2025 INSC 3
SUPREME COURT OF INDIA
(HON’BLE B.R. GAVAI, J. AND
HON’BLE K. V. VISWANATHAN, JJ.)
BERNARD FRANCIS JOSEPH VAZ
Petitioner
VERSUS
GOVERNMENT OF KARNATAKA
Respondent
Civil
Appeal No. OF 2025 (Arising out of SLP (C) No. 10338 of 2023)-Decided on
02-01-2025
Land Acquisition
Land Acquisition;
Delay in award: Award to be on market value of year 2019 instead of 2003
Karnataka Industrial Areas
Development Act, 1966 - Section 28(1)
- Land Acquisition -Delay in
Compensation - Shifting of Notification Date - Judicial Review; Timeliness
in Award Process - The Supreme Court scrutinized the authority of the Special
Land Acquisition Officer (SLAO) to shift the date for determining market value
from the date of the preliminary notification to a later date. It reaffirmed
that such adjustments are permissible only under exceptional circumstances by
higher courts and not by SLAOs. The judgment identified systemic delays in
compensation payment as violating constitutional rights under Article 300-A,
emphasizing the State's duty to expedite the compensation process and resolve
landowners' grievances promptly. The Court directed the SLAO to reassess
compensation based on the market value as of April 22, 2019, thereby ensuring
fair remuneration for the affected landowners.
(Para
59)
Constitution of India, Article 142,
300-A - Right to Property - Delay in Land acquisition award processing Value on
Date of Award - The
Supreme Court highlighted the constitutional right to property under Article
300-A, asserting that landowners’ rights must be protected through timely
payment of compensation following land acquisition. The Court noted that
extensive delays in processing and awarding compensation adversely impact
landowners, necessitating prompt action by the State. It stressed that
compensation should be determined based on current market conditions, and found
justification for shifting the assessment date to ensure equitable treatment of
landowners. The Court mandated the SLAO to calculate new compensation
reflecting market values as of the year 2019 instead of 2003, underscoring the
government’s duty to uphold the rights of citizens against arbitrary
deprivation of property.
(Para
49)
JUDGMENT
B.R. Gavai, J. :- Leave granted.
2.
This appeal takes exception to the final judgment and order dated 22nd November
2022 in Writ Appeal No. 678 of 2022 (LA-KIADB) passed by the High Court of
Karnataka at Bengaluru, whereby the Division Bench of the High Court dismissed
the writ appeal filed by the appellants herein against the judgment and order
dated 18th April 2022 in Writ of the High Court dismissing their writ
petition.
FACTS:
3.
The facts, in brief, giving rise to the present appeal are as follows:
3.1.
From 1995 to 1997, the appellants herein purchased various residential sites at
Gottigere Village, Uttarahalli Hobli, Bengaluru South Taluk, Karnataka vide
registered sale deeds and became absolute owners of their respective sites.
3.2.
On 3rd April 1997, a Framework Agreement (hereinafter, “FWA”) was executed
between Government of Karnataka (Respondent No. 1) and Nandi Infrastructure
Corridor Enterprise Ltd. (hereinafter, “NICE”) (Respondent No. 6) envisaging
the Infrastructure Corridor Project connecting Bengaluru-Mysuru (hereinafter,
“Bengaluru-Mysuru Infrastructure Corridor Project” or “BMICP”). As per the FWA,
the State Government undertook to acquire about 13,237 acres of land from
private persons and about 6,956 acres of Government land. In all 20,193 acres
of land was agreed to be conveyed and transferred in favour of Respondent No. 6
(NICE) for implementation of the BMICP.
3.3.
On 14th October 1998, Respondent No. 6 applied to Karnataka Industrial Areas
Development Board (hereinafter, “KIADB”) (Respondent No. 2) to make available
the lands for the project.
3.4.
On 29th January 2003, a preliminary notification was issued by Respondent No. 2
(KIADB) under sub-section (1) of Section 28 of the Karnataka
Industrial Areas Development Act, 1966 (hereinafter, “KIAD Act”) for acquiring
lands for the BMICP. Notices were issued under sub-section (2) of Section
28 of KIAD Act seeking objections from the land-owners. The appellants
also submitted their objections.
3.5.
On 5th July 2003, upon consideration of the objections to the Preliminary
Notification, the Final Notification was issued by Special Deputy Commissioner
KIADB (Respondent No. 3).
3.6.
On 22nd November 2005, the possession of the appellants’ land was taken over by
Respondent No. 2 (KIADB) and subsequently handed over to Respondent No. 6
(NICE) and its sister concern Nandi Economic Corridor Enterprises Ltd. (NECE)
(Respondent No. 7). However, no Award was passed immediately for such
acquisitions.
3.7.
In 2009-10, the land-owners filed Writ Petitions before the High Court of
Karnataka with a prayer to quash the acquisition notifications insofar as it
relates to their lands. In the alternative, the land-owners sought a
direction to the concerned authorities to allot residential sites of equal
dimension.
3.8.
Vide judgment and order dated 15th June 2011, a Division Bench of the High
Court held that the acquisition notifications cannot be quashed at such a
belated stage and that there cannot be any direction for allotment of
alternative sites to the land-owners. In the result, the batch of Writ
Petitions filed by the land-owners were dismissed, however, liberty was
reserved to approach the concerned authorities if any rehabilitation programme
is specifically worked out or if any welfare programme is generally available.
3.9.
On 12th February 2016, in terms of the judgment and order of the High Court
dated 15th June 2011, some of the land-owners submitted a representation
inter-alia to the Government of Karnataka, KIADB and NICE to frame a
rehabilitation scheme as mandatorily required under the FWA and to allot
alternative sites along with benefits under the scheme at the earliest.
3.10.
On non-consideration of their representation, the landowners filed Writ
Petitions before the High Court being W.P. Nos. 49812-49863 of 2016
(LA-KIADB), with a prayer to direct the State of Karnataka and KIADB to
implement the request made in the representation dated 12th February 2016 at
the earliest 3.11. Vide order dated 24th March 2017, a learned Single Judge of
the High Court disposed of the Writ Petitions filed by the land-owners by
directing the State of Karnataka and KIADB to consider their representation and
pass appropriate orders, in accordance with law, as expeditiously as possible.
3.12.
Alleging non-compliance of the order of the learned Single Judge dated 24th
March 2017, Contempt Petitions being C.C.C. No. 2434 of 2018 and C.C.C. No.
18-65 of 2019 came to be filed by the land-owners.
3.13.
During the pendency of the Contempt Petitions, the Special Land Acquisition
Officer-1, KIADB (BMICP), Bengaluru (hereinafter, “SLAO”) (Respondent No. 4),
on 22nd April 2019, passed an Award for payment of compensation in respect of
lands belonging to the erstwhile land-owners. In terms of the legal opinion
given by the Advocate General, Respondent No. 4 decided to postpone the date of
Preliminary Notification from 29th January 2003 to the year 2011 and decided to
consider the guideline rates prevailing in the said year and formulate an
award. An amount of Rs. 32,69,45,789/- was, accordingly, awarded for 11 Acre
1.25 Guntas of land.
3.14.
In view of the Award dated 22nd April 2019, a compliance report along with an
endorsement came to be filed by the KIADB in the contempt proceedings initiated
by the land-owners before the High Court. Therefore, a Division Bench of the
High Court, vide order dated 27th November 2019, dismissed as withdrawn the
Contempt Petitions with liberty to challenge the endorsement in accordance with
law.
3.15
On 19th June 2019, Respondents No. 6 and 7 (hereinafter collectively referred
to as “Project Proponents”) filed Writ Petitions being W.P. No. 26085 of 2019
and W.P. No. 31407 of 2019 before the Karnataka High Court challenging several
Awards passed by the SLAO, including the Award dated 22nd April 2019. The
Project Proponents were aggrieved by the Award dated 22nd April 2019 inasmuch
as, on account of delay not attributable to them, they are being called upon to
pay higher compensation. It was their contention that the compensation should
be determined on the basis of the market value of land as on the date of
the Preliminary Notification and that the date could not have been shifted.
3.16.
