 5(vi) of the Allotment Letter.
34.
Second, a conjoint reading of Clauses 5(viii) and (ix) of the Allotment Letter
postulates an unambiguous promise on the part of Respondent No. 1: that upon
receipt of the first instalment and on grant of approvals by the Statutory
Authorities, an ‘agreement to sub-lease’ will be executed by Respondent No. 1,
followed by handing over of possession of the Subject Property to the
Appellant.
35.
As held earlier, Respondent No. 1, even after the receipt of the first
instalment, did not take any tangible steps to secure the necessary statutory
approvals. It is obvious that the said failure led to breach of Clause 5(viii)
and (ix) also, as admittedly, no ‘agreement to sub- lease’ was executed in
favour of the Appellant, owing to the non- execution of a perpetual lease by
Respondent No. 2 in favour of Respondent No. 1. Nonetheless, we proceed to
examine the contention of the Appellant that Respondent No. 1 also concealed
the fact that it did not have the title and authority to execute the ‘agreement
to sub-lease’ in favour of the Appellant.
36.
The Appellant’s plea to this effect is fortified by the contents of long drawn
correspondence, including letters dated 03.01.1995, 24.01.1995, 03.03.1995, and
29.03.1995, whereby Respondent No. 1 had been requesting Respondent No. 2 to
execute the perpetual lease deed in its favour, in absence whereof, no
sub-lease could be executed in favour of the Appellant.
37.
The other cascading effect of non-execution of perpetual lease in favour of
Respondent No. 1, or sub-lease in favour of the Appellant, was that the
possession of the Subject Property could not have been handed over to the
Appellant. Admittedly, the perpetual lease deed in favour of Respondent No. 1
was executed only after the cancellation of allotment in favour of the
Appellant, belatedly on 04.07.1997.
38.
Our attention was also drawn towards several legal opinions and internal
documents of Respondent No. 2 and the Ministry of Law & Justice in the
context of the underlying bid dispute. While we do not intend to delve into
these documents, we cannot be ignorant of the fact that these records tend to
support the claim of the Appellant that Respondent No. 1 could not furnish the
sub-leasing arrangements until the perpetual lease was executed in its favour.
39.
As such, Respondent No. 1 being incapable of fulfilling its reciprocal
promises, was not entitled to demand payment for the second instalment until
the perpetual lease deed was executed in its favour. We therefore hold that
Respondent No. 1’s failure to execute the sub-lease in favour of the Appellant,
owing to the lack of its authority and title, also amounts to a breach of their
contractual obligations.
40.
We may hasten to add that besides the breach of aforementioned contractual
obligations, it seems that Respondent No. 1 did not have the necessary
sanctions permitting construction of the 5-star Hotel at the site. This fact
came to light only after Leela succeeded in getting an Arbitration Award in its
favour, on account of alleged failure of Respondent No. 1 to disclose that the
revised layout plan of the Subject Property was yet to be approved.
41.
Furthermore, there is some merit in the Appellant’s grievance of differential
treatment when compared to the Ansals. As noted earlier, the Ansals were
granted an interest-free extension for the pending instalments under similar
circumstances, but the request of the Appellant was declined. It is difficult
to comprehend as to how granting the same relief to the Appellant would have
been detrimental to the interest of Respondent No. 1, when such a relief was
granted to another similarly placed party.
42.
As an upshot of the foregoing, we have no doubt in our mind that Respondent No.
1 was in breach of several obligations as contemplated in the Allotment Letter,
viz. failure to execute documents for securing approval under the ULCR Act and
the IT Act; failure to execute the sub lease agreement in favour of the
Appellant and; failure to secure the approval of the revised layout plan for
the construction of the hotel.
E.
2 Whether the Appellant is entitled to a refund of the forfeited amount?
43.
Having held that Respondent No. 1 has breached its contractual obligations, we
now proceed to determine the Appellant's entitlement to refund of the forfeited
amount. We may clarify here that during the course of oral arguments, the
Appellant sought a refund of the forfeited amount along with reasonable
interest. However, in the written submissions, the Appellant, while reiterating
their stance, has sought a refund of Rs. 28,11,31,929 along with interest from
the date of payment at the rate of 16.48%, i.e., the contractual rate of
interest charged by Respondent No. 1.
44.
