2025 INSC 2
SUPREME COURT OF INDIA
(HON’BLE B.R. GAVAI, J. AND
HON’BLE K.V. VISWANATHAN, JJ.)
MUNICIPAL CORPORATION OF DELHI
Petitioner
VERSUS
GAGAN NARANG
Respondent
Civil
Appeal Nos. 7463-7464 OF 2023-Decided on 02-01-2025
Civil, Electricity
Electricity
Regulatory Commission Jurisdiction not limited to distribution licensees and
generating companies
(A) Electricity Act, 2003 –
Section 63, 86(1)(b), 174,175 - Solid Waste Management Rules, 2016 - Rule
15(v)(b) - National Tariff Policy 2016 - Rule 6.4(1)(ii) and (2) - Jurisdiction
of Electricity Regulatory Commission – Determination of Tariff - Waste to Energy Projects -
Role of Appellant Municipal Corporation Delhi (MCD) - Whether the MCD has the
authority to make an application for adoption of tariff under Section 63 of the
Electricity Act, and whether the Delhi Electricity Regulatory Commission(DER
has jurisdiction to entertain and adjudicate upon the petition filed by the
MCD. The crux of the appeal centered around the jurisdiction of the DERC to act
on applications under Section 63 of the Act by local authorities such as the
MCD.
The
Supreme court determined that the DERC had authority under Section 86(1)(b) to
regulate electricity purchase processes and hence could evaluate applications
for tariff adoption, establishing that the provisions of the Act are
supplementary to the existing frameworks under the SWM Rules and National
Tariff Policy. The ruling emphasized the importance of allowing local
authorities to fulfill their statutory obligations toward municipal waste
disposal while balancing public interest considerations.
The
court highlighted the Mandate of the Municipal Corporation of Delhi (MCD) under
the Solid Waste Management Rules, 2016, which obligates it to facilitate the
construction, operation, and maintenance of solid waste processing facilities.
This obligation was assessed in the context of the Waste to Energy (WTE)
project, clarifying that the MCD's actions in issuing requests for proposals
and overseeing the bidding process were in line with its statutory duties, thus
justifying its role in seeking tariff adoption from the DERC under Section 63
of the Electricity Act, 2003.
(Para
56, 58)
(B) Electricity Act, 2003 -
Section 63 – Jurisdiction of Electricity Regulatory Commission – Determination
of Tariff - Inclusion
of Local Authorities - The Supreme Court held that the interpretation of
Section 63 of the Electricity Act, 2003 by the APTEL—restricting applications
for tariff adoption solely to distribution licensees and generating
companies—was overly restrictive. The Court determined that such an
interpretation failed to recognize the broader legislative intent, which allows
local authorities to invoke these provisions as part of their obligations under
other statutory frameworks, thereby confirming that the Appropriate Commission
has the authority to assess tariff applications arising from local government
initiatives, including those related to WTE projects.
(Para
45)
JUDGMENT
B.R. Gavai, J. :- The present appeals filed under
Section 125 of the Electricity Act, 2003[‘The
Act’ hereinafter] arise out of the Impugned common final judgment and
order of the Appellate Tribunal for Electricity at New Delhi[‘APTEL’ hereinafter] dated 31st August
2023 passed in DFR No. 245 of 2023 and DFR No. 247 of 2023 which were both
filed by the Respondent No. 1 herein- Mr. Gagan Narang. The APTEL disposed
of the appeals and set aside the orders of the Delhi Electricity Regulatory
Commission[‘DERC’ hereinafter]
dated 6th and 7th March 2023. Vide the order dated 6th March 2023 the DERC had
dismissed the petition filed by Waste to Energy Research & Technology
Council[‘WTERT’ hereinafter]
challenging the authority of the Appellant herein - Municipal Corporation of
Delhi [‘Appellant-MCD’ hereinafter],
to issue the tariff- based bid and Request for Proposal [‘RfP’ hereinafter] for setting up the Waste to Energy[ ‘WTE’ hereinafter] project
at Narela Bawana, Delhi. Vide order of 7th March 2023, the DERC had approved
the bid tariff of Rs. 7.38/KWh for the project and had directed the
Distribution Licensee to negotiate the terms of the Power Purchase Agreement[‘PPA’ hereinafter] with the
Appellant-MCD.
