2025 INSC 157
SUPREME COURT OF INDIA
(HON’BLE B.R.
GAVAI, J. AND HON’BLE K. VINOD CHANDRAN, JJ.)
D.M. JAGADISH
Petitioner
VERSUS
BANGALORE DEVELOPMENT
AUTHORITY
Respondent
Civil
Appeal No(S). ___________OF 2025 [@ SLP(C) NO.___________OF 2025 @ DIARY NO(S).
7824 of 2020]-Decided on 04-02-2025
Land
acquisition
Constitution of India,
Article 14 and 226 - Land acquisition – Exclusion of land from acquisition - Learned Single Judge
came to a specific finding that the land adjoining the appellant’s land was
excluded from the acquisition and as such, the appellant was also entitled to
the benefit of exclusion - It was also found that there were structures
existing on the land prior to the preliminary notification issued in 2003 -
However, the learned Single Judge took notice of the fact that out of the land
belonging to the appellant, 15 sites were already allotted to third parties -
The learned Single Judge, therefore, directed that the benefit of the quashing
of acquisition would not be applicable in the case of the 15 sites which were
already allotted to third parties - Division Bench in writ appeal found that it
appears that the constructions were either made after the preliminary
notification was issued or just before the issuance of preliminary notification
having gotten wind of the possible land acquisition proceedings - Insofar as the contention of the appellant
herein that the adjoining lands were already excluded from acquisition, the
Division Bench relied on an affidavit dated 12th September, 2019 sworn by the
Special Land Acquisition Officer, B.D.A. to come to a finding that the land on
the western side of the land of the appellants already stood acquired - Though the
said affidavit was filed on 12th September, 2019 the Division Bench, without
giving any opportunity to the appellant herein to respond to the said
affidavit, closed the matter for hearing on the very same day, though the
judgment was subsequently pronounced on 27th September, 2019 – Held that the approach of
the Division Bench in relying on the affidavit of the authority and closing the
matter on the same day, without giving an opportunity to the appellant herein
to meet the averments made in the said affidavit would be in violation of the
principles of natural justice - The well-reasoned order passed by the learned
Single Judge has been reversed by the learned Division Bench based on the
affidavit of the authority without giving an opportunity to the appellant
herein to meet the averments made therein –On this short ground alone, the
appeal deserves to be allowed and the impugned judgment and order liable to be
quashed and set aside - The matter is remitted back to the Division Bench of
the High Court to consider it afresh in accordance with law.
(Para
10 to 17)
JUDGMENT
B.R. Gavai, J. :- Delay condoned.
2.
Leave granted.
3.
This appeal challenges the judgment and order dated 27th September, 2019, vide
which the appeal filed by the respondent(s) came to be allowed.
4.
A preliminary notification dated 03rd February, 2003 in respect of 380 acres 4
guntas of land came to be issued. In the final notification dated 23 rd
February, 2004, out of the said 380 acres 4 guntas, the acquisition in respect
of 154 acres 26 guntas came to be dropped. The effect being the area
admeasuring 225 acres 18 guntas came to be covered under the final notification
for acquisition. A subsequent revised notification was issued on 18 th June,
2014. By the said notification a further area of 66 acres 3 guntas came to be
excluded from acquisition.
5.
The father of the appellant approached the High Court by way of Writ Petition
Nos.45695-697 of 2004 challenging the acquisition. The said writ petitions were
allowed, thereby quashing the acquisition. The same was challenged in appeal(s)
by the respondent(s). The Writ Appeal No.2624/2005 and 2625/2005 came to be
disposed of on 25th November, 2005. By the said judgment, the Division Bench,
while upholding the acquisition issued several directions to the respondent
No.1/B.D.A.
6.
It will be relevant to refer to the directions issued by the Division Bench in
the said order, which read thus:-
“(i) All the
petitioners who are the land owners who are seeking dropping of the acquisition
proceedings in so far as their respective lands are concerned, on the
ground that:
(a) their lands are
situated within green belt area;
(b) they are totally
built up;
(c) properties wherein
there are buildings constructed 'by charitable, educational and/or religious
institutions
(d) nursery lands;
(e) who have set-up
factories
(f) their lands are
similar to the lands which are adjoining their lands but not notified for
acquisition at all, are permitted to make appropriate application to the
authorities seeking such exclusion and exemption and producing documents to
substantiate their contentions within one month from the date of this order.
