2025 INSC 113
SUPREME COURT OF INDIA
(HON’BLE ABHAY
S. OKA, J. AND HON’BLE UJJAL BHUYAN, JJ.)
SOM DATT
BUILDERS-NCC-NEC(JV)
Petitioner
VERSUS
NATIONAL HIGHWAYS
AUTH.OF INDIA
Respondent
Civil
Appeal No. 2058 OF 2012-Decided on 27-01-2025
Arbitration
Arbitration and
Conciliation Act, 1996 , Section 34 and 37 – Arbitration award – Challenge
as to –
Application u/s 34 of the Act filed by respondent dismissed by learned Single
Judge – Appeal u/s 37 filed by respondent was allowed by learned Division Bench
of the High Court - In the proceedings under Section 34 of the 1996
Act, learned Single Judge examined Clauses 51 and 52 in detail and thereafter
opined that the decision of the Arbitral Tribunal could not be faulted - Learned
Single Judge agreed with the interpretation given by the South African Court
that automatic increase or decrease in the quantity did not form part of the
variation - Learned Single Judge also reiterated the well- recognised principle
in arbitration that the court exercising jurisdiction under Section
34 of the 1996 Act does not sit as a court of appeal over the decision of
an arbitral tribunal, further reiterating the proposition that a contract has
to be interpreted by the arbitrator who is the chosen judge of the parties - So
long as the view of the arbitrator is a plausible one though it may not be the
only possible view, there should be no interference by the court under Section
34 of the 1996 Act – Held that learned Single Judge had adopted the
correct approach and had rightly declined to interfere with the award of the
Arbitral Tribunal affirming the decision of the DRB – Instead of interpreting
the Clauses 51 and 52 in the contractual
context, Division Bench went into the dictionary meaning of the expression
‘variation’ and opined that variation would mean the difference between what is
provided for or contemplated in relation to the work under the contract and
what is the final effect or outcome - Such variation or outcome may be or may
not be the result of an instruction given by the Engineer - Division Bench,
therefore, held that interpretation of the contractual terms given by the
Arbitral Tribunal and accepted by the learned Single Judge cannot be accepted
as a plausible interpretation – Held that cannot accept such sweeping
conclusions reached by the Division Bench - Interpretation given by the
Division Bench to the plain language of Clauses 51 and 52 is not at all a
plausible one, not to speak of being the only possible interpretation and,
therefore, committed a manifest error in interfering with an arbitral award in
a proceeding under Section 37 of the 1996 Act when the learned Single
Judge did not find any justification at all to interfere with the arbitral
award within the limited scope under Section 34 of the 1996 Act - A
closer look at Clauses 51 and 52 would clearly show that the view taken by
DRB and Arbitral Tribunal, both comprised of technical experts, is the correct
one which was acknowledged by the learned Single Judge - Division Bench of the
High Court was not at all justified in setting aside the arbitral award exercising
extremely limited jurisdiction under Section 37 of the 1996 Act by
merely using expressions like ‘opposed to the public policy of India’, ‘patent
illegality’ and ‘shocking the conscience of the court’ - Judgment and order
passed by the Division Bench of the High Court liable to be set aside and the
arbitral award restored
(Para
24 to 28, 42 and 43)
JUDGMENT
Ujjal Bhuyan, J. :- Heard learned counsel
for the parties.
2.
This civil appeal by special leave is directed against the judgment and order
dated 17.11.2009 passed by the High Court of Delhi at New Delhi (‘High Court’)
in FAO(OS) No. 427 of 2007 [National Highways Authority of India Vs. Som
Datt Builders-NCC- NEC(JV)].
2.1.
By the aforesaid judgment, the High Court allowed the appeal of the
respondent-National Highways Authority of India (‘respondent’ or ‘NHAI’
hereinafter) under Section 37 of the Arbitration and Conciliation Act,
1996 (briefly ‘the 1996 Act’ hereinafter). It may be mentioned that
respondent had challenged, by way of the aforesaid appeal, the judgment and
order of the learned Single Judge in OMP No. 316/2005 dated 29.08.2007 whereby
the learned Single Judge dismissed the application filed by NHAI under Section
34 of the 1996 Act for setting aside the award dated 03.06.2005 passed by
the Arbitral Tribunal.
3.
The matter relates to execution of a contract awarded by NHAI to the appellant
regarding the work of four laning and strengthening of the existing two lane
section between Km. 470.000 and Km. 38.000 on NH-2 (construction package II-B)
near Kanpur in the State of Uttar Pradesh under World Bank Loan Assistance.
4.
At the outset, it would be apposite to advert to the relevant facts.
5.
Following a process of open bid tender, the related contract was allotted by
NHAI to the appellant vide the contract agreement dated 27.03.2002 who
undertook to execute the work at the contract price of Rs. 4,961,183,599.00.
Appellant is a joint venture of Somdatt Builders Pvt. Ltd., Nagarjuna
Construction Company and Navayug Engineering Company Limited having its
principal place of business at East of Kailash, New Delhi.
6.
A joint venture between Consulting Engineering Services (I) Ltd. and BECA
International Consultants Ltd. was appointed by NHAI as the Engineer of the
project in terms of the contract agreement to supervise the construction work.
7.
It was a unit rate contract comprising of a detailed Bill of Quantities (BOQ).
The BOQ contained description of the items of the work to be executed by the
appellant as contractor and the estimated quantity of each item. The rates of
each BOQ item were to be filled in by the contractor (appellant).
8.
The contract agreement provided for a mechanism of dispute resolution at the
first instance through a Dispute Review Board (‘DRB’) prior to the parties
availing of their remedy by way of arbitration. A three-member panel of DRB was
constituted comprising of one member appointed by each of the two parties and
the third member appointed by the aforesaid two members.
9.
While executing the contract, a dispute arose between the parties in respect of
item No. 7.07 of the BOQ which provided for reinforced earth structure
including soil reinforcing geogrid with all fixtures and accessories
complete as per approved design and drawing of specialised firm and matters
connected therewith. The dispute was not really in respect of the nature of the
work to be performed but was the consequence of the geogrid/geotextile material
exceeding the BOQ quantities in the contract. In essence, the dispute relates
to power of the Engineer to revise the rates given in the BOQ in the event of
increase in actual quantities. This was contested by the appellant.