2.
Shorn of details, the facts leading to the present appeals are:
2.1
The Appellant-MCD organized a meeting with the Distribution Licensees in Delhi
and other stakeholders on 14 th May 2022. It was agreed that a tariff-based
bidding model may be adopted and the details about the same, including the
volume of waste, total power generation, and other considerations for the
proposed project were decided. It was further decided that the sale of power be
distributed amongst the Distribution Licensees as per their ‘Renewable Purchase
Obligation’. The Appellant was authorized to conduct the bidding process as per
the regulations and requirements of Section 63 of the Act for the proposed WTE
project. The same was put in writing and was detailed in the Minutes of Meeting
dated 30th May 2022.
2.2
The Appellant-MCD, issued the Notice Inviting Tender[‘NIT’ hereinafter] and the RfP dated 15th July 2022 whereby
the tariff-based bids for procurement of power under WTE project for Solid WTE
Processing Facility with a minimum 28 MW capacity in Narela Bawana, New Delhi,
for 3000 (+/- 20%) TPD of MSW[‘Project’
hereinafter] were invited. The documents for the same were sent to the DERC
for its consideration.
2.3
The DERC, vide letter dated 24th August 2022 directed the Appellant-MCD to file
a petition for approval of PPA, RfP, etc. The letter also contained the details
of the petitions filed by South Delhi Municipal Corporation and the East Delhi
Waste Processing Co. Ltd. seeking similar approvals, which were granted by
the DERC through separate orders. An evaluation committee was also constituted
for the evaluation of bids and other related issues. The Appellant-MCD issued a
notice that the bidding process dated 15th July 2022 were closed and a new NIT
was issued on 21st October 2022 with identical terms as the earlier NIT.
2.4
The WTERT filed a Petition No. 65 of 2022 before the DERC inter alia
challenging the authority of the Appellant-MCD for issuing the tariff-based bid
and the RfP in setting up the Project.
During
the pendency of this petition, the bidding process was undertaken, and on 14th
November 2022, bids were received from M/s JITF Urban Infrastructure Ltd. and
M/s JBM Renewables Pvt. Ltd. A meeting of the Evaluation committee was held,
and the documents submitted by the bidders keeping in mind the requirement of
the RfP document were discussed, and on recommendation of the committee, the
bids of both the bidders were declared to be technically qualified and their
bids were allowed to be opened. The Regional Centre for Urban
& Environmental Studies[‘RCUES’
hereinafter] calculated the levelized tariff based on the RfP and the same
was communicated and calculated as:
|
Name
of the Bidder |
Levelized
Tariff (Rs/KWh) |
|
M/s
JITF Urban Infrastructure Limited |
7.380
|
|
M/s
JBM Renewable Pvt. Limited |
9.909
|
2.5
The Financial Bids were evaluated by the Evaluation Committee and its
recommendation report dated 26th November 2022 was issued. It was stated in the
report that in accordance with the terms of the RfP, the “Lowest Bidder” for a
project was to be the qualified bidder and the lowest evaluated levelized
tariff shall be the selected bidder for the Project. M/s JITF Urban
Infrastructure Limited was selected to be the lowest bidder with a levelized
tariff bid of Rs. 7.380/KWh. It was further mentioned that a meeting of the
Evaluation Committee was held on 6th October 2022 for the consideration of the
Financial Model for price bid evaluation prepared by RCUES. The representative
of RCUES presented the financial model and after deliberation, the committee
reached a consensus on the key assumptions taken and had arrived at a
levelized tariff of Rs. 6.73/KWh. Since, there existed a difference between the
tariff according to the financial model and the tariff by the lowest bidder, a
justification/calculation for arriving at the quoted bid was requested from M/s
JITF Urban Infrastructure Limited, and the same was considered by the
committee. It was further mentioned, that after detailed deliberations, the
committee was of the opinion that the bids had been received through a
competitive bidding process and the lowest bid of Rs.7.380/KWh was arrived at,
through a competitive and transparent bidding process. It was further mentioned
that the Appellant-MCD herein has no benefit or loss accruing out of this as
the power is to be procured by the Distribution Companies in accordance with
the approval of tariff by DERC. The report was then forwarded to the DERC as
the final approval was to be given by it.