It is made clear that the
BDA shall consider such request keeping in mind the status of the land as on
the date of preliminary notification and to exclude any developments,
improvements, constructions put up subsequent to the preliminary notification
and then decide whether their cases are similar to that of the land owners
whose lands are notified for acquisition, notified and whose objections were
upheld and no final notification is issued. In the event the BDA comes to the
conclusion that the lands of those persons are similarly placed, then to
exclude those lands from acquisition.
(ii) Petitioners who
are interested in availing this benefit shall make appropriate application
within 30 days from the date of this order and thereafter the BDA shall
give notice to those persons, hear them and pass appropriate orders
expeditiously.
(iii) Till the
aforesaid exercise is undertaken by the BDA and the applications filed by the
petitioners either for allotment of site or for denotifying or exemption sought
for are considered their possession shall not be disturbed and the existing
construction shall not be demolished. After consideration of the applications,
in the light of the aforesaid directions, if the lands are not excluded then
the BDA is at liberty to proceed with the acquisition."
7.
It could thus be seen that the Division Bench had permitted such owners of the
land, whose lands were situated within the green belt where structures were
existing; where they were totally built up; where there were buildings
constructed by charitable, educational and/or religious institutions; nursery
lands; who have set-up factories and the lands adjoining the ones which were
excluded from acquisition, to make an application to the B.D.A. Such petitioners
who wanted to avail the benefit were required to make such applications within
30 days. The B.D.A. was thereafter required to give notice to those
persons, hear them and pass appropriate orders. Till the completion of such an
exercise, the possession of the landowners was not to be disturbed, and the
existing construction was not to be demolished.
8.
Pursuant to the aforesaid directions issued by the Division Bench, the
appellant made an application before the B.D.A. within the prescribed period
urging therein that the land abutting the land had been excluded from the
acquisition and as such, the appellant was also entitled to the benefit of
exclusion of his land from the acquisition. It is also contended that there
were structures existing on the land in question prior to the preliminary
notification being issued. The same was rejected by Respondent No.1/B.D.A. vide
endorsement dated 17th June, 2006. This was again challenged by a Writ Petition
No.13198 of 2006. On the second occasion also, the petition was allowed with
directions to the Land Acquisition Officer to conduct a spot inspection
and consider the claim of the appellant for exclusion of land. The Land
Acquisition Officer, though conducted the inspection, did not pass any orders.
As such, on the third occasion the appellant filed Writ Petition No.33136 of
2015.
9.
The learned Single Judge partly allowed the Writ Petition No. 33136 of 2015
vide judgment and order dated 3rd October 2017. It will be relevant to refer to
the following observations made by the learned Single Judge in the said order:
“11. There is nothing
to show that this exercise was done by the Land Acquisition Officer or by any
of the authorities of the B.D.A. They have not passed any order. They have
blindly proceeded to forward the entire papers to the State Government for
issuing the final notification. The State Government has accordingly issued the
impugned final notification. In the circumstances, petitioner is right and
justified in contending that the B.D.A. has not followed the directions of this
Court and this action has resulted in serious prejudice to the interests of the
petitioner.
12. Before issuing the
final notification, B.D.A. ought to have applied its mind to the
directions of the Division Bench followed by the directions issued by the
learned Single Judge and passed an order after conducting spot inspection. Therefore,
in normal circumstances, the final notification issued in so far as the land in
question is concerned has to be declared as having been vitiated. The fact
remains that thereafter the B.D.A. formed certain sites and as many as 15 sites
have been allotted in favour of third parties. They are not before this Court.
In respect of the remaining land it is urged by the counsel for the B.D.A. that
the sites have been formed. But, there is no dispute that no allotments have
been made to the third parties and the remaining property is kept intact. Therefore,
keeping in mind the interests of the third parties that have intervened, the
question for consideration in this petition is restricted to the remaining
extent of land so as to find out if petitioner is entitled for exclusion of the
same from acquisition by granting appropriate relief.
13. In this
connection, petitioner has produced Annexure J sketch and Annexure K map to
substantiate that the surrounding lands bearing Sy. Nos.63/1, 63/2, 63/3, 64/1
and 64/2 have been excluded from acquisition while issuing the impugned final
notification after considering the entitlement of those land owners as per the
directions issued by the Division Bench whereas the case of the
petitioners in respect of the very adjoining land bearing Sy. No.64/3 has not
been considered and without considering, notification acquiring the land has
been published. Indeed, this contention is probabalised and substantiated by
the very document produced by the respondents at Annexure R1. It is clear from
Annexure R1 sketch that lands lying towards the North, South and West abutting
Sy. No.64/3 have been excluded from acquisition. In respect of the eastern
portion wherein Sy. No.64/4 is situated, 1 acre 30 guntas have been included.