10.
Appellant raised the aforesaid dispute before the DRB contending that the
Engineer/Employer was intending wrongful application of Clause 52.2 of the
Conditions of Particular Application (COPA) for downward revision of rates for
BOQ item No. 7.07 (ii) of geogrid for quantity in excess of BOQ quantity. DRB
heard both the sides and deliberated upon the issue in detail. DRB vide its
decision dated 15.03.2004 recommended that quantities of geogrid required
limited to the facia area provided in the BOQ have to be paid as per the BOQ
rates.
11.
Respondent NHAI was not satisfied with the aforesaid decision of DRB and
invoked the arbitration clause in the contract agreement whereafter the dispute
was referred to arbitration before an Arbitral Tribunal comprising of three
arbitrators: one arbitrator appointed by each of the two parties and the
third arbitrator appointed by the two arbitrators so appointed. It is on record
that each of the arbitrators were technical experts conversant with the nature
of the contract. Arbitral Tribunal, by a majority of 2:1, passed the award
dated 03.06.2005. Arbitral Tribunal held that the quantity of geogrid given at
the tender stage by NHAI was wrong. Therefore, the increase in quantity was a
mere increase to meet the requirement for completion of the RE wall work which
was indicated by the RCC facia quantity at the tender stage. There was no
change in the design but mere increase in the quantity beyond the BOQ quantity
which did not attract Clause 52.2. In this context, Arbitral Tribunal held that
the Engineer does not possess the power to revise the rates for additional
quantity of geogrid required for actual execution of work as per the approved
design. Upholding the recommendations of DRB, Arbitral Tribunal held that
variation in terms of Clause 51.1 was not established and directed NHAI to pay
the appellant for the actual quantity of geogrid required to be executed to
complete the work of RE wall as per the approved design at the BOQ rate.
12.
The aforesaid award dated 03.06.2005 was challenged by the respondent-NHAI
under Section 34 of the 1996 Act which was heard and decided by a
learned Single Judge of the High Court. Learned Single Judge examined the
contours of Clauses 51.1, 51.2, 52.1, 52.2, 52.3 and 55.1 and came to the
definite conclusion that there was no change in the design. The BOQ rate would
apply since the matter was one of mere change in quantity. By the judgment and
order dated 29.08.2007, learned Single Judge of the High Court found no merit
in the application filed by NHAI under Section 34 of the 1996 Act and
dismissed the same.
13.
It was thereafter that NHAI as the appellant preferred the appeal before a
Division Bench of the High Court under Section 37 of the 1996 Act.
The Division Bench examined the primary contention of NHAI that under the contractual
terms, all variations in quantity beyond the tolerance limits set out in the
contract, whether arising as a result of issuance of instructions by the
Engineer or arising even without the issuance of instructions, were open to
renegotiation of the rates by the Engineer. By the judgment and order dated
17.11.2009 (‘impugned judgment’), Division Bench agreed with the
contention of NHAI and set aside the award of the Arbitral Tribunal as
well as the order of the learned Single Judge.
14.
Being aggrieved, the contractor (appellant) preferred the related special leave
petition. On 14.12.2009, this Court had issued notice and passed an interim
order staying encashment of the bank guarantee subject to the appellant
renewing it for a period of one year. Vide order dated 10.02.2012, this Court
granted leave and directed continuance of the interim order. Hence the civil
appeal.
15.
Contention of the appellant is that it is NHAI who had provided the wrong
quantity in respect of item No. 7.07 of the BOQ on the basis of which appellant
had tendered. Upon approval of the design by the Engineer when the increased
quantity became known in April, 2003, the Engineer held that BOQ rate would be
payable for the entire quantity which was not acceptable to NHAI. The increase
in quantity was not as a result of any change in the design or as a result of
any instructions given by the Engineer. The enhancement in the quantity was
necessitated because wrong information was furnished by the respondent at the
stage of tender itself. On dispute being raised, this position was accepted by
the DRB and thereafter by the Arbitral Tribunal. Application filed by the
respondent under Section 34 of the 1996 Act for setting aside of the
arbitral award was rightly rejected by the learned Single Judge of the High
Court. Division Bench of the High Court fell in error and committed a manifest
mistake in overturning the technical findings of the three authorities below
while exercising limited jurisdiction under Section 37 of the 1996 Act.
16.
Counter affidavit has been filed by respondent NHAI. Reliance has been placed
on Clauses 51 and 52 of COPA. Clause 51 of COPA has two parts: 51.1 and 51.2.
Clause 51.1 covers instructed variations which includes any increase or
decrease in the quantity of work. As per Clause 51.2, for increase or decrease
in quantity of any material, instructions of the Engineer are not required. A
combined reading of Clauses 51.1 and 51.2 would indicate that though increase
or decrease in the quantity of any work may be without instructions but it
nonetheless remains a variation. Once it is a variation, Engineer has got the
power to fix a new rate. This power is traceable to Clause 52.1, which does not
make any distinction between instructed variation or uninstructed variation; on
the other hand, it provides that all variations referred to in Clause 51 are to
be valued by the Engineer. In case of instructed variation only, notice is
required to be given in terms of the second proviso to Clause 52.2. If this be
the position, view taken by the Division Bench of the High Court is the correct
one and calls for no interference.
17.
Mr. Arvind Minocha, learned senior counsel for the appellant, at the outset
submits that the core issue involved in this appeal is the justification or
otherwise of the decision of the Division Bench of the High Court upsetting
concurrent findings of three authorities while exercising jurisdiction
under Section 37 of the 1996 Act. He submits that the dispute raised
by the appellant was decided in its favour by the DRB comprising wholly of
technical experts. Arbitral Tribunal again comprising of technical persons
passed the award in favour of the appellant by confirming the decision of the
DRB. When the respondent filed application under Section 34 of the
1996 Act for setting aside of the award, learned Single Judge of the High Court
dismissed the same and affirmed the award passed by the Arbitral Tribunal.