On 5th January 2021, the erstwhile land-owners filed impleadment application in
the Writ Petitions filed by the Project Proponents. The appellants herein,
thereafter, filed a substantive Writ Petition being W.P. No. 1627 of 2021 on 1
st June 2021. The appellants were aggrieved by the Award dated 22nd April 2019
inasmuch as, even though their lands were acquired in the year 2003, no
compensation for such acquisition has been disbursed to the appellants despite
a lapse of 18 years. It was their contention that the compensation should be
determined as per the current market value of the lands.
3.17.
Vide common judgment and order dated 18th April 2022, a learned Single Judge of
the Karnataka High Court at Bengaluru allowed the Writ Petitions filed by the
Project Proponents. The High Court quashed the Award dated 22nd April 2019
passed by Respondent No. 4 (SLAO). In view of the decision in the Writ
Petitions filed by the Project Proponents, the Writ Petition filed by the
appellants herein was disposed of as the same did not survive for consideration
inasmuch as the Award dated 22nd April 2019 was quashed. Ultimately, the
High Court directed the concerned authorities to pass fresh awards in
accordance with law and after providing sufficient and reasonable opportunity
to the parties as expeditiously as possible and at any rate within a period of
three months.
3.18.
Aggrieved thereby, the appellants herein filed a Writ Appeal being W.A. No. 678
of 2022 (LA-KIADB). Vide impugned judgment and order dated 22nd November 2022,
the Division Bench of the High Court dismissed the Writ Appeal filed by the
appellants herein. Hence, the present appeal by way of special leave.
4.
We have heard Shri R. Chandrachud, learned counsel appearing on behalf of the
appellants, Shri Atmaram N. S. Nadkarni, learned Senior Counsel for Respondents
No. 6 and 7, Shri Avishkar Singhvi, learned Additional Advocate General
appearing for the State of Karnataka and Shri Purushottam Sharma Tripathi for
Respondents Nos. 2 to 5.
SUBMISSIONS:
5.
Shri Chandrachud submitted that the Division Bench of the High Court
erroneously dismissed the Writ Appeal against the judgment and order of the
learned Single Judge of the High Court as “premature”. It is submitted
that the Writ Appeal was not premature as the appellants’ plea to shift the
date for considering the market value of land as on the date of the Award and
not as on the date of the Preliminary Notification was rejected by the learned
Single Judge and thus the issue stood decided against the appellants. It is
further submitted that more than 21 years have passed since the Preliminary Notification
was passed acquiring the appellants lands and they have not received any
compensation yet for the same. Relying on the judgments of this Court in Ram
Chand and Others v. Union of India and Others[(1994) 1 SCC 44 : 1993 INSC 315] and Tukaram Kana Joshi and
Others Through Power-of-Attorney Holder v. Maharashtra Industrial
Development Corporation and Others[(2013)
1 SCC 353 : 2012 INSC 503], it is submitted that in exceptional cases, the
authorities must be directed to determine compensation on the basis of market
value of the land as on the date of the Award by notionally shifting the date
of the Preliminary Notification. It is lastly submitted that the compensation
be determined as per the provisions contained in the Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation and Resettlement Act,
2013 (hereinafter, “2013 LA Act”) inasmuch as in terms of Section
30 of the KIAD Act, the provisions of the Land Acquisition
Act 1894 (hereinafter, “1894 LA Act”) have been made applicable
mutatis mutandis for the purposes of determination and award of
compensation. Reliance in this regard was placed by the learned counsel
for the appellants on the judgment of this Court in Maharashtra State Road
Transport Corporation v. State of Maharashtra and Others[(2003) 4 SCC 200 : 2003 INSC 137].
6.
Per contra, Shri Nadkarni for Respondents No. 6 and 7 submitted that between
2009 and 2012, the Project Proponents wrote several letters to Respondent No. 2
(KIADB) requesting for awards to be passed. It is further submitted that as no
awards were passed by the SLAOs, the Project Proponents were constrained to
file Writ Petition before the High Court seeking direction to pass awards which
was allowed in 2013, thereafter, on non-compliance the Project Proponents
initiated contempt proceedings in 2015 as no awards were still passed. It was,
therefore, submitted that if this Court is inclined to grant any relief in the
form of additional compensation or direct shifting of date as sought for,
it may be seen that there was no error or delay on part of the Project
Proponents, who have deposited compensation with Respondent No.2 (KIADB) as per
the agreement and therefore any additional liability should fall on the State
Government and/or the KIADB. Relying on the judgment of this Court
in Competent Authority v. Barangore Jute Factory and Others[(2005) 13 SCC 477 : 2005 INSC 585], it
is submitted that shifting of date can only take place in very rare
circumstances. It is further submitted that there is no question of awarding
compensation under the 2013 LA Act and a completely new case has been
sought to be made out before this Court, which was not contended before the
learned Single Judge or Division Bench of the High Court. It is lastly
submitted that the appellants never sought directions to the State
Government/SLAO to pass awards and that steps in that regard were taken only in
the year 2021 which was pursuant to the various proceedings initiated by the
Project Proponents.
7.
Shri Singhvi for Respondent No. 1 submitted that the appellants’ claims are
premature and speculative, as they have yet to exhaust remedies available
under the ongoing award proceedings. It is further submitted that the Division
Bench of the High Court in the impugned judgment and order, expressly held that
the issue of shifting the date of acquisition notification can only be examined
after the award has been passed by the SLAO. It was, therefore, submitted that
present appeal is untenable at this stage.
8.
Shri Purushottam Sharma Tripathi for Respondent Nos. 2 to 5 submitted that the
SLAO passed the Award dated 22nd April 2019, on the basis of specific opinion
tendered by the learned Advocate General with regard to shifting of the date.
It is submitted that the learned Single Judge of the High Court, upon
consideration of the material placed before it, has quashed the Award and
directed the SLAO to pass fresh awards within a stipulated timeframe. It is
further submitted that pursuant to the directions by the learned Single Judge
of the High Court, the SLAO has now passed fresh awards for the acquired lands
and if the appellants are aggrieved by the compensation awarded, they may take
such steps as are permissible in law. It is, therefore, submitted that this
Court should not interfere with the concurrent findings of the
learned
Single Judge and the Division Bench of the High Court.
DISCUSSION
AND ANALYSIS:
9.
To consider the case of the appellants, it would be appropriate to refer to the
prayer clause of their Writ Petition before the High Court. The appellants
herein had filed Writ Petition being W.P. No. 1627 of 2021 (LA-KIADB) with the
following prayers:
“WHEREFORE, the Petitioners most
respectfully prays that this Hon’ble Court be pleased to:
a. Issue a writ of certiorari or
any other writ of the same nature to quash and setting aside the Impugned Award
dated 22.04.2019 passed by the Respondent No.14)/1998-99, 39 (30, 31, 37, 38, 40)/2002-03
SLAO-1, produced at ANNEXURE – A;
b. Consequent to prayer (a) issue
a writ of mandamus or any other writ of the same nature to direct the
Respondents to issue notice to Petitioners for determining compensation and
pass the Award as per market value of land closest to date of passing the
Award;
c. Grant such other reliefs as
this Hon’ble Court deems fit in the above circumstances of the case, in the
interests of justice and equity.”
10.
It is relevant to note that prior to the appellants herein Respondents No. 6
and 7 (Project Proponents) had also filed Writ Petitions before the High Court.
From a perusal of the judgment and order of the learned Single Judge dated 18th
April 2022, it is clear that the Project Proponents by way of Writ Petitions
being W.P. No. 26085 of 2019 and W.P. No. 31407 of 2019 had also challenged the
awards. Therefore, in the three writ petitions before the learned Single Judge,
a common question with regard to the legality, validity and correctness of the
Award dated 22nd April 2019 was raised.
11.
Before adverting to the findings of the learned Single Judge on the legality of
the Award dated 22nd April 2019, it would be appropriate to reproduce certain
extracts from the Award, as under:
“14. Valuation of land:
In the notification dated: 29/01/2003
issued under Section 28(1) of the Survey number lands, based on the
above sales figures, the value is Rs. 2,90,532/- per acre and the guidance
value is Rs. 6.00 lakhs. Therefore, if the guidance value is Rs. 6.00 lakhs
including all other allowances, this rate will be found to be real and fair.
Accordingly, it was decided and declared the award on 05/07/2018 and submitted
for approval.
