2025 INSC 138
SUPREME COURT OF INDIA
(HON’BLE ABHAY
S. OKA, J. AND HON’BLE UJJAL BHUYAN, JJ.)
M/S. C & C
CONSTRUCTIONS LTD.
Appellant
VERSUS
IRCON INTERNATIONAL
LTD.
Respondent
Appeal
No. 6657 OF 2023-Decided on 31-01-2025
Arbitration
(A)
Arbitration and Conciliation Act, 1996, Sections 16, 34 and 37 – Arbitration
award – Estoppel -
Appellant acted upon clause 49.5 and sought an extension of time on three
occasions - The claim in the letter dated 25th January, 2017 was made by the
appellant after giving solemn undertaking on 14th January, 2015 not to make any
claim other than escalation in respect of delays in the completion of work -
The claim made was contrary to the undertakings - By the undertakings, the
appellant agreed not to make a claim contrary to what is provided in clause
49.5 – Held that by conduct, the
appellant was estopped from challenging the validity of clause 49.5.
(Para 18)
(B)
Arbitration and Conciliation Act, 1996, Sections 16, 34 and 37 –Arbitration
award – Challenge as to – First
contention raised by the appellant was that all 15 monetary claims could not
have been summarily rejected by the Arbitral Tribunal exercising jurisdiction
under Section 16 of the Arbitration Act, without giving an opportunity to the
appellant to lead evidence and to prove that the claims were not barred by
clause 49.5 - Secondly, the appellant sought to rely upon clause 49.4 - Another
contention raised on behalf of the appellant was that clause 49.5 was waived by
the respondent – Held that as the claims were hit by Clause 49.5 on its plain
reading, there was no question of allowing the appellant to lead evidence -
Clause 49.4 will apply when the delay is not due to the respondent -
Admittedly, in this case, the delay was on the part of the respondent - Hence,
clause 49.5 will apply and not clause 49.4.
(Para 22 and 23)
(C)
Arbitration and Conciliation Act, 1996, Sections 16, 34 and 37 – Indian
Contract Act, 1872, Section 23, 28 - Arbitration award – Challenge as to – New plea - Now, in this appeal, a contention has been
raised that the validity of clause 49.5 ought to have been examined in the
light of Sections 23 and 28 of the Contract Act, but the High Court has not
examined the said issue - Careful perusal of the judgment of the learned Single
Judge shows that the contention that the validity of clause 49.5 ought to be
decided in the light of Sections 23 and 28 of the Contract Act was not raised
before the learned Single Judge in a petition under Section 34 - The said
contention was not raised even before the Division Bench in appeal under
Section 37 - Therefore, it is not open to the appellant to raise the said
contention in this appeal for the first time.
(Para 24)
(D)
Arbitration and Conciliation Act, 1996, Section 37 – Arbitration - New plea at
appellate stage –
Plea of waiver - A contention was raised for the first time in appeal under
Section 37 that clause 49.5 was waived by the respondent - Apart from the fact
that said contention could not have been raised for the first time in appeal
under Section 37 of the Arbitration Act, on the applications made by the
appellant specifically invoking clause 49, the respondent granted an extension
of time on more than one occasion - On this behalf, much capital was sought to
be made about what is stated by the respondent in its letter dated 14th
October, 2013 - By no stretch of imagination, after reading the said letter it
can be inferred that clause 49.5 was waived by the respondent - In fact, the
respondent stated that the claim for financial burden would have to be dealt
with together with the proposal for an extension of time, and the said claim
cannot be processed separately - Thereafter, on two occasions, on specific
requests made by the appellant under clause 49 of the GCC, the extension of time
was granted by the respondent - Except sub-clause 5 of clause 49, there is no
other sub-clause which provides for grant of extension when the delay was
attributable to the respondent - The extensions were granted at the instance of
the appellant by invoking clause 49 - Hence, the argument of waiver of Clause
49.5 by the respondent deserves to be rejected.
(Para
25 and 26)
JUDGMENT
Abhay S. Oka, J.:-
FACTUAL
ASPECTS
1.
This appeal arises out of the impugned judgment and order of the Division Bench
of the High Court of Delhi dated 1st March, 2021, which is passed in an appeal
under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, ‘the
Arbitration Act’).