17.1. Learned senior counsel submits that scope of interference by the
appellate court under Section 37 of the 1996 Act is extremely
limited. None of the grounds for invocation of jurisdiction under Section
37 of the 1996 Act were satisfied. Learned Single Judge while
exercising jurisdiction under Section 34 of the 1996 Act had repelled
the challenge of the respondent to the arbitral award. View taken by the
learned Single Judge is a plausible view, if not the only possible view.
Therefore, Division Bench committed a manifest error in setting aside the
arbitral award as well as the order passed by the learned Single Judge
affirming the same.
17.2.
Adverting to the facts of the case, learned senior counsel submits that the
scope of the contract involved construction of 50 Kms. of road, service roads
on both sides, drains, 17 main bridges, 65 culverts and 20 under-passes. The 51
Kms. stretch of road included raised carriageway of about 22 Kms. having
Reinforced Concrete wall (RCC wall) on both sides for 9.5 Kms. and Reinforced
Earth wall (RE wall) for about 12 Kms. with concrete facia panels. After the award
of work, the design of the wall was to be done by the appellant based on the
design criteria given in the contract with the approval of the Engineer
appointed by the respondent. The item RE wall is mentioned at item No. 7.07 in
the BOQ having three sub-items:
(i) RCC facia wall on both sides,
(ii) filter media,
(iii) geogrid.
17.3.
He submits that dispute in the present matter relates to the sub-item geogrid
as the respondent had given a wrong estimate of the quantity in respect of
geogrid while correct quantities were given for the other two sub-items. This
mistake was detected when the design was prepared by the appellant and approved
by the Engineer. When the quantity of material in respect of geogrid increased,
the Engineer decided that the BOQ rate would be applicable for the increased
quantity of geogrid.
17.4.
After the appellant commenced the work, the respondent was making the monthly
payment for the said item as per the BOQ rate. After a new Engineer was
appointed by the respondent, it was decided that the rate for the increased
quantity of geogrid should be renegotiated.
17.5.
Thereafter, the matter was referred by the appellant to the DRB which decided
in favour of the appellant. DRB held that variation in terms of Clause 51.1 was
not established and recommended payment of geogrid at the BOQ rate for the
entire quantity.
17.6.
Respondent did not accept the above recommendations of the DRB and invoked the
arbitration clause in the contract. Arbitral Tribunal, comprised wholly of
technical persons, by a majority of 2:1 held that increase in the quantity of
geogrid for erection of the RE wall as per the approved design could not be
termed as a variation in terms of Clause 51.1. Further holding that the
Engineer did not have the power to revise the rate qua the BOQ rate for the
additional quantity of geogrid required for execution of the work as per the
approved design, Arbitral Tribunal directed payment as per the BOQ rate for the
additional quantity.
17.7.
In the application filed by the respondent under section 34 of the
1996 Act for setting aside of the arbitral award, the challenge centred around
Clauses 51 and 52 only. Learned Single Judge rejected the challenge of the
respondent and upheld the arbitral award. After the award was confirmed by the
learned Single Judge under Section 34 of the 1996 Act, the Division
Bench acting as the appellate court was not at all justified to overturn the
concurrent findings of three adjudicating fora while exercising extremely
limited jurisdiction under Section 37 of the 1996 Act.
17.8.
He further submits that the interpretation given by the Division Bench is not
only contrary to Clause 51.1 and the proviso to Clause 52.2 but renders
those provisions completely otiose. Division Bench misdirected itself by
stretching the meaning of the word variation by referring to dictionary
meanings whereas the said expression has to be understood in the context of the
relevant clauses of the contract. Division Bench failed to appreciate that in
so far automatic increase in the quantity is concerned, the rate which is
payable is the one as agreed in the BOQ. If any other rate is to be fixed, the
same can be considered only in case of instructed variation provided 14 days
prior notice before commencement of the work is given which was admittedly not
done in the present case. In this connection he places reliance on a Delhi High
Court judgment in the case of NHAI vs. M/s ITD Cementation India Limited[(2009) 113 DRJ 176].
17.9.
On the limited scope of interference under Section 37 of the 1996
Act, learned senior counsel for the appellant has placed reliance on the
following decisions:
(i) S.V. Samudram Vs. State of Karnataka [(2024) 3 SCC 623]
,
(ii) M/s. Hindustan
Construction Company Ltd. Vs. M/sNHAI
[(2024) 2 SCC 613]
(iii) Reliance
Infrastructure Ltd. Vs. State of Goa[(2024)
1 SCC 479]
(iv) Konkan Railway Corporation Limited Vs.
Chenab Bridge Project Undertaking[(2023)
9 SCC 85]
(v) M/s Larsen Air Conditioning and Refrigeration
Company Vs Union of India[2023 INSC
708]
(vi) MMTC Ltd. Vs. Vedanta Limited[(2019) 4 SCC 163]
(vii) MP Power
Generation Company Ltd. Vs. Ansaldo Energia SPA[(2018) 16 SCC 661]
18.
Per contra, Mr. Krishnan Venugopal, learned senior counsel appearing for NHAI
submits that Division Bench of the High Court has rightly set aside the
arbitral award finding the same to be perverse.
18.1.
He submits that the core issue involved in the present appeal is whether the
arbitral award dated 03.06.2005 goes contrary to the only interpretation of
Clauses 51 and 52 of the General Conditions of Contract (GCC) read with COPA as
contained in the contract dated 27.03.2002 executed between the parties.
18.2.
Learned senior counsel submits that subject matter of the dispute relates to
BOQ item No. 7.07 (II) i.e. geogrid. Due to change in design of the RE wall,
quantity of geogrid increased almost by 300 percent during execution. Since the
twin conditions contemplated under Clause 52.2 were being fulfilled i.e.
overall quantity of geogrid executed by more than 25 percent from the estimated
quantity and the cost of geogrid being more than 2 percent of the contract
value, the rate for the additional quantity of geogrid was required to be
reworked. Therefore, the present case is that of instructed variation under
Clause 51.1(a) for which the appellant was also notified on 28.10.2003
fulfilling the requirement of 14 days’ notice contained in Clause 52.2. 18.3.