Chief Executive Officer and
Executive Member wrote a letter vide No. KIADB/CEO&EM/16/2019- 20 dated
16/04/2019. Along with the said letter, Government’s letter and Advocate
General’s opinion are attached, it is suggested to prepare the revised award as
per the opinion given by the Advocate General and submit it for approval. In
this regard, this office letter No. KIADB/BMICP/LAQ(1)/G.I/01/2019-20 dated
22/04/2019 has been written to the Special Deputy Commissioner, KIADB (BMICP)
seeking clarification on other issues that there is no scope for revising the
current decision. On 22/04/2019 as per the Chief Executive Officer and
Executive Member’s letter No. KIADB/BMICP/LAQ/CR/31/2013-14 dated 22/04/2019,
it is said that it has been suggested to submit again as per the Advocate
General’s opinion and based on the previous judgments of the Hon’ble Supreme
Court in several cases regarding framing of compensatory rate/award in land
acquisition cases that even for the lands acquired for BMICP scheme, it has
been again instructed to prepare a revised decision immediately as per the
rules and submit it for the approval of the government. For revising the award
and not considering the preliminary notification, the Advocate General in his
legal opinion dated 16/04/2019 has given the following legal opinion:
“KIADB and the State do not have
any choice but to pass the award which may be passed taking into account and
consideration the market value of the property as on date.” As per the opinion
given by the present Advocate General, the award has to be made at current
market rate equal to the current market rate. In this regard, the Hon’ble
Supreme Court in several cases has issued preliminary notification, final
notification and handed over the assets to the Claims Department, but in the
case where no award has been made for ten years, it is appropriate to pay real
and fair land compensation to the land owners to avoid injustice, in such
cases, the date of preliminary notification should be changed to the date of
handing over the assets to the Claims Department, which was prevailing on
that date. The order is to create a judgment considering the market rate. The
following civil appeal cases of the Hon’ble Supreme Court have been perused to
form a award in this regard.
1. CA No. 7015-7018/2005
(Competent Authority V/s Barangore Jute Factory and Others)
2. SLP (Civil) No. 1787473/2004
(State of M.P. V/s Onkar Prasad Patel)
3. CA No. 965/1979 with CA No.
3325/1984, 2185-87/1980, 2381/1980, SLP No. 12352-53/1984, 10572-74/1984 and
others (Gauri Shankar Gaur and others V/s State of U.P. and others)
4. CA No. 2739/2000 with Nos. 2737/2000,
2738/2000, 2736/2000 Contempt Petition (C) No. 62/1999 (Haji Saeed Khan and
others V/s State of U.P. and others).
In the above cases the Hon’ble
Supreme Court has ordered to change the preliminary notification to the date of
handing over of the asset or to an appropriate date conducive to giving
equitable relief in cases where there is severe delay in adjudication.
Based on the above judgments of
the Hon’ble Supreme Court, in the present case, the possession of the land was
handed over on 05/04/2004, 22/11/2005 and 25/11/2005, if the award is framed
considering the guideline rates of 2011 (sic), it is not possible to give real
and fair compensation to the land owner.
Therefore, with a view to
providing real and fair land compensation to the landowners, it was decided to
postpone the date of preliminary notification to the year 2011 and decided to
consider the guideline rates prevailing in the said year and formulate an award
as per the legal opinion given by the Advocate General.”
(emphasis
supplied)
12.
It can thus be seen that the learned Advocate General rendered an opinion on
16th April 2019, wherein it was stated that while passing the awards, the
market value as on date has to be taken on account of enormous delay in passing
the awards. KIADB forwarded the opinion to the Special Deputy Commissioner
(BMICP) and SLAO directing them to pass the awards as per the opinion. On 22nd
April 2019, the SLAO wrote letters to the Special Deputy Commissioner (BMICP)
raising certain queries with regard to passing of fresh awards and the
compensation to be calculated in view of awards already passed by them and sent
for approval on 3rd November 2018. In response to the said letters, the CEO of
KIADB once again addressed a letter dated 22nd April 2019, to the Special
Deputy Commissioner (BMICP) and the SLAO instructing them to pass the awards as
directed in the opinion of the learned Advocate General.
13.
It can further be seen that the opinion of the learned Advocate General as well
as the judgments of this Court referred to in the Award were the only two
factors that were taken into account for the purpose of passing the Award
dated 22nd April 2019, by Respondent No. 4 (SLAO) by shifting/postponing the
date of the Preliminary Notification to the year 2011 and by considering the
guideline rates prevailing in the said year.
14.
Aggrieved by the suo-motu shifting/postponing of the date of the Preliminary
Notification, the Project Proponents, who as a result were called upon to pay
higher compensation, had filed a Writ Petition before the High Court. The
appellants herein filed an impleadment application in the Writ Petition filed
by the Project Proponents so also a substantive Writ Petition with prayers
referred to hereinbefore. Their grievance was two-fold to quash the Award and
to direct passing of an Award as per market value of land closest to date of
passing the Award.
15.
For the common prayer qua quashing of the Award dated 22nd April 2019, it will
be profitable to refer to the following paragraphs of the judgment and order
dated 18th April 2022, passed by the learned Single Judge of the High Court:
“17.8 A perusal of the impugned
awards will indicate that the opinion of the learned Advocate General as well
as the judgments of the Apex Court referred to in the awards were the only
two factors that were taken into account for the purpose of passing the awards
by the SLAOs. As stated supra, in so far as the opinion of the learned Advocate
General is concerned, the same with regard to shifting of the date to reckon
the market value of the land from the date of the preliminary notification to a
later date is concerned, the said opinion was beyond the scope and ambit of the
query put forth to him and consequently, the said opinion could not have been
made the basis by the SLAOs to pass the impugned awards.
X—X —X —X —X —X —X
17.10 The second
factor/circumstance that has been taken into account by the SLAOs to shift the
date to reckon the market value of the lands from the date of the preliminary
notification to a later/subsequent dates is by placing reliance upon the
following decisions of the Apex Court viz.,
a. Competent Authority Vs.
Barangor Jute Factory C/w State of Madhya Pradesh Vs. Onkar Prasad
Patel – (2005) 13 SCC 47
b. Gaurishankar Gaur Vs. State
of Uttar Pradesh – (1994) 1 SCC 92; and
c. Haji Saeed Khan Vs. State
of Uttar Pradesh – (2001) 9 SCC 513.
17.11 In this context, it is
relevant to state that as can be seen from the aforesaid decisions as well as
various decisions of the Apex Court as well as this Court referred to supra by
both sides, that the market value of the acquired lands has to be taken as on
the date of the preliminary notification as contemplated under Section
11 of the L.A. Act, 1894; it has been held that under exceptional
circumstances, where either the Apex Court or High Courts came to the
conclusion that the acquisition proceedings themselves were liable to be
quashed on account of certain illegalities or infirmities in the acquisition
process/procedure, it was permissible only for the Apex Court in exercise of
its powers under Article 32/142 or the High Courts under Article
226 of the Constitution of India to shift the date to a later/subsequent
date; however, this power to shift the date is available only to either the
Apex Court or the High Courts and not definitely/certainly to the SLAOs or the
State Government; in other words, a perusal of the decisions referred to supra,
will indicate that in cases, where the Apex Court as well as this Court deemed
it necessary to shift the date in order to do complete and substantial justice,
inherent powers of the Courts were invoked and the dates were shifted in order
to ensure no hardship, loss or prejudice would be caused to the land losers.
17.12 A perusal of the decisions
relied upon by the SLAOs in the impugned awards referred to supra, will clearly
indicate that in the said cases, the Apex Court has invoked its extraordinary
jurisdiction and powers under Article 142 of the Constitution of India
and in the peculiar/special facts and circumstances obtaining in the said
cases, the Apex Court had shifted the date to reckon the market value. The
SLAOs clearly fell in error in placing reliance upon the said decisions of the
Apex Court for the purpose of shifting the date from the date of the
preliminary notification without appreciating that the said shifting of the
date by the SLAOs or the State Government is not legally permissible in law
either under the provisions of the L.A. Act, 1894 or the KIAD
Act or the Rules or by any judicial precedent. It is also relevant to
state that even as per the aforesaid judgments, shifting of the date from the
date of the preliminary notification to any later/subsequent date has been done
only up to the date of taking possession from the land losers. In the
instant case, the impugned awards disclose that the SLAOs have shifted the date
to a date subsequent/later to the date of taking possession.