2.6
Pursuant to the same, the Appellant-MCD filed a Petition No. 72 of 2022 before
the DERC for the approval of the bidding process of the Project.
2.7
The DERC, vide order dated 6th March 2023, dismissed the Petition No. 65 filed
by WTERT and inter alia held that the Appellant-MCD is mandated under the
Solid Waste Management Rules, 2016[‘SWM
Rule 2016’ hereinafter] to construct, operate, and maintain the solid waste
processing facilities. Vide order dated 7th March 2023, the DERC in Petition
No. 72 filed by the Appellant-MCD herein, approved the bid tariff of Rs.
7.38/KWh for the project and directed the Distribution Licensee to negotiate
terms of the PPA with the Appellant-MCD and place a signed copy of the PPA
before the DERC within three months.
2.8
Aggrieved, two separate appeals were filed by the Respondent No. 1 herein
bearing DFR Nos. 245 of 2023 and 247 of 2023 against the orders dated 7th March
2023 and 6th March 2023 respectively.
2.9
The APTEL, vide the Impugned common final judgment and order dated 31st August
2023 disposed of the appeals and set aside both the orders dated 6th and 7th
March 2023 passed by the DERC on the ground that the DERC lacked jurisdiction
to entertain and adjudicate upon a petition filed by the Appellant-MCD herein.
2.10
Aggrieved, the present appeals are filed under Section 125 of the
Electricity Act, 2003.
3.
We have heard Mr. Ramji Srinivasan, learned Senior Counsel appearing for the
Appellant and Mr. Basava Prabhu Patil, learned Senior Counsel appearing for the
Respondent No.1, Mr. Krishna M. Singh, Ms. Ishita Jain, Mr. Buddy Ranganathan,
Mr. Suresh Chandra Tripathi, learned counsel appearing for Respondent Nos. 2,
3, 4 & 5, and 9 respectively and Mr. Pukhrambam Ramesh Kumar, learned
counsel for the applicant.
4.
Mr. Ramji Srinivasan, learned Senior Counsel appearing for the Appellant
submits that the APTEL has grossly erred in restricting the applicability
of Sections 63 and 86(1)(b) of the Act only to the
distribution licensee[‘Discoms’
hereinafter] or generating company insofar as the filing of application for
adoption of tariff is concerned. He submits that the provisions of Section
86(1)(b) of the Act would reveal that a wide power is bestowed upon the
State Commission to regulate electricity purchase and procurement process of
Discoms including the price at which electricity shall be procured from the
generating companies or licensees or from other sources.
5.
Learned Senior Counsel further submits that the Appellant-MCD, which is a
statutory body under the Delhi Municipal Corporation Act, has been put
under statutory obligation under Rule 15(v)(b) of the SWM Rules 2016 to proceed
for setting up of the WTE projects. It is submitted that this statutory duty
has also been recognized by this Court in the case of Pune Municipal
Corporation v. Sus Road Baner Vikas Manch and others[(2024) 9 SCC 1].
6.
The learned Senior Counsel further submits that Rule 6.4(1)(ii) and (2) of the
National Tariff Policy 2016 mandates Discoms to procure 100% of the power
produced from all WTE plants either through Section 62 (normative
tariff process) or through Section 63 (competitive based mechanism).
7.
It is further submitted that Section 175 of the Act itself provides
that the provisions of the Act are in addition to and not in derogation of any
other law for the time being in force. It is, therefore, submitted that the
mandate for setting up the WTE project by MCD has to be read in consonance with
the provisions of the Environment (Protection) Act, 1986 and the
Rules framed there under.
8.
It is submitted that for WTE projects, no guidelines have been framed by the
Central Government for conducting the bidding and accordingly the DERC has
exercised its powers to regulate under Section 86(1)(b) of the Act to
approve the bidding process and adopt the tariff. It is submitted that this is
in tune with the judgment of this Court in the case of Energy Watchdog v.