Referring to the arbitral award, Mr. Venugopal submits that contrary to the
evidence on record and contrary to the relevant clauses of the contract,
Arbitral Tribunal held that it was not a case of instructions issued by the
Engineer but a case of automatic increase of quantity. Referring to Clause
51.1(a), he submits that increase or decrease in quantity is also a variation
and as per Clause 51.2, no instructions are required for such increase or
decrease of quantity though the same continues to be a variation.
18.4.
Even assuming but not admitting that the Engineer did not issue any notice to
the appellant then also, according to Mr. Venugopal, a bare reading of Clause
52.2 would make it apparent that for a non-instructed variation, the condition
of giving 14 days’ notice would not apply.
18.5.
Learned senior counsel also submits that the contention of the appellant that
the quantity of geogrid had increased due to negligence and wrong mentioning of
figures by the respondent is totally fallacious in as much as Clause 55.1 of
the contract clarifies that the quantity set out in the contract are the
estimated quantities only.
18.6.
He would therefore contend that this is not a case of plausible interpretation
but a case of adopting an interpretation which is contrary to the only possible
interpretation of the contractual clauses. Arbitral Tribunal has rewritten the
contract by ignoring the plain and simple language of the relevant clauses and
the parties’ intentions besides overlooking the evidence on record which is
legally impermissible. All these aspects were raised by the respondent in its
application under Section 34 of the 1996 Act but the learned Single
Judge failed to consider the same by placing reliance on a South African
judgment which is clearly distinguishable in the facts of the present
case. Therefore, Division Bench of the High Court acting as the appellate court
under Section 37 of the 1996 Act rightly interfered in the matter by
setting aside the arbitral award.
18.7.
Learned senior counsel has placed reliance on the following decisions to
buttress his submissions:
(i) Associate Builders Vs. DDA[(2015) 3 SCC 49]
(ii) Ssangyong Engineer and Construction
Company Ltd. Vs. NHAI[(2019) 15 SCC
131]
(iii) PSA Sical Terminals Private Ltd. Vs.
Board of Trusteesof V.O. Chidambranar Port Trust Tuticorin[(2023) 15 SCC 781]
18.8.
Learned senior counsel further submits that the judgment in the case of NHAI
Vs. M/s ITD Cementation India Limited, cited and relied upon by the appellant,
is not applicable to the facts of the present case. Firstly, the judgment is by
a Single Bench whereas the impugned order has been passed by a Division Bench
which is also later in point of time. Secondly, the said
judgment does not deal with the power of the Engineer to fix a new rate in
terms of Clause 52.
18.9.
He finally submits that the present appeal is devoid of any merit and the same
is therefore liable to be dismissed by this Court.
19.
Submissions made by learned counsel for the parties have received the due
consideration of the court.
20.
At the outset, it would be relevant to advert to Clauses 51 and 52 of the GCC
read with COPA. Clauses 51 and 52 are as under:
Alteration, Additions
and Omissions 51.1 Variations (GCC) The Engineer shall make any variation of
the form, quality or quantity of works or any part thereof that may, in his
opinion, be necessary and for the purpose, or if for any other reason it shall,
in his opinion, be appropriate, he shall have the authority to instruct the
Contractor to do and the Contractor shall do any of the following:-
(a) increase or
decrease the quantity of any work included in the Contract.
(b) omit any such work
(but not if the omitted work is to be carried out by the Employer or by another
contractor),
(c) change the
character or quality or kind of any such work,
(d) change the levels,
lines, position and dimensions of any part of the works,
(e) execute additional
work of any kind necessary for the completion of the works, or
(f) change any
specified sequence or timing of construction of any part of the works.
No such variation
shall in any way vitiate or invalidate the Contract, but the effect, if any, of
all such variations shall be valued in accordance with Clause 52.
Provided that where
the issue of an instruction to vary the works is necessitated by some default
of or breach of contract by the Contractor or for which he is responsible, any
additional cost attributable to such default shall be borne by the Contractor.
51.2 Instructions for
Variations (GCC) The Contractor shall not make any such variation without an
instruction of the Engineer.
Provided that no
instruction shall be required for increase or decrease in the quantity of any
work where such increase or decrease is not the result of an instruction given
under this Clause, but is the result of the quantities exceeding or being less
than those stated in the Bill of Quantities.
52.1 Valuation of
Variations (GCC) All variations referred to in Clause 51 and any additions to
be Contract Price which are required to be determined in accordance with Clause
52 (for the purposes of this Clause referred to as “varied work”), shall be
valued at the rates and prices set out in the Contract if, in the opinion of
the Engineer, the same shall be applicable. If the contract does not contain
any rates or prices applicable to the varied work, the rates and prices in the
Contract shall be used as the basis for valuation so far as may be reasonable,
failing which, after due consultation by the Engineer with the Employer and the
Contractor, suitable rates or prices shall be agreed upon between the Engineer
and the Contractor. In the event of disagreement, the Engineer shall fix such
rates or prices as are, in his opinion, appropriate and shall notify the
Contractor accordingly, with a copy to the Employer. Until such time as rates
or prices are agreed or fixed, the Engineer shall determine provisional rates
or prices to enable on- account payments to be included in certificates
issued in accordance with Clause 60.
(COPA)
Where the Contract
provides for the payment of the Contract Price in more than one currency, and
varied work is valued at, or on the basis of, the rates and prices set out in
the Contract, payment for such varied work shall be made in the proportions of
various currencies specified in the Appendix to Bid for payment of the Contract
Price. Where the Contract provides for payment of the Contract Price in more
than one currency, and new rates or prices are agreed, fixed, or determined as
stated above, the amount or proportion payable in each of the applicable
currencies shall be specified when the rates or prices are agreed, fixed, or
determined, it being understood that in specifying these amounts or proportions
the Contractor and the Engineer (or, failing agreement, the Engineer) shall
take into account the actual or expected currencies of cost (and the
proportions thereof) of the inputs of the varied work without regard to the
proportions of various currencies specified in the Appendix to Bid for payment
of the Contract Price.