Under these circumstances, it is
clear that the impugned awards purporting to shift the date suffers from
several legal and factual infirmities and illegalities which vitiate the
impugned awards, which deserve to be quashed on this ground also.”
(emphasis
supplied)
16.
It can thus be seen that the learned Single Judge of the High Court, upon
appreciation of the material placed on record, was of the view that insofar as
the opinion of the learned Advocate General with regard to shifting of the date
of the preliminary notification to a later date is concerned, the said opinion
was beyond the scope and ambit of the query put forth to him and consequently,
the said opinion could not have been made the basis by the SLAO to pass the
Award. It is further to be seen that the learned Single Judge of the High Court
after considering the provisions of 1894 LA Act, KIAD Act and various decisions
of this Court, observed that the market value of the acquired land has to be
taken as on the date of the preliminary notification as contemplated
under Section 11 of the 1894 LA Act. Further, the learned Single
Judge of the High Court observed that only in exceptional circumstances, where
either this Court or the High Court comes to the conclusion that the
acquisition proceedings themselves were liable to be quashed on account of
certain illegalities or infirmities in the acquisition process/procedure, it
was permissible only for this Court in exercise of its powers under Article
32/142 or the High Courts under Article 226 of the Constitution of
India to shift the date to a later/subsequent date. It was further observed
that this power to shift the date is available only to either this Court or the
High Courts and not definitely/certainly to the SLAOs or the State Government.
17.
We are in agreement with the findings of the learned Single Judge of the High Court,
inasmuch as the SLAO cannot shift/postpone the date of preliminary
notification. In case, upon appreciation of the material placed on record if
this Court or the High Court, in exceptional circumstances, came to the
conclusion that the acquisition proceedings themselves were liable to be
quashed only then by exercising inherent powers this Court under Article 32/142
or the High Courts under Article 226 of the Constitution of India
respectively can shift/postpone the date of preliminary notification to a later
date. In our considered opinion, therefore, the learned Single Judge of
the High Court rightly came to the conclusion that the Award dated 22nd April
2019 be quashed and set aside and ordered accordingly.
18.
Having decided thus, in the Writ Petitions filed by the Project Proponents, the
learned Single Judge of the High Court came to the conclusion that the Writ
Petition filed by the appellants herein before the High Court does not survive
for consideration and the same was, accordingly, disposed of.
19.
Aggrieved thereby, the appellants herein filed an intra- court appeal being
Writ Appeal No. 678 of 2022 (LA-KIADB) before the Division Bench of the High
Court.
20.
The Division Bench of the High Court vide impugned judgment and order dated
22nd November 2022 upon consideration of the material placed before it, in
paragraph 9, observed thus:
“9. Further, the learned Single
Judge held that the SLAO has to determine the compensation as on the date of
issuing the preliminary notification as contemplated under Section
11 of the Land Acquisition Act, 1894, and not to shift the date to a
later/subsequent date. The learned Single Judge has set aside the award passed
by the SLAO and directed the SLAO to reconsider and pass award. The grievance
of the petitioner regarding shifting the date at any later or subsequent date
could be considered only if award is passed by the SLAO.
The SLAO is yet to pass an award.
The grievance raised by the petitioner in this writ appeal is premature. If the
petitioner is dissatisfied with the award to be passed by the SLAO, liberty is
reserved to the petitioner to raise the grounds urged in this appeal in the
appropriate proceedings before the appropriate forum. The question of considering
the shifting of date from the date of preliminary notification to any other
date would arise only when the award is passed. The cause of action arose for
the petitioner to raise the said issue only after the award is passed. The
shifting of the date to a later/subsequent date is available only to the
Hon’ble Apex Court and this Court, but not to the SLAO or State Government…”
(emphasis
supplied)
21.
It can thus be seen that the Division Bench of the High Court dismissed the
Writ Appeal on the ground that the learned Single Judge has set aside the award
passed by the SLAO and directed the SLAO to reconsider and pass award and so
the grievance regarding shifting the date at any later or subsequent date could
be considered only if an award is passed by the SLAO. The Division Bench of the
High Court was, therefore, of the opinion that the grievance sought to be
raised in the writ appeal is premature and that the question of considering the
shifting of date of preliminary notification to any other date would arise only
when the award is passed.
22.
In the present appeal, it was sought to be contended by the learned counsel for
the appellants that the Writ Appeal was not pre-mature inasmuch as the prayer
to shift the date for considering the market value of the land as on the date
of the award and not as on the date of the preliminary notification was
rejected by the learned Single Judge of the High Court and thus the issue stood
decided against the appellants, as a consequence of which the cause of action remained.
23.
We are of the opinion that the contention of the learned counsel for the
appellants is liable to be accepted. We say so because upon adjudication of the
Writ Petitions filed by the Project Proponents, the learned Single Judge of the
High Court came to the conclusion that the Award dated 22nd April 2019, is
liable to be quashed and set aside and ordered accordingly. However, upon
consideration of the extant position of law, the learned Single Judge further
directed that the SLAO has to determine the compensation as on the date of
issuance of the preliminary notification and not to shift the date to a
later/subsequent date. Therefore, the learned Single Judge of the High Court
while exercising inherent powers under Article 226 of the Constitution
quashed and set aside the Award dated 22nd April 2019, but decided against
granting relief to the appellants by shifting/postponing the date of the
preliminary notification to a later/subsequent date. In our opinion, therefore,
the cause of action with regard to prayer clause (b) of the Writ Petition filed
by the appellants herein still survives for consideration. The Division Bench
of the High Court should have, especially taking into consideration the facts
and circumstances of the present case, at least considered the case of the
appellants herein with regard to said prayer. We are, therefore, of the opinion
that the impugned judgment and order dated 22nd November 2022, passed by the
Division Bench of the High Court is liable to be quashed and set aside on this
short ground alone. We order accordingly.
24.
Having set aside the impugned judgment and order passed by the Division Bench
of the High Court on the aforesaid ground, we shall now proceed to examine if
the relief sought by the appellants herein in prayer clause (b) of the Writ
Petition referred to hereinbefore is liable to be granted or not.
25.
For the purpose of consideration of the relief sought by the appellants herein,
it will be appropriate to refer to a few judgements of this Court on which
reliance has been placed by the learned counsel for the parties.
26.
In the case of Ram Chand (supra), proceedings were instituted for quashing the
land acquisition proceedings, which had been initiated between the years 1959
and 1965 by issuance of notifications under Section 4 of the
1894 LA Act but in which no awards were made upto the years 1979-80,
although the declarations under Section 6 of the 1894 LA
Act had been made in the years 1966 and 1969. The question sought to be
answered by this Court in the aforesaid case was as to if a person is paid
compensation in the year 1980/81 at the market rate prevailing twenty years
back, will that be in compliance of the constitutional and statutory mandate.
In this regard, this Court observed thus:
“14. … Ignoring the escalation of
the market value of the lands, especially near the urban agglomeration or
metropolitan cities, will amount to ignoring an earthquake and courts can
certainly take judicial notice of the said fact. The interest and the solatium,
which have to be paid under the provisions of the Act, are linked with the
market value of the land with reference to the date of the notification under
sub-section (1) of Section 4 of the Act. If a decision had been taken
as early as in the year 1966, by issuance of declarations under Section 6,
that the lands belonging to the different cultivators, who held those lands
within the ceiling limit for cultivation, were needed for public purpose,
respondents should have taken steps for completion of the acquisition
proceedings and payment of compensation at an early date. In the present cases,
unless a justification is furnished on behalf of the respondents, can it be
said that the statutory power of making an award under Section 11 has
been exercised within a reasonable time from the date of the declaration
under Section 6? Due to escalation in prices of land, more so in this
area, during the preceding two decades, in reality, the market rate, on the
date of the notification under Section 4(1) is a mere fraction, of
the rate prevailing at the time of its determination in the Award.”
(emphasis
supplied)
27.