2.
We refer to a few factual aspects of the case. An agreement dated 28th June,
2012 was entered into between the appellant and the respondent for constructing
five Road Over Bridges (for short, ‘ROBs’)and their approaches at different
locations in the State of Rajasthan. The schedule of completion in respect of
each ROB was different. The locations where ROBs were to be constructed have
been described as LC-200, LC-89, LC-228, LC-233 and LC-108. According to the
appellant's case, the work at the sites was delayed for the reasons
attributable to the respondent. According to the appellant's case, the
respondent withdrew the work relating to the construction of two ROBs (LC-200
and LC-233) from the scope of work and certified the completion of the
remaining work. There is no dispute that we are not concerned with LC-200 and
LC-233 in this appeal. In the case of LC_89 and LC-228, the scheduled
completion date was 15th September, 2013. For LC-108, it was 16th July, 2013.
As per the completion certificate dated 22nd March 2016, the work of LC-89 was
completed on 8th October 2014, and the work of LC-228 was completed on 21st
March 2015. According to the appellant's case, work at LC-108 was completed on
31st March 2017.
3.
On 19th June 2013, the appellant addressed a letter to the respondent's General
Manager stating that the construction delay of ROBs at LC-108 was due to
various hindrances at the site. By the said letter, the appellant requested the
respondent to grant an extension of264 days. The appellant contended that the
delay in construction work has resulted in an additional financial burden on
account of the establishment and overheads, etc., for a longer period than
planned, for which the appellant would be claiming separately. By the reply
dated 14th October 2013, the respondent informed the appellant that the
statement of the appellant that it would be claiming separately for financial
burden was not acceptable. The respondent stated that the claim would have to
be considered along with the prayer for extension. Therefore, the respondent
requested the appellant to submit a detailed claim immediately so that the
prayer for an extension of time could be considered. Separate letters dated
30th August, 2013 were addressed by the appellant to the respondent regarding
LC-89 and LC-228 for grant of extension by 430 and 437 days, respectively. By a
letter dated 29thNovember, 2013, the respondent granted an extension of time as
follows:
|
LC
No. |
Extension
Upto |
Penalty |
|
228
|
20th
March, 2014 |
With
Penalty |
|
89
|
28th
February, 2014 |
With
Penalty |
|
108
|
31st
March, 2014 |
Without
Penalty |
4.
On 28th February, 2014, 09th April, 2014 and 19th April, 2014, the appellant
again applied for a grant extension of time regarding LC Nos. 89, 228 and 108,
respectively. By a letter dated 24th May, 2014, the respondent granted an
extension of time as follows:
|
LC
No. |
Extension
Upto |
Penalty |
|
228
|
31st
January, 2015 |
Without
Penalty |
|
89
|
30th
November, 2014 |
Without
Penalty |
|
108
|
15th
December, 2014 |
Without
Penalty |
5.
By letters dated 03rd September, 2014, the appellant submitted separate claims
concerning the three ROBs for damages on account of the delay on the part of
the respondent. By letters dated 14th October, 2014, the respondent rejected
the claims. The appellant applied for further extension of time by letters
dated 08th January, 2015. In response, the respondent addressed a letter dated
09th January, 2015 by which the appellant was called upon to give undertakings
to the effect that the appellant will not claim anything extra other than
escalation for the work executed. The appellant submitted undertakings on 14th
January, 2015 accordingly.
6.
The appellant invoked the arbitration clause on 25th January 2017. The
appellant filed a statement making a claim for Rs. 44.11 crores under 15
substantive heads besides the claim of interest and costs. The respondent filed
its statement of defence on 25th August,2017.
7.
The respondent filed an application under Section 16(2) of the Arbitration Act.
It was contended in the said application that clause 49.5 of the General
Conditions of Contract (for short, ‘GCC’) disentitles the appellant from
raising any claim for damages or compensation for failure or delay caused by
the respondent in fulfilling its obligations under the contract. The Arbitral
Tribunal passed the order in the respondent’s application under Section 16 of
the Arbitration Act in nature of an award dated 21st December, 2019 by which
all claims were rejected based on clause 49.5 of GCC.