52.2 Power of Engineer
to fix Rates (GCC) Provided that if the nature or amount of any varied work
relative to the nature or amount of the whole of the works or to any part
thereof, is such that, in the opinion of the Engineer, the rate or price
contained in the Contract for any item of the works is, by reason of such
varied work, rendered inappropriate or inapplicable, then, after due
consultation by the Engineer with the Employer and the Contractor, a suitable
rate or price shall be agreed upon between the Engineer and the Contractor. In
the event of disagreement the Engineer shall fix such other rate or price as
is, in his opinion, appropriate and shall notify the Contractor accordingly,
with a copy to the Employer. Until such time as rates or prices are agreed or
fixed, the Engineer shall determine provisional rates or prices to enable
on-account payments to be included in certificates issued in accordance with
Clause 60.
(COPA)
Where the Contract
provides for the payment of the Contract Price in more than one currency, the
amount or proportion payable in each of the applicable currencies shall be
specified when the rates or prices are agreed, fixed or determined as stated
above, it being understood that in specifying these amounts or proportions the
Contractor and the Engineer (or, failing agreement, the Engineer) shall take
into account the actual or expected currencies of cost (and the proportions
thereof) of the inputs of the varied work without regard to the proportions of
various currencies specified in the Appendix to Bid for payment of the Contract
Price. (GCC) Provided also that no varied work instructed to be done by the
Engineer pursuant to Clause 51 shall be valued under Sub-Clause 52.1 or under
this Sub-Clause unless, within 14 days of the date of such instruction and, other
than in the case of omitted work, before the commencement of the varied work,
notice shall have been given either:
(a) by the Contractor
to the Engineer of his intention to claim extra payment or a varied rate or
price, or
(b) by the Engineer to
the Contractor of his intention to vary a rate or price. (GCC) (COPA) Provided
further that no change in the rate or price for any item contained in the
Contract shall be considered unless such item accounts for an amount more than
2 percent of the Contract Price, and the actual quantity of work executed under
the item exceeds or falls short of the quantity set out in the Bill of
Quantities by more than 25 percent.
52.3 Variations
Exceeding 15 per cent (GCC) If, on the issue of the Taking-Over
Certificate for the whole of the works, it is found that as result of :
(a) all varied work
valued under Sub-Clauses 52.1 and 52.2 and
(b) all adjustments
upon measurement of the estimated quantities set out in Bill of Quantities,
excluding provisional sums, dayworks and adjustments of price made under Clause
70.
But not from any other
cause, there have been additions to or deductions from Contract Price which
taken together are in excess of 15 per cent of the “Effective Contract Price”
(which for the purposes of this Sub- Clause shall mean Contract Price,
excluding provisional sums and allowance for dayworks, if any) then and in such
event (subject to any action already taken under any of Sub-Clauses of this
Clause), after due consultation by the Engineer with the Employer and the
Contractor, there shall be added to or deducted from Contract Price, such
further sum as may be agreed between the Contractor and Engineer or, failing
agreement, determined by the Engineer having regard to the Contractor’s site
and general overhead costs of the Contract. The Engineer shall notify the
Contractor of any determination made under this Sub-Clause, with copy to the
Employer. Such sum shall be based only on the amount by which such additions or
deductions shall be in excess of 15 per cent of the Effective Contract Price.
(COPA)
Where the Contract
provides for the payment of the Contract Price in more than one currency, the
amount or proportion payable in each of the applicable currencies shall be
specified when such further sum is agreed or determined, it being understood
that in specifying these amounts or proportions the Contractor and the Engineer
(or, failing agreement, the Engineer) shall take into account the currencies
(and the proportions thereof) in which the Contractor’s site and general
overhead cost of the Contract were incurred without being bound by the
proportions of various currencies specified in the Appendix to Bid payment of
the Contract Price.
21.
DRB while rejecting the contention of NHAI was of the view that the design of
geogrid is contingent to the height and area of facia panel within the
prescribed length mentioned in the BOQ and based on the
parameters/specifications as prescribed in the agreement, there was no change
in the concept or design. Basically, the design submitted by the appellant was
approved and accepted by the Engineer. Since the work was done as per the valid
approved design, plea taken by NHAI that there was a change of form in terms of
the wall heights and length of RE wall could not be evidenced by NHAI. After an
in-depth analysis, DRB concluded that there was no change of form but only a
working arrangement. The design having been approved after the full knowledge
of the Engineer that enhancement in quantity to a large extent was involved and
accordingly, the matter was referred by the Engineer for allocation of funds.
Therefore, there was no variation as per Clause 51.1 or Clause 51.2 and hence
payment as per the BOQ rate should be made for the entire quantity. Though NHAI
had contended that appellant had changed the form and varied the design, this
could not be proved in any way. Therefore, DRB held that variation in
terms of Clause 51.1 could not be established. As such, DRB recommended that
quantities of geogrid required, limited to the facia area, should be paid as
per the BOQ rates.
22.
As already noticed, the DRB recommendations were not acceptable to NHAI which
thereafter invoked the arbitration clause. Arbitral Tribunal comprised of three
arbitrators; one each appointed by the two parties who thereafter appointed the
third arbitrator. All the three arbitrators were technical experts. Arbitral
Tribunal referred to Clause 67.1 of the GCC which says that recommendations of
the DRB shall be binding on both parties giving prompt effect to it until and
unless the same is revised by the Arbitral Tribunal. Arbitral Tribunal,
therefore, was of the view that NHAI should have complied with the DRB
recommendations which was subject to outcome of the arbitral award. However,
NHAI failed to do so. Thereafter, Arbitral Tribunal framed the core issue to be
considered viz. whether as per the contract, Engineer has the right to revise
the rate for additional quantities of geogrid in excess of the BOQ quantities
which are required for actual execution of the RE wall as per approved design.