Central Electricity Regulatory Commission and others[(2017) 14 SCC 80], wherein this Court has held that in a situation
when there are no guidelines, then the general regulatory powers
under Section 79(1)(b) can be exercised by the Commission. It is,
therefore, submitted that by the same analogy the State Commission can exercise
such powers in view of Section 86(1)(b) of the Act.
9.
The learned Senior Counsel submits that the APTEL has failed to take into
consideration the larger issue of public interest. It is submitted that WTE
project was necessary for processing the unprocessed municipal solid waste
which is increasing day by day.
10.
It is further submitted that the DERC vide its order dated 6th March 2023 had
held that the Appellant-MCD under Rule 15(v) of the SWM Rules 2016 was
performing its statutory functions to conduct the bidding process for the
Project and that there is no bar in the National Tariff Policy that WTE project
cannot be set up under Section 63 of the Act. It is submitted that on
an earlier occasion also the DERC has approved the bidding process with regard
to Tehkhand WTE at Okhla which is under operation and supplying electricity to
all Delhi Discoms.
11.
Mr. Basava Prabhu Patil, learned Senior Counsel appearing for the Respondent
No.1, on the contrary, submits that the APTEL has rightly held that the
Appellant-MCD was not entitled to make an application for adoption of tariff
under Section 63 of the Act. It is submitted that the APTEL rightly
held that it is only the Discoms or generating companies who are entitled to
invoke the provisions of Section 63 of the Act. The learned Senior
Counsel submits that in view of Rule 6.4(2) of the National Tariff Policy,
2016, it is exclusively for the Ministry of Power to provide a mechanism for
adoption of tariff for WTE projects. It is, therefore, submitted that the DERC
has no jurisdiction to entertain the application filed by the present
Appellant-MCD. He, therefore, prays for the dismissal of the present
appeals.
12.
The limited question that falls for consideration in the present appeals is
that, whether the application under Section 63 of the Act could have
been made by the present Appellant- MCD which is a “local authority” within the
meaning of Section 2(41) of the Act.
13.
For appreciating the rival controversy, it will be necessary to consider the
nature of the Project which the Appellant-MCD was implementing. For the said
purpose, it will be relevant to refer to clauses (q) and (v) of Rule 15 of the
SWM Rules 2016, which read thus:
“15. Duties and responsibilities
of local authorities and village panchayats of census towns and urban
agglomerations.—The local authorities and Panchayats shall— ***
(q) transport segregated
bio-degradable waste to the processing facilities like compost plant,
biomethanation plant or any such facility. Preference shall be given for on
site processing of such waste;
***
(v) facilitate construction,
operation and maintenance of solid waste processing facilities and associated
infrastructure on their own or with private sector participation or through any
agency for optimum utilisation or various components of solid waste adopting
suitable technology including the following technologies and adhering to
the guidelines issued by the Ministry of Urban Development from time to time
and standards prescribed by the Central Pollution Control Board. Preference
shall be given to decentralised processing to minimise transportation cost and
environmental impacts such as—
(a) bio-methanation, microbial
composting, vermi-composting, anaerobic digestion or any other appropriate
processing for bio-stabilisation of biodegradable waste;
(b) waste to energy processes
including refused derived fuel for combustible fraction of waste or supply as
feedstock to solid waste based power plants or cement kilns;”
14.
It could thus be seen that the SWM Rules 2016 require that, while making
provisions for solid waste disposal, the authorities shall give a preference to
decentralized processing to minimize transportation cost and environmental
impacts such as, waste to energy processes including refused derived fuel for
combustible fraction of waste or supply as feedstock to solid waste based power
plants or cement kilns.
15.
It is further to be noted that the “Tariff Policy” notified by the Ministry of
Power on 28th January 2016 is in compliance with the mandate of Section
3 of the Act. It could further be seen that under the said “Tariff
Policy”, a provision has been made for renewable sources of energy generation
including Co- generation from renewable energy sources. It will be relevant to
refer to Rule 6.4 of the said “Tariff Policy”, which reads thus:
“6.4 Renewable sources of energy
generation including Co-generation from renewable energy sources:
(1) Pursuant to provisions
of section 86(1)(e) of the Act, the Appropriate Commission shall fix
a minimum percentage of the total consumption of electricity in the area of a
distribution licensee for purchase of energy from renewable energy sources,
taking into account availability of such resources and its impact on retail
tariffs. Cost of purchase of renewable energy shall be taken into account while
determining tariff by SERCs. Long term growth trajectory of Renewable Purchase
Obligations (RPOs) will be prescribed by the Ministry of Power in consultation
with MNRE.