It is therefore clear that the case of the petitioner was eminently fit for
being considered favourably keeping in mind the parameters prescribed by the
Division Bench. In this connection, it has to be also stated that it is the
specific case of the petitioner that he had put up construction in the acquired
portion of the land. Indeed this is probabalized by the spot inspection
conducted on 27.12.2006, at an earlier point of time, pursuant to the
directions issued by this Court that there were two RCC constructions and one
bore-well. It is not the case made out by the B.D.A. that these constructions
have been put up after the preliminary notification was published. Nothing of
that sort emerges from the spot inspection though an assertion is made in the
statement of objections that these constructions have come up later. In such
circumstances, it has to be stated that if only the B.D.A. had complied
with the directions of this Court and passed an order keeping in mind the
parameters prescribed by the Division Bench, petitioner would have got the
benefit of exclusion of his land from acquisition in view of the exclusion of
similarly placed lands abutting the land of petitioner. The omission on the
part of the B.D.A. in not discharging its duties as per directions of the
Division Bench has landed the petitioner into this legal entangle in as much as
he is forced to approach this Court again and again. Indeed, this is the third
time petitioner is before this Court in respect of the very same grievance.”
10.
It can thus be seen that the learned Single Judge came to a specific finding
that the land adjoining the appellant’s land was excluded from the acquisition
and as such, the appellant was also entitled to the benefit of exclusion. It
was also found that there were structures existing on the land prior to the
preliminary notification issued in 2003.
11.
It was sought to be contended before the learned Single Judge by the B.D.A.
that the constructions were carried on by the appellant on the land in question
after the preliminary notification was issued. The learned Single Judge
specifically rejected the said contention. The Court therefore found that the
appellant was entitled to the reliefs claimed. The learned Single Judge also
observed that this was the third round of litigation at the instance of the
appellant and therefore thought it appropriate not to remand back the matter.
However, the learned Single Judge took notice of the fact that out of the land
belonging to the appellant, 15 sites were already allotted to third parties.
The learned Single Judge, therefore, directed that the benefit of the quashing
of acquisition would not be applicable in the case of the 15 sites which were
already allotted to third parties.
12.
Respondent No.1/B.D.A. challenged the same by way of Writ Appeal No. 8 of 2018.
The said Writ Appeal came to be allowed by the impugned order. It is to be
noted that though in paragraph 13, the Division Bench of the High Court found
that from the inspection report dated 20 th September, 2003 in Survey No.64 of
2003 there existed one RCC roof building and four AC sheet rooms, the approximate
age of the building was recent one. It further found that as per the subsequent
inspection report dated 28th March, 2006 conducted pursuant to the order of the
Division Bench of the High Court dated 25 th November 2005, it was noticed that
there were further additional constructions.
13.
The Division Bench found that it appears that the constructions were either
made after the preliminary notification was issued or just before the issuance
of preliminary notification having gotten wind of the possible land acquisition
proceedings.
14.
Insofar as the contention of the appellant herein that the adjoining lands were
already excluded from acquisition, the Division Bench relied on an affidavit
dated 12th September, 2019 sworn by the Special Land Acquisition Officer,
B.D.A. to come to a finding that the land on the western side of the land of
the appellants already stood acquired. It is pertinent to note that
though the said affidavit was filed on 12th September, 2019 the Division
Bench, without giving any opportunity to the appellant herein to respond to the
said affidavit, closed the matter for hearing on the very same day, though the
judgment was subsequently pronounced on 27 th September, 2019.
15.
We find that the approach of the Division Bench in relying on the affidavit of
the authority and closing the matter on the same day, without giving an
opportunity to the appellant herein to meet the averments made in the said
affidavit would be in violation of the principles of natural justice. The
well-reasoned order passed by the learned Single Judge as has been reproduced
by us hereinabove has been reversed by the learned Division Bench based on the
affidavit of the authority without giving an opportunity to the appellant
herein to meet the averments made therein.
16.
We find that on this short ground alone, the appeal deserves to be allowed and,
therefore, is allowed. The impugned judgment and order is quashed and set
aside. The matter is remitted back to the Division Bench of the High Court to
consider it afresh in accordance with law.
17.
Needless to state that if the High Court finds that any further spot inspection
is necessary, it may direct so. The parties are directed to maintain status quo
as on the date of the order of the learned Single Judge of the High Court,
until the decision of the Writ Appeal on remand.
18.
Pending application(s), if any, shall stand disposed of.
------