8.
Aggrieved by the impugned award dated 21st December 2019, the appellant
preferred a petition under Section 34 of the Arbitration Act. The learned
Single Judge of the High Court of Delhi dismissed the petition, holding that a
term like clause 49.5 of the GCC would bar the appellant's claim. Moreover, the
appellant had accepted the communication dated 14th October 2014, issued by the
respondent dismissing the claim. It was also held that clause 49.5 was valid
and,after the appellant accepted the same, it could not contend to the
contrary.
9.
Being aggrieved by the judgment of the learned Single Judge, the appellant preferred
an appeal before the Division Bench of the High Court of Delhi by invoking
Section 37 of the Arbitration Act. While dismissing the appeal, the Division
Bench held that the requirement of clause 49.5 was never waived by the
respondent. The Division Bench held that clause 49.5 was a valid clause. After
holding that the powers of the Court while dealing with an appeal under Section
37 of the Arbitration Act are limited by Section 34, the Division Bench
dismissed the appeal.
SUBMISSIONS
10.
The learned counsel appearing for the appellant has made detailed submissions.
His first submission is that the award of the Arbitral Tribunal was contrary to
public policy and suffered from patent illegality. The learned counsel also
pointed out that the main issue was whether a clause prohibiting the payment of
damages, like clause 49.5, could be enforced. He submitted that the Arbitral
Tribunal and the learned Single Judge failed to appreciate the crucial aspects
striking at the root of the award. The learned counsel pointed out various
decisions of the Delhi High Court and this Court. After relying upon several
decisions of this Court, he urged that the parties to the contract cannot
contract against the Indian Contract Act, 1872 (for short, ‘the Contract Act’).
He submitted that the finding recorded by the Arbitral Tribunal that clause
49.5 aims to protect the interests of PSUs and the Government is illegal. He
relied upon the decision of this Court in the case of Pam Developments Pvt.
Ltd. v. State of West Bengal[(2019) 8 SCC
112]. The learned counsel submitted that the additional documents filed by
the appellant ought to be considered. Therefore, the learned counsel appearing
for the appellant submitted that the impugned judgments deserve to be set
aside.
11.
Learned counsel for the respondent submitted that clause 49.5 of GCC read with
clause 12 of the Special Conditions of Contract (for short ‘SCC’) are
limitation of liability clauses. These clauses are not in conflict with either
Section 23 or Section 28 of the Contract Act. He submitted that if clause 49.5
of GCC and clause 12 of SCC are read together, it is apparent that in case of
delay or fault on the part of the employer (respondent), a reasonable extension
of time can be granted and payment of price variation as per the formula agreed
between the parties in the contract itself can be made. Learned counsel
submitted that this Court has consistently upheld the enforceability of
limitation of liability clauses. He relied upon what is held in paragraph 10 of
the decision of this Court in the case of ONGC v. Wig Brothers Builders and
Engineers Private Limited[(2010) 13 SCC
377]. He submitted that the appellant made an irreversible election to
accept the extension of time in terms of the agreed scheme of the contract
between the parties without payment of liquidated damages. Therefore, the
appellant is not entitled to make any additional claim for compensation and/or
damages beyond the stipulations in the contract and contrary to the express
prohibition in clause 49.5 of GCC. He pointed out the letters addressed by the
respondent by which initially liquidated damages/penalty were imposed on the
appellant for the delay. However, on the request made by the appellant, the
respondent granted an extension of time by waiving liquidated damages.
Therefore, the appellant made an irreversible election to accept an extension
of time under clause 49.5 of GCC. He relied upon three letters addressed by the
appellant in which the appellant agreed not to make any claim other than
escalation against the respondent because of the delay on the part of the
respondent for which an extension of time has been sought. He pointed out that
the claim for damages was raised two years after the date of the last
extension. Learned counsel would, thus, submit that the appellant has lost its
right to challenge clause 49.5 and therefore, no interference is called for
with the impugned judgment.
OUR
VIEW
12.
We are concerned with three ROBs bearing numbers LC-89, LC_228 and LC-108.