It can thus be seen that this Court in the aforesaid case has observed that the
respondents therein should have taken steps for completion of the acquisition proceedings
and payment of compensation at an early date. It was further observed that due
to escalation in prices of land, more so in the area in question, during the
preceding two decades, in reality, the market rate, on the date of the
notification under Section 4(1) of the
1894 LA Act is a mere fraction of the rate prevailing at the time of
its determination in the Award. This Court, however, in the aforesaid case was
also dealing with a challenge to the acquisition proceedings itself. In this
regard, this Court observed thus:
“16. On behalf of the
respondents, it was pointed out that the petitioners have approached this Court
only after making of the awards, or when awards were to be made, having waited
for more than fourteen years, without invoking the jurisdiction of the High
Court under Article 226 or of this Court under Article
32. It is true that this Court has taken note of delay on the part of the
petitioners concerned in invoking the jurisdiction of the High Court or of this
Court for quashing the land acquisition proceedings on the ground that the
proceedings for acquisition of the lands in question have remained pending for
more than a decade, in the cases of Aflatoon v. Lt. Governor of
Delhi [(1975) 4 SCC 285] and Ramjas Foundation v. Union of India [1993
Supp (2) SCC 20 : AIR 1993 SC 852].
According to us, the question of
delay in invoking the writ jurisdiction of the High Court under Article
226 or of this Court under Article 32, has to be considered along
with the inaction on the part of the authorities, who had to perform their
statutory duties. Can the statutory authority take a plea that although it has
not performed its duty within a reasonable time, but it is of no consequence
because the person, who has been wronged or deprived of his right, has also not
invoked the jurisdiction of the High Court or of this Court for a suitable writ
or direction to grant the relief considered appropriate in the circumstances?
The authorities are enjoined by the statute concerned to perform their duties
within a reasonable time, and as such they are answerable to the Court why such
duties have not been performed by them, which has caused injury to claimants.
By not questioning, the validity of the acquisition proceedings for a long time
since the declarations were made under Section 6,
the relief of quashing the acquisition proceedings has become inappropriate,
because in the meantime, the lands notified have been developed and put to
public use. The lands are being utilised to provide shelter to thousands and to
implement the scheme of a planned city, which is a must in the present set-up.
The outweighing public interest has to be given due weight. That is why
this Court has been resisting attempts on the part of the landholders, seeking
quashing of the acquisition proceedings on ground of delay in completion of
such proceedings. But, can the respondents be not directed to compensate the
petitioners, who were small cultivators holding lands within the ceiling limit
in and around Delhi, for the injury caused to them, not by the provisions of
the Act, but because of the non-exercise of the power by the authorities under
the Act within a reasonable time?”
(emphasis
supplied)
28.
It can thus be seen that this Court in the aforesaid case observed that by not
questioning the validity of the acquisition proceedings for a long time since
the declarations were made under Section 6 of the 1894 LA Act,
the relief of quashing the acquisition proceedings has become inappropriate,
because in the meantime, the lands notified have been developed and put to
public use. It was further observed that the lands are being utilized to
provide shelter to thousands and to implement the scheme of a planned city,
which is a must in the present set- up and that the outweighing public interest
has to be given due weight.
29.
Ultimately, this Court in paragraph 27 of the aforesaid case, taking into
consideration the interest of the public, instead of quashing the proceedings
for acquisition, directed that the petitioners therein shall be paid an
additional amount of compensation to be calculated at the rate of 12% per
annum, after expiry of two years from August 23, 1974, till the date of the
making of the awards by the Collector, to be calculated with reference to the
market value of the lands in question on the date of the notifications under sub-section (1) of Section 4 of
the 1894 LA Act.
30. In
the case of Haji Saeed Khan and Others v. State of U.P. and Others[(2001) 9 SCC 513], land was acquired
for the purposes of construction of a housing colony under the “Planned
Development Scheme” in Village Dhimri Pargana, District Moradabad by the
Moradabad Development Authority. The challenge to the land acquisition proceedings
before the High Court in the aforesaid case was dismissed. Aggrieved thereby,
this Court was called upon to adjudicate the lis. This Court, having regard to
the peculiar facts of the aforesaid case, instead of deciding the matter on
merits, suggested to the counsel on both sides that it would be reasonable in
the interests of justice if they agreed that the market value of the property
could be fixed by treating 15th June, 1998, i.e., the date of taking
possession as the date of notification under Section 4(1) of the
1894 LA Act instead of the actual date of notification
under Section 4(1) of the 1894 LA Act i.e., 30th March,
1995. When the suggestion came from the Bench, the counsel appearing on both
sides accepted the suggestion from the Court. Accordingly, this Court upheld
the judgment and order of the High Court, thereby the land acquisition
proceedings were upheld with modification to the limited extent qua the date of
notification under Section 4(1) of the 1894 LA Act shifted
to the date of taking possession.
31. In
the case of Barangore Jute Factory (supra), the subject matter of the
appeals before this Court was the compulsory acquisition of certain lands by
the Central Government by a notification dated 11th June 1998
under Section 3-A of the National Highways Act, 1956 (hereinafter,
“NH Act”). The landowners challenged the acquisition of their land on various
grounds before the Calcutta High Court. The Division Bench of the High Court by
a judgment and order dated 7th April 2004, disposed of the writ-petition
holding the impugned notification regarding compulsory acquisition of land to
be bad in law, however, keeping in view the fact that possession of the
acquired land had already been taken by the authorities, the High Court felt that
no useful purpose would be served by quashing the notification. The High Court
also took note of the power of the acquiring authority to issue a fresh
notification for acquisition of the land which could only lead to possible
increase in the amount of compensation payable to the owners. Keeping these
aspects in view, it ordered that an additional amount of compensation
(calculated at 30% over and above the above the compensation already
determined) be awarded to the landowners. Aggrieved by the judgment and order
of the Calcutta High Court, three appeals by way of special leave were filed
before this Court. The first by the competent authority qua validity of
acquisition notification, second by the National Highways Authority of India
(hereinafter, “NHAI”) qua award of additional compensation to the landowners
and third by the landowners qua the acquisition notification not being quashed
in spite of having been declared as illegal.
32.
The acquisition of land in the aforesaid case was under the NH Act. The
power to acquire land is contained in Section 3-A of the NH Act.
According to sub-section (1) of Section 3-A of the NH Act, where the
Central Government is satisfied that for a public purpose any land is required
for building, maintenance, management or operation of a national highway or
part thereof, it may, by notification in the Official Gazette, declare its
intention to acquire such land. Sub-section (2) of Section 3-A of the
NH Act provides that every notification under sub-section (1) thereof shall
give a brief description of land. Under sub-section (3) of Section
3-A of the NH Act, the competent authority is required to cause the
substance of the notification to be published in two local newspapers, one of
which will be in a vernacular language. The acquisition notification in the
aforesaid case was challenged on the ground that it does not give a brief
description of the land sought to be compulsorily acquired. This Court, upon
consideration of the acquisition notification, observed thus:
“5. …So far as the question
whether the impugned notification meets the requirement of Section
3-A(1) of the Act regarding giving brief description of land is concerned,
we have already shown that even though plot numbers of lands in respect of each
mouza are given, different pieces of land are acquired either as whole or in
part. Wherever the acquisition is of a portion of a bigger piece of land, there
is no description as to which portion was being acquired. Unless it is known as
to which portion was to be acquired, the petitioners would be unable to
understand the impact of acquisition or to raise any objection about user
of the acquired land for the purposes specified under the Act or to make a
claim for compensation. It is settled law that where a statute requires a particular
act to be done in a particular manner, the act has to be done in that manner
alone. Every word of the statute has to be given its due meaning. In our view,
the impugned notification fails to meet the statutory mandate. It is vague. The
least that is required in such cases is that the acquisition notification
should let the person whose land is sought to be acquired know what he is going
to lose. The impugned notification in this case is, therefore, not in
accordance with the law.”
33.
It can thus be seen that this Court in the aforesaid case observed that it is
settled law that where a statute requires a particular act to be done in a
particular manner, the act has to be done in that manner alone. It can further
be seen that this Court held that the acquisition notification therein failed
to meet the statutory mandate and that it was vague. It was further held that
the least that was required was that the acquisition notification therein
should have let the person whose land was sought to be acquired know what he
was going to lose. It was, therefore, held that the acquisition notification
was not in accordance with law.
34.