After thorough examination of the rival claims, Arbitral Tribunal recorded
the finding that the quantity of geogrid given at the tender stage which was
part of the responsibility of NHAI was found to be erroneous. Therefore, the
increase in quantity was merely to meet the requirement for completion of the
RE wall which was indicated by the RCC facia quantity at the tender stage. NHAI
had admitted the fact that the design evolved by the appellant’s consultant met
the specified criteria. In other words, there was no change in the design and
NHAI could not establish the same before the Arbitral Tribunal which held as
follows:
8.3 In a contract of
the type in question which is an item rate contract based on the price schedule
of provisional quantities the ultimate contract amount can be ascertained when
all the work done in terms of the contract is finally measured and the contract
amount computation done on the. basis of the prices and rates set out in the
Bill of Quantities. The contract between the parties, therefore, is a frame
work which determines the parties rights and obligations. The scope of work in
this case was indicated by RCC facia quantity as mentioned hereinbefore which
determines the length of the RE Wall to be constructed for raised carriage way
and the quantity of other sub-item i.e. the geogrid quantity to be used is
contingent to the facia quantity. Both the parties knew about the scope of work
of RE Wall in this manner and both knew that it was impossible to
determine the ultimate contract amount before the completion of RE Wall work
and if ultimate quantity exceeds the BOQ quantity, it will be an automatic
change and shall be paid at BOQ rate in such type of measurement contracts
where the quantities are provisional and ultimate quantities required for
completion of the work are to be executed and paid as per the quoted rate.
8.4 The fact that
ultimate measured amount of work performed is different from estimated quantity
is irrelevant because both the parties contracted on the basis that the
ultimate quantity may increase or decrease.
22.1.
On the above basis, Arbitral Tribunal concluded that the change in quantity did
not constitute a variation so as to attract the provisions of Clause 52.2,
further noting that this clause clearly provides that it would be applicable
only in respect of varied work instructed to be done by the Engineer as per
Clause 51 and that the present was not a case where such instructions were
required. While upholding the interpretation of the appellant of Clauses 51 and
52, Arbitral Tribunal held that the Engineer does not possess the power to
revise the rates for additional quantity of geogrid required for actual execution
of the work as per the approved design. Arbitral Tribunal upheld the
recommendations of DRB and passed the following award:
(i) The variation in
terms of Clause 51.1 is not established.
(ii) Claimant (NHAI)
was directed to pay the Respondent (Som Datt Builders - NCC-NEC- JV) the actual
quantity of geogrid required to be executed to complete the work of RE wall as
per the approved design at the BOQ rate.
23.
DRB had recorded a finding of fact that there was no change in the concept or
design. As a matter of fact, the design prepared and submitted by the appellant
was approved by the Engineer whereafter the related work was executed as per
the approved design. On the basis of such finding of fact, DRB interpreted
Clauses 51 and 52 to hold that there was no instructed variation and,
therefore, the excess quantity of geogrid required while executing the work,
limited to the facia area, should be paid as per the BOQ rates. Arbitral
Tribunal reiterated the aforesaid finding of fact and affirmed the interpretation
given by the DRB. On that basis, Arbitral Tribunal concluded that the change in
quantity did not constitute a variation so as to attract the provisions of
Clause 52.2. Arbitral Tribunal concurred with the DRB that the Engineer did not
have the competence to revise the rates for the additional quantity of geogrid
required for execution of the work as per the approved design.
24.
In the proceedings under Section 34 of the 1996 Act, learned Single
Judge examined Clauses 51 and 52 in detail and thereafter opined that the
decision of the Arbitral Tribunal could not be faulted. Analysis of Clause 51.1
read with the other clauses would indicate that the variations referred therein
are instructed variations. In the present case, Clause 52 would not come into
play since the same arises only in the case of instructed variations. Learned
Single Judge noted with approval the finding of the Arbitral Tribunal that the
ultimate measured work performed was different from the estimated quantity but
the parties had contracted on the basis that such quantity may increase or
decrease. There was no change in the design in view of the clear admission of
NHAI before the DRB that the design was reviewed and found according to the
specified criteria and that NHAI was unable to establish any change in the
design. Learned Single Judge while exercising jurisdiction under Section
34 of the 1996 Act after analysing Clauses 51 and 52 held that the
Arbitral Tribunal had reached the conclusion that the second para of Clause
52.2, which mandates that the said provision would be applicable only for
varied work instructed to be done by the Engineer as per Clause 51, was not
attracted to the facts of the present case, and therefore, the Engineer
did not give any notice of 14 days of his intention to vary the rate. Since the
matter fell within the domain of uninstructed variations, there was no need to
give 14 days’ notice which is the requirement in the case of instructed
variation.
24.1.
Learned Single Judge also referred to a decision of the Appellate Division of
the South African Court in Grinaker Construction (TVL) Ltd Vs. Transvaal
Provincial Administration[1982 (1) AD
78] , where similar contractual clauses came up for interpretation.
Learned Single Judge agreed with the interpretation given by the South African
Court that automatic increase or decrease in the quantity did not form part of
the variation.
24.2.
Learned Single Judge highlighted the aspect that the interpretation given to
the aforesaid clauses was also the interpretation arrived at by the DRB as also
by the Arbitral Tribunal. The contractual clauses have been interpreted by
technical people who were well conversant with the nature of the dispute and
for this reason also greater weight has to be given to such a view. Learned
Single Judge held that once a contracted price is provided and the quantities
are held to be tentative, any increase or decrease in quantity must be
governed by the same price. It is only in respect of any instructed variation
arising from the instruction of the Engineer on account of any additional work
or less work that there can be some element of renegotiation and determination
in terms of Clauses 51 and 52 of the GCC. Therefore, learned Single Judge
concurred with the view taken by the Arbitral Tribunal which had affirmed the
view of the DRB.
25.
Learned Single Judge also reiterated the well- recognised principle in
arbitration that the court exercising jurisdiction under Section
34 of the 1996 Act does not sit as a court of appeal over the decision of
an arbitral tribunal, further reiterating the proposition that a contract has
to be interpreted by the arbitrator who is the chosen judge of the parties. So
long as the view of the arbitrator is a plausible one though it may not be the
only possible view, there should be no interference by the court
under Section 34 of the 1996 Act.
26.
According to us, learned Single Judge had adopted the correct approach and had
rightly declined to interfere with the award of the Arbitral Tribunal affirming
the decision of the DRB.
27.