Provided that cogeneration from
sources other than renewable sources shall not be excluded from the
applicability of RPOs.
(i) Within the percentage so made
applicable, to start with, the SERCs shall also reserve a minimum percentage
for purchase of solar energy from the date of notification of this policy which
shall be such that it reaches 8% of total consumption of energy, excluding
Hydro Power, by March 2022 or as notified by the Central Government from time
to time.
(ii) Distribution Licensee(s)
shall compulsorily procure 100% power produced from all the Waste-to-Energy
plants in the State, in the ratio of their procurement of power from all
sources including their own, at the tariff determined by the Appropriate
Commission under Section 62 of the Act.
(iii) It is desirable that
purchase of energy from renewable sources of energy takes place more or less in
the same proportion in different States. To achieve this objective in the
current scenario of large availability of such resources only in certain parts
of the country, an appropriate mechanism such as Renewable Energy Certificate
(REC) would need to be promoted. Through such a mechanism, the renewable energy
based generation companies can sell the electricity to local distribution
licensee at the rates for conventional power and can recover the balance cost
by selling certificates to other distribution companies and obligated entities
enabling the latter to meet their renewable power purchase obligations.
The REC mechanism
should also have a solar specific REC.
(iv) Appropriate Commission may
also provide for a suitable regulatory framework for encouraging such other
emerging renewable energy technologies by prescribing separate technology based
REC multiplier (i.e. granting higher or lower number of RECs to such emerging
technologies for the same level of generation).
Similarly, considering the change
in prices of renewable energy technologies with passage of time, the
Appropriate Commission may prescribe vintage based REC multiplier (i.e.
granting higher or lower number of RECs for the same level of generation based
on year of commissioning of plant).
(2) States shall endeavor to
procure power from renewable energy sources through competitive bidding to keep
the tariff low, except from the waste to energy plants. Procurement of power by
Distribution Licensee from renewable energy sources from projects above the
notified capacity, shall be done through competitive bidding process, from the
date to be notified by the Central Government.
16.
It can thus be seen that clause (1) of Rule 6.4 provides that the Appropriate
Commission shall fix a minimum percentage of the total consumption of
electricity in the area of a distribution licensee for purchase of energy
from renewable energy sources, taking into account availability of such
resources and its impact on retail tariffs. It further provides that the cost
of purchase of renewable energy shall be taken into account while determining
tariff by SERCs and that the long-term growth trajectory of Renewable Purchase
Obligations (RPOs) will be prescribed by the Ministry of Power in consultation
with Ministry of New and Renewable Energy (MNRE).
17.
Certain exceptions have been made to the applicability of the said clause. One
of the exceptions is that, the Distribution Licensee(s) shall compulsorily
procure 100% of the power produced from all the Waste-to-Energy plants in the
State, in the ratio of their procurement of power from all sources including
their own, at the tariff determined by the Appropriate Commission
under Section 62 of the Act.
18.
It is further to be noted that the following provision has been made in SWM
Rules 2016:
“9. Duties of the Ministry of
Power.- The Ministry of Power through appropriate mechanisms shall,-
(a) decide tariff or charges for
the power generated from the waste to energy plants
based on solid waste.
(b) compulsory purchase power
generated from such waste to energy plants by distribution company.”
19.
It could thus be seen that under the SWM Rules 2016, a duty is cast upon the
Ministry of Power to decide tariff or charges for the power generated from the
waste to energy plants based on solid waste and compulsory purchase of power
generated from such waste to energy plants by distribution company.
20.
Thus, it is to be noted that the Project, for which bids were invited by the
Appellant-MCD, was proposed to be set up by the Appellant-MCD in pursuance of
its statutory obligations under the SWM Rule 2016.
21.
A perusal of the record would reveal that the Appellant- MCD issued NIT for the
competitive tariff bidding process for setting up of the Project for
procurement of power by Discoms in the NCT of Delhi as part of Discom’s Renewal
Purchase Obligation[“RPO” for short].