Clause 49.5 of GCC reads thus:
“49.5 Delays due to
Employer/Engineer In the event of any failure or delay by the Employer/Engineer
in fulfilling his obligations under the contract, then such failure or delay,
shall in no way affect or vitiate the contract or alter the character thereof;
or entitle the Contractor to damages or compensation thereof but in any such
case, the Engineer shall grant such extension or extensions of time to complete
the work, as in his opinion is/are reasonable.”
(emphasis
added)
13.
Initially, by a letter dated 11th February, 2013, the respondent had imposed a
penalty on the appellant for slippage of milestones and non_deployment of
engineers. On 19th June, 2013, a letter was addressed by the appellant to the
respondent in respect of LC-108 seeking an extension of time of 264 days as
there were delays on the part of the respondent. The said letter mentioned that
as the delay resulted in an additional financial burden on the appellant, they
would claim it separately. Similar separate letters in respect of LC-228 and
LC-89 wereaddressed by the appellant on 30th August, 2013. In the said three
letters, the appellant invoked clause 49 of GCC for grant of extension of time.
Sub-clause No.5 of clause 49 is the only sub-clause in clause 49 which provides
for extension of time on account of delay due to the respondent. By a letter
dated 29th November, 2013, the respondent communicated to the appellant the
decision regarding the grant of extension of time regarding LC-228, LC-89 and
LC-108 till 09th April,2014, 28th February, 2014 and 19th April, 2014
respectively. As stated in the letter, in the case of LC-89 and LC-228, the
extension was granted subject to penalty. In the case of LC-89, the appellant
addressed a letter dated 28th February, 2014 to the respondent requesting that
an extension of time be granted till 30th May, 2014, without penalty. Similar
letters were addressed on 9th April, 2014 regarding LC-228 and on 19thApril,
2014 regarding LC-108, wherein a request was made to grant an extension of time
till 31st January, 2015 and 15th December, 2014 respectively, without penalty.
It is pertinent to note that in these letters, the appellant did not state that
it would be making any claim on account of the delay on the part of the
respondent. On 28th February, 2014, 9thApril, 2014 and On 19th April, 2014, by
separate letters, the appellant applied for grant of extension of time for all
three ROBs without penalty.
14.
By letter dated 24th May, 2014, the respondent approved the extension of time
for LC-228, LC-89 and LC-108 up to 31st January, 2015, 30th November, 2014 and
15th December, 2014 respectively. The extension was granted without penalty.
Thus, based on the requestsmade by the appellant, while granting further
extension, the respondent waived the penalty.
15.
Thereafter, on 03rd September, 2014, the appellant addressed three separate
letters to the respondent raising monetary claims on account of the delay on
the part of the respondent. The respondent replied on 14th October, 2014 by
separate letters. The letters are identical. For the sake of convenience, we
are referring to the letter of the respondent in respect of LC-108, which reads
thus:
“The claim of Rs.
65696068/- is not at all admissible and acceptable. The time extension which
has been granted to you without penalty is not at all basis of any claims as
per clause 49 of General Conditions of Contract. As per clause No. 4.1 of
Special Conditions of Contract your claims is not tenable. The same was already
discussed with you earlier and in response to that you had removed your lines
of "It is also to mention here that delay in work is resulting in
additional financial burden on us on account of establishment and over heads
and cost overrun etc., for a lengthier period than planned, for which we will
be claiming separately” from your request letter for extension of time. That
time you were also agreed with it and re submitted your request letter without
such lines.Once again you are requested to complete the work within the
extended period and do not waste your time as well as our time in writing such
type of false claims.”
(emphasis
added)
16.
Thereafter, concerning the three LCs, separate letters were addressed by the
appellant on 8th January, 2015, requesting the respondent to grant further
extension. The respondent sent separate replies to these three letters on 9th
January, 2015. In the said letters, the respondent informed the appellant as
under: “Vide above mentioned letters you have requested for Extension of Time
in respect of ROB in lieu of LC No. 89 (Dadi ka Phatak) up to 30.06.2015. In
this connection you are requested to kindly submit an undertaking that you will
not claim anything extra other than escalation for work executed in the
extended.”
(emphasis added)
17.