Clause 5 (vi) of the Allotment Letter, which deals with the monies paid by the
Appellant, provides that Respondent No. 1 will execute all required documents
to obtain approval from the Competent Authority under the ULCR
Act and also from the Appropriate Authority as envisaged in Chapter
XX C of the IT Act, failing which, Respondent No. 1 will refund the amount paid
without any interest.
45.
The contents of the above clause unequivocally enumerate that the parties had
ample knowledge of the obligation cast upon Respondent No. 1 to refund the
amounts paid by the Appellant, in case statutory approvals were not accorded.
Significantly, the said clause also provides that such a refund will be without
any interest or claim of compensation for damages.
46.
We have already held in Issue No. E. 1 of this judgment that Respondent No. 1
was in breach of several obligations as contemplated in the Allotment Letter.
47.
That being the case, it is imperative to maintain the sanctity of the terms of
the agreement between the parties. It is a settled position of law that a
commercial document ought not to be interpreted in a manner that arrives at a
complete variance with what may originally have been the intention of the
parties. As a result, we hold that Respondent No. 1 is liable to refund the
amount of Rs. 28,11,31,939 (First instalment of Rs. 27.04 Crores along with
interest for three months amounting to Rs. 1,04,81,939/- and Rs. 2.5 Lakhs
towards maintenance corpus) deposited by the Appellant pursuant to the
Allotment Letter.
E.
3 Whether the Appellant is entitled to interest on refund of the forfeited
amount?
48.
Having held that Respondent No. 1 is liable to refund the principal sum, we may
now proceed to determine the Appellant's claim for interest on the amount
directed to be refunded. Evidently, the
Appellant is not entitled to any interest on
the amount to be refunded in terms of the Allotment Letter. The Appellant, of
course, can seek award of interest under Section 34 of the CPC, which
inter alia provides that “the court may, in the decree, order interest at such
rate as the Court deems reasonable to be paid on the principal sum adjudged
from the date of the suit to the date of the decree.”
49.
It is trite law that under Section 34 of the CPC, the award of
interest is a discretionary exercise steeped in equitable considerations. The
law in this regard has been succinctly discussed in the Constitution Bench
judgment of this Court in Central Bank of India v. Ravindra & Ors.;
(2002) 1 SCC 367, which states:
“Award of interest
pendente lite or post-decree is discretionary with the Court as it is
essentially governed by Section 34 of the CPC de hors the contract
between the parties. In a given case if the Court finds that in the principal
sum adjudged on the date of the suit, the component of interest is
disproportionate with the component of the principal sum actually advanced, the
Court may exercise its discretion in awarding interest pendente lite and
post-decree interest at a lower rate or may even decline to award such
interest. The discretion shall be exercised fairly, judiciously, and for not
arbitrary or fanciful reasons.”
[Emphasis
supplied]
50.
There is no gainsaying that the power to award interest ought to be exercised
judiciously, aligning with equitable considerations and also ensuring neither
undue enrichment nor unfair deprivation.
Courts are duty-bound to assess the facts and
circumstances of each case, applying the principles of fairness and justice.
This discretion must reflect a balanced approach, grounded in reason, and
guided by the overarching objective of equity.
51.
It is against this backdrop that the contentions of Respondent No. 1 concerning
the conduct of the Appellant become material. Respondent No. 1 has contended
that the Appellant’s actions demonstrate unscrupulous and evasive conduct,
apart from their financial incapability to honour the contractual obligations,
undermining the essence of the contract.
52.
It is not in dispute that in the First Suit, the High Court on 31.01.1996,
passed a status quo order against Respondent No. 1 conditionally, obligating
the Appellant to deposit Rs. 15 Crores by 08.04.1996. It was contemplated in
the order that if the Appellant fails to make the stipulated deposit, the
status quo order would stand vacated. Admittedly, despite seeking an extension
of 10 days, the Appellant failed to deposit Rs. 15 Crores and establish their
bona fides.
53.
Shortly after the vacation of the status quo order and cancellation of the
allotment, the Appellant sought to withdraw the First Suit which was pending
before the High Court under its original jurisdiction, instead of seeking
amendment of the plaint and the consequential relief(s) on the basis of
subsequent events. This was done with an oblique motive, as the Appellant did
not want to take a chance before the High Court whose order they had failed to
comply with. The Appellant thus withdrew the First Suit unconditionally even
without the liberty to file a fresh one, ostensibly with a calculated mindset.