Having held that the notification regarding acquisition of land was invalid
because it failed to meet the statutory requirements and also having found that
taking possession of the land of the landowners in the aforesaid case in
pursuance to the acquisition notification was not in accordance with law, the
question that arose for the consideration of this Court was as to what relief
can be granted to the landowners. In that regard, this Court observed thus:
“14. … The High Court rightly
observed that the acquisition of land in the present case was for a project of
great national importance i.e. the construction of a national highway. The
construction of a national highway on the acquired land has already been
completed as informed to us during the course of hearing. No useful purpose
will be served by quashing the impugned notification at this stage. We cannot
be unmindful of the legal position that the acquiring authority can always
issue a fresh notification for acquisition of the land in the event of the
impugned notification being quashed. The consequence of this will only be that
keeping in view the rising trend in prices of land, the amount of compensation
payable to the landowners may be more. Therefore, the ultimate question will be
about the quantum of compensation payable to the landowners. Quashing of the
notification at this stage will give rise to several difficulties and practical
problems. Balancing the rights of the petitioners as against the problems
involved in quashing the impugned notification, we are of the view that a
better course will be to compensate the landowners, that is, the writ
petitioners appropriately for what they have been deprived of. Interests of
justice persuade us to adopt this course of action.”
35.
It can thus be seen that this Court in the aforesaid case observed that the
Calcutta High Court rightly observed that the acquisition of land was for a
project of great national importance i.e., the construction of a national
highway. This Court further observed that the construction of a national
highway on the acquired land had already been completed. It was further
observed that no useful purpose would be served by quashing the acquisition
notification at this stage. Pertinently, this Court observed that the acquiring
authority could always issue a fresh notification for acquisition of the land
in the event the acquisition notification therein was quashed and that the
consequence of that would only be that the amount of compensation payable to
the landowners may be more. Therefore, this Court observed that the ultimate
question would be about the quantum of compensation payable to the landowners.
Having observed so, this Court held that the better course would be to
compensate the landowners appropriately for what they have been deprived of and
that the interests of justice persuade this Court to adopt that course of
action. The relief, therefore, granted by this Court in the aforesaid case
was molded in the form of paragraph 15, which reads as under:
“15. Normally, compensation is
determined as per the market price of land on the date of issuance of the
notification regarding acquisition of land. There are precedents by way of
judgments of this Court where in similar situations instead of quashing the
impugned notification, this Court shifted the date of the notification so that
the landowners are adequately compensated. Reference may be made to:
(a) Ujjain Vikas Pradhikaran v.
Raj Kumar Johri [(1992) 1 SCC 328]
(b) Gauri Shankar Gaur v. State
of U.P. [(1994) 1 SCC 92]
(c) Haji Saeed Khan v. State of
U.P. [(2001) 9 SCC 513] In that direction the next step is what should be
the crucial date in the facts of the present case for determining the quantum
of compensation.
We feel that the relevant date in
the present case ought to be the date when possession of the land was taken by
the respondents from the writ petitioners. This date admittedly is 19-2-2003.
We, therefore, direct that compensation payable to the writ petitioners be
determined as on 19-2- 2003, the date on which they were deprived of possession
of their lands. We do not quash the impugned notification in order not to
disturb what has already taken place by way of use of the acquired land for
construction of the national highway. We direct that the compensation for the
acquired land be determined as on 19-2-2003 expeditiously and within ten weeks
from today and the amount of compensation so determined, be paid to the writ
petitioners after adjusting the amount already paid by way of compensation
within eight weeks thereafter. The claim of interest on the amount of
compensation so determined is to be decided in accordance with law by the
appropriate authority. We express no opinion about other statutory rights, if
any, available to the parties in this behalf and the parties will be free to
exercise the same, if available. The compensation as determined by us under
this order along with other benefits, which the respondents give to parties
whose lands are acquired under the Act, should be given to the writ petitioners
along with what has been directed by us in this judgment.”
(emphasis
supplied)
36.
It can thus be seen that this Court in the aforesaid case observed that
normally, compensation is determined as per the market price of land on the
date of issuance of the notification regarding acquisition of land but there
are judgments of this Court where in similar situations instead of quashing the
impugned notification, this Court shifted the date of the notification so that
the landowners are adequately compensated. This Court directed that
compensation payable to the landowners be determined as on the date when
possession of land was taken by the respondents therein i.e., 19th February
2003.
37.
In the case of Tukaram Kana Joshi (supra), the land situated in Village
Shirwame, Taluka and District Thane, stood notified under Section
4 of the 1894 LA Act on 6th June 1964 for establishment of Ulhas
Khore Project i.e., a project for industrial development. However, no
subsequent proceedings were taken up thereafter, and the acquisition
proceedings lapsed. The respondent-authorities therein realised, in 1981, that
grave injustice had been done to the appellants therein and so a fresh
notification under Section 4 of the 1894 LA Act was issued
on 14th May 1981. However, no further proceedings were initiated and therefore,
such proceedings also died a natural death. In the aforesaid case, when the
appellants therein reached this Court, this Court in unequivocal terms observed
that even after the right to property ceased to be a fundamental right, taking
possession of or acquiring the property of a citizen most certainly tantamounts
to deprivation and such deprivation can take place only in accordance with
“law”, as the said word has specifically been used in Article
300-A of the Constitution. In paragraph 22 of the aforesaid case, this
Court observed that the concerned-State therein came forward with a welcome
suggestion stating that in order to redress the grievances of the appellants
therein, the respondent authorities would notify the land in dispute
under Section 4 of the 1894 LA Act and that the market
value of the land in dispute would be assessed as it prevails on the date
on which Section 4 notification is again published in the Official
Gazette.
38.
In the aforesaid case of Tukaram Kana Joshi (supra), this Court observed that
the right to property is now considered to be not only a constitutional or a
statutory right but also a “human right”. It was further observed that human
rights are considered in the realm of individual rights, such as right to
health, right to livelihood, right to shelter and employment, etc. This Court
further observed that now, however, human rights are gaining an even greater
multifaceted dimension and that the right to property is considered very much
to be a part of such new dimension.
39.
It would be appropriate to refer to two recent pronouncements of this Court on
the right to property.
40.
This Court, in the case of Vidya Devi v. State of Himachal Pradesh and
Others[(2020) 2 SCC 569 : 2020 INSC 23],
while surveying the earlier judgments on the issue, has observed thus:
“12.1. The appellant was forcibly
expropriated of her property in 1967, when the right to property was a
fundamental right guaranteed by Article 31 in Part III of the
Constitution. Article 31 guaranteed the right to private property
[State of W.B. v. Subodh Gopal Bose, (1953) 2 SCC 688 : AIR 1954 SC 92] ,
which could not be deprived without due process of law and upon just and fair
compensation.
12.2. The right to property
ceased to be a fundamental right by the Constitution (Forty-Fourth
Amendment) Act, 1978, however, it continued to be a human right [Tukaram Kana
Joshi v. MIDC, (2013) 1 SCC 353 : (2013) 1 SCC (Civ) 491] in a welfare State,
and a constitutional right under Article 300-A of the
Constitution. Article 300-A provides that no person shall be deprived
of his property save by authority of law. The State cannot dispossess a citizen
of his property except in accordance with the procedure established by law. The
obligation to pay compensation, though not expressly included in Article
300-A, can be inferred in that Article. [K.T. Plantation (P) Ltd. v. State
of Karnataka, (2011) 9 SCC 1 : (2011) 4 SCC (Civ) 414]
12.3. To forcibly dispossess a
person of his private property, without following due process of law, would be
violative of a human right, as also the constitutional right under Article
300-A of the Constitution. Reliance is placed on the judgment
in Hindustan Petroleum Corpn. Ltd. v. Darius Shapur Chenai [Hindustan
Petroleum Corpn. Ltd. v. Darius Shapur Chenai, (2005) 7 SCC 627] , wherein
this Court held that: (SCC p. 634, para 6)
“6. … Having regard to the
provisions contained in Article 300-A of the Constitution, the State
in exercise of its power of “eminent domain” may interfere with the right of
property of a person by acquiring the same but the same must be for a public
purpose and reasonable compensation therefor must be paid.”
(emphasis
supplied)
12.4. In N. Padmamma v.
S. Ramakrishna Reddy [N. Padmamma v. S. Ramakrishna Reddy, (2008) 15 SCC
517] , this Court held that: (SCC p. 526, para 21)
“21. If the right of property is
a human right as also a constitutional right, the same cannot be taken away
except in accordance with law. Article 300-A of the Constitution protects
such right. The provisions of the Act seeking to divest such right, keeping in
view of the provisions of Article 300-A of the Constitution of India,
must be strictly construed.”