Let us now deal with the impugned order. Division Bench of the High Court
exercising jurisdiction under Section 37 of the 1996 Act acknowledged
that primarily it was for the Arbitral Tribunal to interpret the contractual
terms and if the interpretation given by the Arbitral Tribunal is a plausible
one, then the court would not interfere with the award merely because according
to the court, another interpretation is preferable. Having said that, Division
Bench examined Clauses 51 and 52 of the contract. Instead of interpreting the
aforesaid clauses in the contractual context, Division Bench went into the
dictionary meaning of the expression ‘variation’ and opined that variation
would mean the difference between what is provided for or contemplated in
relation to the work under the contract and what is the final effect or
outcome. Such variation or outcome may be or may not be the result of an
instruction given by the Engineer. It has further been observed that the
instruction issued by the Engineer to the contractor does not necessarily mean
that the contractor should carry out a ‘variation’. It may relate to
performance of one or more of the specific acts enumerated in Clause 51.1.
According to the Division Bench, variation in quantity, even when it is not a
result of an instruction given under Clause 51.1 by the Engineer to the
contractor does not cease to be a variation within the meaning of that
expression used in Clause 51.1. Division Bench, therefore, opined that
there is no basis or underlying principle stated either by the Arbitral
Tribunal or by the learned Single Judge that only if the variation is the
result of instruction given by the Engineer under Clause 51.1, rates and prices
of the BOQ items in question would be open to renegotiation and not otherwise;
variation in quantity, even when it is not a result of an instruction given by
the Engineer to the contractor under Clause 51.1, does not cease to be a
‘variation’ within the meaning of the expression used in Clause 51.1.
27.1.
Division Bench disagreed with the observations of the Arbitral Tribunal as
upheld by the learned Single Judge that even if there was error in estimating
the quantity of geogrid while preparing the BOQ, that by itself would not lead
to the conclusion that NHAI cannot seek renegotiation of the rates even if the
actual quantity exceeds by over 300 percent. The contract does not provide that
NHAI should suffer on account of the estimated quantities mentioned in the BOQ
turning out to be way off the mark when the contract is executed.
27.2.
It was on the above basis, Division Bench held that there is no reason as to
why variation in quantity beyond the limits set out in the contract, whether
instructed or not instructed, should not lead to renegotiation of the
rates at the instance of either party. That would be the only fair, reasonable
and equitable way to work the contract.
27.3.
Division Bench, therefore, held that interpretation of the contractual terms
given by the Arbitral Tribunal and accepted by the learned Single Judge cannot
be accepted as a plausible interpretation. Division Bench observed that such
interpretation is unreasonable and wholly implausible and that the arbitral
award is opposed to the public policy of India, shocking the conscience of the
court. Therefore, the order of the learned Single Judge as well as the arbitral
award were set aside.
28.
We are afraid we cannot accept such sweeping conclusions reached by the
Division Bench. Interpretation given by the Division Bench to the plain
language of Clauses 51 and 52 is not at all a plausible one, not to speak of
being the only possible interpretation and, therefore, committed a manifest
error in interfering with an arbitral award in a proceeding under Section
37 of the 1996 Act when the learned Single Judge did not find any
justification at all to interfere with the arbitral award within the limited
scope under Section 34 of the 1996 Act. A closer look at Clauses 51
and 52 would clearly show that the view taken by DRB and Arbitral Tribunal,
both comprised of technical experts, is the correct one which was acknowledged
by the learned Single Judge.
29.
As per Clause 51.1, Engineer has the competence to make any variation of the
form, quality or quantity of works, either wholly or any part thereof, if in
his opinion, it is necessary to do so. In that event, Engineer has the
authority to instruct the contractor to carry out the same and the contractor
shall in such event would be under an obligation to do what is contemplated in
sub-clauses (a) to (f) thereunder, such as, increase or decrease in the
quantity of any work included in the contract, etc.. Clause 51.1 clarifies that
such instructed variation shall not vitiate or invalidate the contract, but
such variation shall be valued in accordance with Clause 52. What Clause 51.2
indicates is that it is not open to the contractor to make such variation
without any instruction from the Engineer. Proviso to Clause 51.2 is relevant.
It says that no instruction from the Engineer would be required for the
increase or decrease in the quantity of any work where such increase or
decrease is not the result of any instruction given under Clause 51.1 but is
the result of the quantities exceeding or being less than those stated in the
BOQ.
30.
Clause 52.2, on the other hand, mentions that all variations referred to in
Clause 51 (which means instructed variations) shall be valued at the rates and
prices in the contract, if in the opinion of the Engineer, the same is
applicable. If the contract does not contain any rates or prices applicable to
the varied works, the rates and prices in the contract shall be used as the
basis for valuation so far it may be reasonable. If this is not possible, then
the Engineer shall carry out the valuation after due consultation with the
Employer and the contractor. The GCC proviso to Clause 52.2 says that no varied
work instructed to be done by the Engineer shall be valued under Clause 52.1 or
under Clause 52.2 unless 14 days’ notice is given by either of the parties.
31.
The further proviso under COPA to Clause 52.2 says that no change in the rate
or price for any item contained in the contract shall be considered unless such
item accounts for more than 2 percent of the contract price and the actual
quantity of the work executed under the item exceeds or falls short of the
quantity set out in the BOQ by more than 25 percent.
32.
The aforesaid provision is not a mandate for change in the rate or price for
any item contained in the contract, if such item accounts for an amount which
is more than 2 percent of the contract price and the actual quantity of
work executed under the item exceeds or falls short of the quantity set out in
the BOQ by more than 25 percent. Rather, it is an enabling provision which
enables either of the parties to consider change in the rate or price of any
item mentioned in the contract, in the event, the above two conditions are
fulfilled.
33.
In so far Clause 51.1 is concerned, the variation contemplated thereunder
relates to the form, quality or quantity of the works which in the opinion of
the Engineer is necessary. In the present case, there is a clear finding of
fact by two authorities i.e. DRB and the Arbitral Tribunal, both comprised of
technical experts, that there is no variation either in the form or quality or
quantity of the works. What actually happened is that at the time of execution
of the contract pertaining to the RE wall, the geogrid required turned out to
be much more than the estimated figure given in item No. 7.7 of the contract.
It is in this backdrop that both the fact finding authorities held that there
was no variation in terms of Clause 51.1 and that the Engineer did not have the
competence to renegotiate the price or rate of the geogrid for the excess
quantity of geogrid required.