54.
We have no hesitation in holding that such conduct was nothing short of a
brazen attempt at forum shopping, as the Appellant wanted to avoid the
jurisdiction of the High Court before whom they had failed to prove their bona
fides by not depositing the stipulated sum. Such demeanour not only raises
grave suspicions on the Appellant’s propriety, but also amounts to sheer abuse
of the process of law and a waste of precious judicial time.
55.
Even in the Second Suit, upon an objection raised by the Union of India when
the High Court directed the Appellant to deposit requisite court fees, the
Appellant abandoned the relief of possession of the suit land to avoid payment
of ad-valorem court fees. This again casts serious aspersions on the bona fides
and financial capabilities of the Appellant.
56.
The material on record sufficiently indicates that the Appellant did not
approach the Court with clean hands and instead attempted to hoodwink the
judicial process by creating a facade to subterfuge their inability to meet
their contractual obligations. We are constrained to observe that the intent of
the Appellant throughout appears to be that of prolonging the litigation to
cloak its impecuniousness.
57.
It needs no emphasis that whosoever comes to the court claiming equity, must
come with clean hands. The expression ‘clean hands’ connotes that the suitor or
the defendant have not concealed material facts from the court and there is no
attempt by them to secure illegitimate gains. Any contrary conduct must warrant
turning down relief to such a party, owing to it not acting in good faith and
beguiling the court with a view to secure undue gain. A court of law cannot be
the abettor of inequity by siding with the party approaching it with unclean
hands. This also brings to mind the oft-quoted legal maxim—he who seeks equity
must do equity.
58.
We are conscious of the fact that as a general principle, in commercial
disputes, the award of interest pendente lite or post- decree is typically
granted as a matter of course. This is because such interest serves to
compensate the aggrieved party for the time value of money that was due but
withheld during the legal process. It reflects an established norm aimed at
ensuring fairness and equity in commercial transactions.
59.
Having said so, we find the instant case to be fit to justify a deviation from
the established standards. In the facts and circumstances, though we have held
Respondent No. 1 to be in breach of several contractual obligations, the
conduct of the Appellant is rife with instances where it has also sought to
undermine the authority and integrity of the judicial process, by treating the
Court with disregard, and attempting to exploit procedural mechanisms for
personal gain. We, thus, hold that in view of the above reasons, the Appellant
is not entitled to any discretionary relief of interest under Section 34 of
CPC.
F.
CONCLUSION
60.
Striking a balance between these considerations, we deem it appropriate to
allow this appeal in part, and dispose of the same in the following terms:
(i) Respondent No.
1/HUDCO, was in breach of its reciprocal contractual obligations, thereby
disentitling them from forfeiting the monies already paid by the Appellant
towards the first instalment as enshrined in Clause 5 (iii) of the Allotment
Letter dated 31.10.1994.
(ii) Given that the Appellant has blatantly
engaged in forum shopping, and considering that their overall conduct does not
in any manner reflect an approach aligning with the clean hands doctrine, they
are not entitled to grant of any discretionary relief of interest in their
favour.
(iii) The Impugned
Judgement dated 03.06.2016 passed by the High Court is set aside to the extent
above.
(iv) The Second Suit
filed by the Appellant is decreed in part, and the Appellant is held entitled
to a refund of the principal amount, without any interest.
(v) As a sequel to the
above, we direct Respondent No. 1/HUDCO, to refund the amount of Rs.
28,11,31,939 to the Appellant within three (3) months from the date of this
order.
(vi) In the event
Respondent No. 1 fails to refund the amount within the stipulated time, the
Appellant shall be entitled to interest at the rate of 6% per annum till the
date of realisation.
61.
We find it necessary to clarify that the above-mentioned directions pertain
only to the Subject Property, i.e., land for the establishment of a 5-star
Hotel and the already built Car Park. We have not expressed any opinion on the
pending matters between the parties insofar as the other properties are
concerned. The other pending cases shall be decided by the concerned Court on
their own merit and in accordance with law.
62.
The appeal is disposed of in the above terms.
63.
Pending interlocutory applications are also disposed of in the above terms.
Ordered accordingly
------