(emphasis
supplied)
12.5. In Delhi Airtech Services
(P) Ltd. v. State of U.P. [Delhi Airtech Services (P) Ltd. v. State of U.P.,
(2011) 9 SCC 354 : (2011) 4 SCC (Civ) 673] , this Court recognised the right to
property as a basic human right in the following words: (SCC p. 379, para 30)
“30. It is accepted in every
jurisprudence and by different political thinkers that some amount of property
right is an indispensable safeguard against tyranny and economic oppression of
the Government. Jefferson was of the view that liberty cannot long subsist
without the support of property. “Property must be secured, else liberty cannot
subsist” was the opinion of John Adams. Indeed the view that property itself is
the seed-bed which must be conserved if other constitutional values are to
flourish, is the consensus among political thinkers and jurists.”
(emphasis
supplied)
12.6. In Jilubhai Nanbhai Khachar
v. State of Gujarat [Jilubhai Nanbhai Khachar v. State of Gujarat, 1995 Supp
(1) SCC 596] , this Court held as follows: (SCC p. 627, para 48)
“48. … In other
words, Article 300-A only limits the powers of the State that no
person shall be deprived of his property save by authority of law. There has to
be
no deprivation without any sanction of law.
Deprivation by any other mode is
not acquisition or taking possession under Article 300-A. In other words, if
there is no law, there is no deprivation.”
(emphasis
supplied)
12.7. In this case, the appellant
could not have been forcibly dispossessed of her property without any legal
sanction, and without following due process of law, and depriving her payment
of just compensation, being a fundamental right on the date of forcible
dispossession in 1967.
12.8. The contention of the State
that the appellant or her predecessors had “orally” consented to the
acquisition is completely baseless. We find complete lack of authority and
legal sanction in compulsorily divesting the appellant of her property by the
State. 12.9. In a democratic polity governed by the rule of law, the State
could not have deprived a citizen of their property without the sanction of
law. Reliance is placed on the judgment of this Court in Tukaram Kana Joshi v.
MIDC [Tukaram Kana Joshi v. MIDC, (2013) 1 SCC 353 : (2013) 1 SCC (Civ) 491]
wherein it was held that the State must comply with the procedure for
acquisition, requisition, or any other permissible statutory mode. The State
being a welfare State governed by the rule of law cannot arrogate to itself a
status beyond what is provided by the Constitution.
12.10. This Court in State
of Haryana v. Mukesh Kumar [State of Haryana v. Mukesh Kumar, (2011) 10
SCC 404 : (2012) 3 SCC (Civ) 769] held that the right to property is now
considered to be not only a constitutional or statutory right, but also a human
right. Human rights have been considered in the realm of individual rights such
as right to shelter, livelihood, health, employment, etc. Human rights have
gained a multi-faceted dimension.
………………
12.13. In a case where the demand for
justice is so compelling, a constitutional court would exercise its jurisdiction
with a view to promote justice, and not defeat it. [P.S. Sadasivaswamy v. State
of T.N., (1975) 1 SCC 152 : 1975 SCC (L&S) 22]”
41. In
the case of Ultra-Tech Cement Ltd. v. Mast Ram and Others[2024 SCC OnLine 2598 : 2024 INSC 709],
this Court observed thus:
“D. Role of the State
under Article 300-A of the Constitution
43. The Right to Property in our
country is a net of intersecting rights which has been explained by this Court
in Kolkata Municipal Corporation v. Bimal Kumar Shah, 2024 SCC OnLine SC
968. A division bench of this Court identified seven non-exhaustive sub-rights
that accrue to a landowner when the State intends to acquire his/her property.
The relevant observations of this Court under the said judgment are
reproduced below:
“…27.
… Seven such sub-rights can be
identified, albeit non-exhaustive. These are : i) duty of the State to inform
the person that it intends to acquire his property - the right to notice, ii)
the duty of the State to hear objections to the acquisition - the right to be
heard, iii) the duty of the State to inform the person of its decision to
acquire - the right to a reasoned decision, iv) the duty of the State to
demonstrate that the acquisition is for public purpose - the duty to acquire
only for public purpose, v) the duty of the State to restitute and rehabilitate
- the right of restitution or fair compensation, vi) the duty of the State to
conduct the process of acquisition efficiently and within prescribed
timelines of the proceedings - the right to an efficient and expeditious
process, and vii) final conclusion of the proceedings leading to vesting - the
right of conclusion…” [Emphasis Supplied] This Court held that a fair and
reasonable compensation is the sine qua non for any acquisition process.
44. In Roy Estate v.
State of Jharkhand, (2009) 12 SCC 194; Union of India v. Mahendra Girji, (2010)
15 SCC 682 and Mansaram v. S.P. Pathak, (1984) 1 SCC 125, this Court
underscored the importance of following timelines prescribed by the statutes as
well as determining and disbursing compensation amount expeditiously within
reasonable time.
45. The subject land came to be
acquired by invoking special powers in cases of urgency under Section
17(4) of the 1894 Act. The invocation of Section
17(4) extinguishes the statutory avenue for the landowners under Section
5A to raise objections to the acquisition proceedings. These circumstances
impose onerous duty on the State to facilitate justice to the landowners by
providing them with fair and reasonable compensation expeditiously. The seven
sub-rights of the landowners identified by this Court in Kolkata Municipal
Corporation (supra) are corresponding duties of the State. We regret to
note that the amount of Rs. 3,05,31,095/- determined as compensation under the
Supplementary Award has not been paid to the landowners for a period of more
than two years and the State of Himachal Pradesh as a welfare State has made no
effort to get the same paid at the earliest.
46. This Court has held
in Dharnidhar Mishra (D) v. State of Bihar, 2024 SCC OnLine SC 932 and
State of Haryana v. Mukesh Kumar, (2011) 10 SCC 404 that the right to property
is now considered to be not only a constitutional or statutory right, but
also a human right. This Court held in Tukaram Kana Joshi thr. Power of
Attorney Holder v. M.I.D.C., (2013) 1 SCC 353 that in a welfare State, the
statutory authorities are legally bound to pay adequate compensation and
rehabilitate the persons whose lands are being acquired. The non-fulfilment of
such obligations under the garb of industrial development, is not permissible
for any welfare State as that would tantamount to uprooting a person and
depriving them of their constitutional/human right.
47. That
time is of the essence in determination and payment of compensation is
also evident from this Court's judgment in Kukreja Construction Company v.
State of Maharashtra, 2024 SCC OnLine SC 2547 wherein it has been held that
once the compensation has been determined, the same is payable immediately
without any requirement of a representation or request by the landowners and a
duty is cast on the State to pay such compensation to the land losers,
otherwise there would be a breach of Article 300-A of the Constitution.
48. In the present case, the
Government of Himachal Pradesh as a welfare State ought to have proactively
intervened in the matter with a view to ensure that the requisite amount
towards compensation is paid at the earliest. The State cannot abdicate its
constitutional and statutory responsibility of payment of compensation by
arguing that its role was limited to initiating acquisition proceedings under
the MOU signed between the Appellant, JAL and itself. We find that the delay in
the payment of compensation to the landowners after taking away ownership of
the subject land from them is in contravention to the spirit of the
constitutional scheme of Article 300A and the idea of a welfare
State.
49. Acquisition of land for
public purpose is undertaken under the power of eminent domain of the
government much against the wishes of the owners of the land which gets
acquired. When such a power is exercised, it is coupled with a bounden
duty and obligation on the part of the government body to ensure that the owners
whose lands get acquired are paid compensation/awarded amount as declared by
the statutory award at the earliest.
50. The State Government, in
peculiar circumstances, was expected to make the requisite payment towards compensation
to the landowners from its own treasury and should have thereafter proceeded to
recover the same from JAL. Instead of making the poor landowners to run after
the powerful corporate houses, it should have compelled JAL to make the
necessary payment.”
42.
Right to Property ceased to be a Fundamental Right by the Constitution
(Forty-Fourth Amendment) Act, 1978, however, it continues to be a human right
in a welfare State, and a constitutional right under Article 300-A of
the Constitution.
43. Article
300-A of the Constitution provides that no person shall be deprived of his
property save by authority of law. The State cannot dispossess a citizen of his
property except in accordance with the procedure established by law.
44.
This Court in the aforesaid case of Vidya Devi (supra) observed that
in a democratic polity governed by the rule of law, the State could not have
deprived a citizen of their property without the sanction of law. It was
further observed that the State being a welfare State governed by the rule
of law cannot arrogate to itself a status beyond what is provided by the
Constitution.