34.
As already discussed above, this is clearly a plausible view. In fact,
according to us, it is the correct interpretation of Clause 51 made by the DRB
and the Arbitral Tribunal. As such, learned Single Judge rightly declined to
interfere with the award under Section 34 of the 1996 Act. If that be
the position, there was no justification at all for the Division Bench of the
High Court to set aside the award under Section 37 of the 1996 Act.
35.
Though learned counsel for the parties had cited a number of decisions at the
time of hearing, it is not necessary to refer to and discuss each one of them.
However, reference to a few of the judgments would suffice.
36. In MMTC
Ltd. Vs. Vedanta Ltd. [(2019) 4 SCC
163] , this Court held that as far as Section 34 is
concerned, the position is well settled that the court does not sit in appeal
over an arbitral award and may interfere on merits only on the limited ground
provided under Section 34(2)(b)(ii) i.e. if the award is against the
public policy of India. Even then, the interference would not entail a review
on the merits of the dispute but would be limited to situations where the
findings of the arbitrator are arbitrary, capricious or perverse or when the
conscience of the court is shocked or when the illegality is not trivial
but goes to the root of the matter. An arbitral award may not be interfered
with if the view taken by the arbitrator is a possible view based on facts. As
far as interference with an order made under Section 34 by the court
under Section 37 is concerned, it has been held that such
interference under Section 37 cannot travel beyond the restrictions
laid down under Section 34. In other words, the court cannot undertake an
independent assessment of the merits of the award and must only ascertain that
the exercise of power by the court under Section 34 has not exceeded
the scope of the provision.
37.
What is public policy of India has been explained in Ssangyong Engineer
and Construction Company Ltd. (supra). It means the fundamental policy of
Indian law. Violation of Indian statutes linked to public policy or public
interest and disregarding orders of superior courts in India would be regarded
as being contrary to the fundamental policy of Indian law. It would also mean
that the arbitral award is against basic notions of justice or morality. An
arbitral award can be set aside on the ground of patent illegality i.e. where
the illegality goes to the root of the matter but re-appreciation of evidence
cannot be permitted under the ground of patent illegality.
38. In PSA
Sical Terminals Private Ltd. (supra), this Court reiterating the well
settled principles held as under:
40. It will thus
appear to be a more than settled legal position, that in an application
under Section 34, the court is not expected to act as an appellate court
and reappreciate the evidence. The scope of interference would be limited to
grounds provided under Section 34 of the Arbitration Act. The
interference would be so warranted when the award is in violation of “public
policy of India”, which has been held to mean “the fundamental policy of Indian
law”. A judicial intervention on account of interfering on the merits of the
award would not be permissible. However, the principles of natural justice as
contained in Sections 18 and 34(2)(a)(iii) of the
Arbitration Act would continue to be the grounds of challenge of an award. The
ground for interference on the basis that the award is in conflict with justice
or morality is now to be understood as a conflict with the “most basic notions
of morality or justice”. It is only such arbitral awards that shock the
conscience of the court, that can be set aside on the said ground. An award
would be set aside on the ground of patent illegality appearing on the face of
the award and as such, which goes to the roots of the matter. However, an
illegality with regard to a mere erroneous application of law would not be a
ground for interference. Equally, reappreciation of evidence would not be
permissible on the ground of patent illegality appearing on the face of the
award.
41. A decision which
is perverse, though would not be a ground for challenge under “public policy of
India”, would certainly amount to a patent illegality appearing on the face of
the award. However, a finding based on no evidence at all or an award which
ignores vital evidence in arriving at its decision would be perverse and liable
to be set aside on the ground of patent illegality.
39. In
Reliance Infrastructure Ltd. (supra), this Court referring to one of its
earlier decisions in UHL Power Company Ltd. Vs. State of Himachal Pradesh[(2022) 4 SCC 116] , held that
scope of interference under Section 37 is all the more circumscribed
keeping in view the limited scope of interference with an arbitral award
under Section 34 of the 1996 Act. As it is, the jurisdiction
conferred on courts under Section 34 of the 1996 Act is fairly
narrow. Therefore, when it comes to scope of an appeal under Section
37 of the 1996 Act, jurisdiction of the appellate court in examining an
order passed under Section 34, either setting aside or refusing to set
aside an arbitral award, is all the more circumscribed.
40.
Again in M/s Larsen Air Conditioning and Refrigeration
Company (supra), this Court reiterated the position that Section
37 of the 1996 Act grants narrower scope to the appellate court to
review the findings in an arbitral award if it has been upheld or substantially
upheld under Section 34.
41.
This Court in M/s. Hindustan Construction Company Ltd. (supra) declared
that it is the settled jurisprudence of the courts in the country that arbitral
awards which contain reasons especially when they interpret contractual terms
ought not to be interfered with lightly. An error in the interpretation of
contractual terms by an arbitrator is an error within his jurisdiction and
would, therefore, not be a ground to interfere with an arbitral award.
42.
As already discussed above, the Arbitral Tribunal had interpreted Clause 51 in
a reasonable manner based on the evidence on record. This interpretation was
affirmed by the learned Single Judge exercising jurisdiction under Section
34 of the 1996 Act. Therefore, Division Bench of the High Court was not at
all justified in setting aside the arbitral award exercising extremely limited
jurisdiction under Section 37 of the 1996 Act by merely using
expressions like ‘opposed to the public policy of India’, ‘patent illegality’
and ‘shocking the conscience of the court’. As reiterated by this Court in
Reliance Infrastructure Ltd. (supra), it is necessary to remind the courts that
a great deal of restraint is required to be shown while examining the
validity of an arbitral award when such an award has been upheld, wholly or
substantially, under Section 34 of the 1996 Act. Frequent interference
with arbitral awards would defeat the very purpose of the 1996 Act.
43.
For all the aforesaid reasons, we are of the unhesitant view that the impugned
order cannot be sustained. Accordingly, judgment and order dated 17.11.2009
passed by the Division Bench of the High Court is hereby set aside and the
arbitral award dated 03.06.2005 is restored. Consequently the appeal is
allowed. However, there shall be no order as to cost.
------