Pursuant to the said letters, by three separate letters dated 14thJanuary,
2015, in respect of the said three LCs, the appellant submitted undertakings in
the following terms:
“We, therefore,
undertake that we will not make any claim other than Escalation against the
IRCON because of the delay in completion of which extension of time has been
sought by us.”
(emphasis
added)
18.
After giving the said undertakings, two years thereafter, on 25thJanuary, 2017,
the appellant made claims on account of delay on the part of the respondent,
for which an extension was granted. The appellant invoked the arbitration
clause on the basis of the said claims.19. Considering the conduct of the
appellant, the following conclusions can be drawn:
a) The appellant acted
upon clause 49.5 and sought an extension of time on three occasions;
b) The claim in the
letter dated 25th January, 2017 was made by the appellant after giving solemn
undertaking on 14th January, 2015 not to make any claim other than escalation
in respect of delays in the completion of work. The claim made was contrary to
the undertakings;
c) By the
undertakings, the appellant agreed not to make a claim contrary to what is
provided in clause 49.5; and
d) Therefore, by
conduct, the appellant was estopped from challenging the validity of clause
49.5.
20.
At this stage, we must refer to the decision of the learned Single Judge in the
petition under Section 34 filed by the appellant. The contentions raised by the
appellant have been reproduced by the learned Single Judge of Delhi High Court
in paragraphs 12 and 13 of the Judgment. Paragraphs 12 and 13 read thus:
“12. Mr. Naveen Kumar,
learned counsel for the petitioner has primarily submitted that the Tribunal
has clearly erred in accepting the application of the respondent under Section
16 of the Act of 1996. The Tribunal should have allowed the petitioner to
produce evidence that the delay in discharging the obligations under the
contract was clearly on the respondent and as such, the petitioner was entitled
to the claims, which were in the nature of damages.
13. That apart, he has
drawn my attention to various documents to contend that the respondent had by
its own conduct, not adhered to Clause 49.5 of the GCC. In support of his
submission, he has drawn my attention to page 670 of the documents, wherein the
respondent in its communication to the petitioner has stated for grant of
extension of time, the petitioner's claims for additional financial burden has
to be dealt together. In other words, the respondent has agreed with the claim
of the petitioner for additional financial burden. Mr. Kumar has relied upon
the judgment reported in MANU/SC/1620/2009, Asian Techs Ltd. v. Union of India,
in support of his submission that de-hors a stipulation which bars a claim,
still the Arbitrator can consider the aspect of delay and award the claim, if
justified.”
(emphasis
added)
21.
No other submission made by the appellant has been noted in the judgment. The
learned Single Judge firstly held that on the plain reading of clause 49.5 of
the GCC, the claims made by the appellant before the Arbitrator were barred.
Learned Single Judge held that having accepted the stipulation in clause 49.5,
the appellant could not have contended otherwise.
22.
Now, we turn to the impugned judgment of the Division Bench. The first
contention raised by the appellant was that all 15 monetary claims could not
have been summarily rejected by the Arbitral Tribunal exercising jurisdiction
under Section 16 of the Arbitration Act, without giving an opportunity to the
appellant to lead evidence and to prove that the claims were not barred by
clause 49.5. Secondly, the appellant sought to rely upon clause 49.4. Another
contention raised on behalf of the appellant was that clause 49.5 was waived by
the respondent.
23.
As the claims were hit by Clause 49.5 on its plain reading, there was no
question of allowing the appellant to lead evidence. Clause 49.4 will apply
when the delay is not due to the respondent. Admittedly, in this case, the
delay was on the part of the respondent. Hence, clause 49.5 will apply and not
clause 49.4.
24.
Now, in this appeal, a contention has been raised that the validity of clause
49.5 ought to have been examined in the light of Sections 23 and 28 of the
Contract Act, but the High Court has not examined the said issue. Careful
perusal of the judgment of the learned Single Judge shows that the contention
that the validity of clause 49.5 ought to be decided in the light of Sections
23 and 28 of the Contract Act was not raised before the learned Single Judge in
a petition under Section 34. The said contention was not raised even before the
Division Bench in appeal under Section 37. Therefore, it is not open to the
appellant to raise the said contention in this appeal for the first time.