45.
Recently, this Court in the aforesaid case of Ultra-Tech Cement
Ltd. (supra) observed that the Government as a welfare State ought to have
proactively intervened in the matter with a view to ensure that the requisite
amount towards compensation is paid at the earliest. It was further observed
that the State cannot abdicate its constitutional and statutory responsibility
of payment of compensation by arguing that its role was limited to initiating
acquisition proceedings. It was, therefore, observed that the delay in the
payment of compensation, in accordance with law, to the landowners after taking
away ownership of the subject land from them is in contravention to the spirit
of the constitutional scheme of Article 300-A and the idea of a
welfare State.
46. In
the aforesaid case of Ultra-Tech Cement Ltd. (supra), this Court
further observed that acquisition of land for public purpose is undertaken
under the power of eminent domain of the government much against the wishes of
the owners of the land which gets acquired. It was, therefore, observed
that when such a power is exercised, it is coupled with a bounden duty and
obligation on the part of the government body to ensure that the owners whose
lands get acquired are paid compensation/awarded amount as declared by the
statutory award at the earliest.
47.
It will also be appropriate for the purpose of the present discussion to refer
to the judgment of this Court, in the case of K. Krishna Reddy and Others
v. Special Deputy Collector, Land Acquisition Unit II, LMD Karimnagar, Andhra
Pradesh[(1988) 4 SCC 163 : 1988 INSC 265],
specifically in paragraph 12, observed thus:
“12. We can very well appreciate
the anxiety and need of claimants to get compensation here and now. No matter
what it is. The lands were acquired as far back in 1977. One decade has already
passed. Now the remand means another round of litigation. There would be
further delay in getting the compensation. After all money is what money buys.
What the claimants could have bought with the compensation in 1977 cannot do in
1988. Perhaps, not even one half of it. It is a common experience that the
purchasing power of rupee is dwindling. With rising inflation, the delayed
payment may lose all charms and utility of the compensation. In some cases, the
delay may be detrimental to the interests of claimants. The Indian
agriculturists generally have no avocation. They totally depend upon land. If
uprooted, they will find themselves nowhere. They are left high and dry. They
have no savings to draw.
They
have nothing to fall back upon. They know no other work. They may even face
starvation unless rehabilitated. In all such cases, it is of utmost importance
that the award should be made without delay. The enhanced compensation must be
determined without loss of time. The appellate power of remand, at any rate
ought not to be exercised lightly. It shall not be resorted to unless the award
is wholly unintelligible. It shall not be exercised unless there is total lack
of evidence. If remand is imperative, and if the claim for enhanced
compensation is tenable, it would be proper for the appellate court to do
modest best to mitigate hardships. The appellate court may direct some interim
payment to claimants subject to adjustment in the eventual award.”
48.
It cannot be gainsaid that the appellants herein have been deprived of their
legitimate dues for almost 22 years ago. It can also not be controverted that
money is what money buys. The value of money is based on the idea that money
can be invested to earn a return, and that the purchasing power of money
decreases over time due to inflation. What the appellants herein could have
bought with the compensation in 2003 cannot do in 2025. It is, therefore, of
utmost importance that the determination of the award and disbursal of
compensation in case of acquisition of land should be made with promptitude.
49.
We find that in the present case, the appellants were required to knock at the
doors of the courts on number of occasions during the period of last twenty-two
years. The appellants have been deprived of their property without paying any
compensation for the same in the said period of last twenty-two years. As already
discussed hereinabove, the appellants had purchased the plots in question for
construction of residential houses. Not only have they not been able to
construct, but they have also not been even paid any compensation for the same.
As discussed hereinabove, though Right to Property is no more a fundamental
right, in view of the provisions of Article 300-A of the Constitution
of India, it is a constitutional right. A person cannot be deprived of his
property without him being paid adequate compensation in accordance with law
for the same.
50.
In the present case, it can clearly be seen that there is no delay which can be
attributed to the appellants in not getting compensation, but it was on account
of the lethargic attitude of the officers of the State/KIADB that the
appellants were deprived of compensation.
51.
Only after the notices were issued in the contempt proceedings, the
compensation was determined by the SLAO on 22nd April 2019 taking guideline
values prevailing in the year 2011 for determining the market value of the
acquired land.
52.
No doubt that as already observed by us hereinabove, we do not find any error
in the approach adopted by the learned Single Judge of the High Court in
holding that the SLAO could not have shifted the date and it could have been
done only by this Court in exercise of powers under Article 32/142 of the
Constitution of India or by the High Court under Article 226 of the
Constitution of India. However, the learned Single Judge of the High Court instead
of relegating the appellants to again go through the rigors of determination by
SLAO, ought to have exercised powers under Article 226 of the
Constitution to do complete justice. Even the Division Bench of the High Court
on a hyper technical ground has non-suited the appellants.
53.
In that view of the matter, we find that it is a fit case wherein this Court in
exercise of its powers under Article 142 of the Constitution should
direct shifting of the date for determination of the market value of the
land in question of the appellants.
54.
If the compensation to be awarded at the market value as of the year 2003 is
permitted, it would amount to permitting a travesty of justice and making the
constitutional provisions under Article 300-A a mockery.
55.
Since the State/KIADB was in deep slumber from 2003 to 2019 and acted for the
first time only after the notices were issued in contempt proceedings, we find
that though SLAO had no power to shift the date for determination of market
value, he had rightly done so. The learned Single Judge of the High Court also
does not say that the determination of compensation to be awarded by shifting
of the date by the SLAO to that of 2011 was unjust but only sets aside the
award on the ground that SLAO had no jurisdiction to do so.
56.
There is another reason for doing so. If on account of the inordinate delay in
paying the compensation and thereby depriving the constitutional right to the
appellants under Article 300-A, the land acquisition proceedings are
quashed, the only recourse available to the State/KIADB in order to save the
project will be to now issue a fresh acquisition notification by invoking
the provisions as applicable under the 2013 LA Act which would entail
huge expenditure to the public exchequer.
57.
We, therefore, in exercise of power of this Court under Article
142 of the Constitution of India, find it appropriate in the interest of
justice that the SLAO be directed to determine the compensation to be awarded
to the appellants herein on the basis of the market value prevailing as on 22nd
April 2019. The appellants shall also be entitled to all the statutory benefits
as are available to them under the 1894 LA Act. This shall be without
prejudice to the rights/contentions of either party, in case they make a
reference before an appellate authority, if they are so aggrieved by the fresh
determination of compensation by the SLAO. We further clarify that, any other
award which may have been passed pursuant to the directions of the learned
Single Judge of the High Court shall stand nullified by this judgment.
58.
Respondent Nos.6 and 7 contend that they cannot be imposed with a liability for
this huge additional expenditure. It is their contention that the delay in
determination of compensation and payment of the same is not attributable
to them but is on account of inaction on the part of the State and KIADB.
We clarify that we are not observing anything about the inter se dispute
between the State and KIADB on the one hand and Respondent Nos.6 and 7 on the
other hand, inasmuch as the same shall be governed by the FWA and/or any other
agreement between them. We only say that Respondent Nos.6 and 7, will be at
liberty to take recourse to such remedies as are available to them in law for
redressal of their inter se dispute.
59.
In the result, the appeal is disposed of in the following terms:
(i) The judgment and order passed
by the Division Bench of the High Court dated 22nd November 2022 in Writ Appeal
No. 678 of 2022 (LA-KIADB) is quashed and set aside;
(ii) The writ petition filed by
the appellants herein before the High Court being W.P. No. 1627 of 2021 is
allowed;
(iii) The SLAO shall pass a fresh
award taking the market value prevailing as on 22nd April 2019 within a period
of two months from today after hearing the parties;
(iv) The appellants herein shall be entitled
to all statutory benefits as are available to them in law;
(v) The rights of parties to
challenge the award in reference, if they are aggrieved by it, shall remain
open; and
(vi) As we have not expressed our
opinion on the claims, if any, of Respondent Nos.6 and 7 against the
State/KIADB qua the delay in passing the award by the SLAO, Respondent Nos. 6
and 7 are at liberty to take such steps as are permissible in law in case they
are aggrieved by the award to be passed by the SLAO.
60.
Pending application, if any, shall stand disposed of.
------