25.
A contention was raised for the first time in appeal under Section 37 that
clause 49.5 was waived by the respondent. Apart from the fact that said
contention could not have been raised for the first time in appeal under
Section 37 of the Arbitration Act, on the applications made by the appellant
specifically invoking clause 49, the respondent granted an extension of time on
more than one occasion. On this behalf, much capital was sought to be made
about what is stated by the respondent in its letter dated 14th October, 2013.
Though the said contention could not have been raised in an appeal under
Section 37 still, we are examining the same. In the letter dated 14th October,
2013, the respondent stated:
“Vide above mentioned
letter, you have requested for extension of time for a total of 264 days.
However, in, your letter you have mentioned as under:
"it is also
mentioned here that delay in work in resulting in additional financial burden
on us on account of establishment and over heads etc., for a longer period than
planned, for which we will be claiming separately
"For grant of
extension of time, your claim for additional financial burden has to be dealt
together with the proposal of extension of time. Hence, your statement that you
will be claiming separately for additional financial burden is not acceptable.
Hence, you are
requested to submit your detailed claim immediately so that your request for
extension of time can be processed early.”
26.
By no stretch of imagination, after reading the said letter it can be inferred
that clause 49.5 was waived by the respondent. In fact, the respondent stated
that the claim for financial burden would have to be dealt with together with
the proposal for an extension of time, and the said claim cannot be processed
separately. Thereafter, on two occasions, on specific requests made by the
appellant under clause 49 of the GCC, the extension of time was granted by the
respondent. Except sub-clause 5 of clause 49, there is no other sub-clause
which provides for grant of extension when the delay was attributable to the
respondent. The extensions were granted at the instance of the appellant by
invoking clause 49. Hence, the argument of waiver of Clause 49.5 by the respondent
deserves to be rejected. Moreover, detailed claim, as stated in the letter
dated 14th October, 2013 was not submitted by the appellant. Therefore, the
Division Bench rightly found no merit in the said contention.
27.
As far as scope of interference in an appeal under Section 37 of Arbitration
Act is concerned, the law is well settled. In the case of Larsen Air
Conditioning and Refrigeration Company v. Union of India and Ors. [(2023) 15 SCC 472] in paragraph 15,
this court held thus:
“15. The limited and
extremely circumscribed jurisdiction of the court under Section 34 of the Act,
permits the court to interfere with an award, sans the grounds of patent
illegality i.e. that “illegality must go to the root of the matter and cannot
be of a trivial nature”; and that the Tribunal “must decide in accordance with
the terms of the contract, but if an arbitrator construes a term of the
contract in a reasonable manner, it will not mean that the award can be set
aside on this ground” [ref : Associate Builders [Associate Builders v. DDA,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , SCC p. 81, para 42]. The other
ground would be denial of natural justice. In appeal, Section 37 of the Act
grants narrower scope to the appellate court to review the findings in an award,
if it has been upheld, or substantially upheld under Section 34.”
(emphasis
added)
28.
In the case of Konkan Railway Corporation Limited v. Chenab Bridge Project
Undertaking[(2023) 9 SCC 85] in
paragraph 18, this court held thus:
“18. At the outset, we
may state that the jurisdiction of the court under Section 37 of the Act, as
clarified by this Court in MMTC Ltd. v. Vedanta Ltd. [MMTC Ltd. v. Vedanta
Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ) 293] , is akin to the jurisdiction
of the court under Section 34 of the Act. [Id, SCC p. 167, para 14:
“14. As far as
interference with an order made under Section 34, as per Section 37, is
concerned, it cannot be disputed that such interference under Section 37 cannot
travel beyond the restrictions laid down under Section 34. In other words, the
court cannot undertake an independent assessment of the merits of the award,
and must only ascertain that the exercise of power by the court under Section
34 has not exceeded the scope of the provision.”] Scope of interference by a
court in an appeal under Section 37 of the Act, in examining an order, setting
aside or refusing to set aside an award, is restricted and subject to the same
grounds as the challenge under Section 34 of the Act.”
29.
Considering the limited scope of interference, as laid down by this Court, we
find absolutely no merit in the appeal and the same is accordingly dismissed.
------