The said project was on Design, Build, Finance, and Operate basis and was to be
transferred back to the Appellant-MCD after 25 years.
22.
It is further to be noted that after the bid was conducted in consonance with
the decision taken in the meeting dated 14th May 2022, wherein the Discoms
authorized the Appellant- MCD to proceed with the same, on 3rd August 2022, the
bidding documents were sent to the DERC for its consideration. Based on the
same, the DERC vide letter dated 24th August 2022 directed the Appellant-MCD to
file a Petition for adoption of tariff. The DERC, further informed the Appellant-MCD
about similar petitions filed by East Delhi Processing Limited seeking similar
approvals.
23.
After M/s JITF Urban Infrastructure Ltd. emerged as a L- 1 bidder at the
levelized tariff of Rs.7.380/KWh, the Appellant- MCD filed a Petition No. 72 of
2022 before the DERC for adoption of tariff and approving the draft PPA. The
DERC vide its order dated 7th March 2022 adopted the tariff of Rs.7.380/KWh and
directed the Discoms and the successful bidder to renegotiate the terms of the
PPA.
24.
Insofar as the petition of the WTERT is concerned, the DERC specifically
rejected the contention of the WTERT to the effect that since the Appellant-MCD
was not an authorized distribution licensee, it cannot float the impugned
tender. It was further sought to be argued that the Bidding procurement
under Section 63 of the Act was impermissible in case of ‘waste to
energy’ power.
25.
The DERC relying on the provisions of Rule 15 of the SWM Rules 2016
specifically rejected the said contention and held that the Appellant-MCD was
performing its statutory obligations.
26.
While allowing the applications filed by the Respondent No. 1, the APTEL
interpreted Section 63 of the Act and held that since the
Appellant-MCD was neither a distribution licensee nor a generating company, it
had no jurisdiction to file an application under Section 63 of the
Act for adoption of tariff.
27.
For appreciating the correctness of the findings of the APTEL, it will be
apposite to refer to Section 63 of the Act, which reads thus:
“63. Determination of tariff by
bidding process.- Notwithstanding anything contained in section 62, the
Appropriate Commission shall adopt the tariff if such tariff has been
determined through transparent process of bidding in accordance with the
guidelines issued by the Central Government.”
28.
It could thus be seen that under Section 63 of the Act, the
Appropriate Commission is entitled to adopt the tariff if such tariff has
been determined through a transparent process of bidding in accordance with the
guidelines issued by the Central Government.
29.
It could be seen that a plain reading of Section 63 of the Act would
reveal that it does not restrict invoking of the provisions of Section
63 only to Discoms or generating companies.
30.
It is a settled principle of law that the first and foremost principle of
interpretation is that of literal interpretation. When the statute read in a
literal manner is capable of giving meaning to the provision that the
legislation intended to and does not lead to any absurdity, it is not
permissible by judicial interpretation to add, alter, or delete any words to
such a statute. Reliance in this respect could be placed on the judgment of
this Court in the case of Punjab State Power Corporation Limited and
another vs. Emta Coal Limited[(2022) 2
SCC 1] wherein this Court has observed thus:
“23. The principle of giving a
plain and literal meaning to the words in a statute is well-recognised for
ages. Though there are a number of judgments, we may gainfully refer to the
judgment of this Court delivered by Das, J. as early as
1955 in Jugalkishore Saraf v. Raw Cotton Co.Ltd. [Jugalkishore Saraf
v. Raw Cotton Co. Ltd., (1955) 1 SCR 1369 : AIR 1955 SC 376] : (AIR p. 381,
para 6)
“6. … The cardinal rule of
construction of statutes is to read the statute literally, that is by giving to
the words used by the legislature their ordinary, natural and grammatical
meaning. If, however, such a reading leads to absurdity and the words are
susceptible of another meaning the Court may adopt the same. But if no such
alternative construction is possible, the Court must adopt the ordinary rule of
literal interpretation.”
24. Though there are various
authorities on the said subject, we do not wish to burden the present judgment
by reproducing those. In our considered view, if the words used in Section
11 of the said Act are construed in plain and literal term, they do not
lead to an absurdity and as such, the rule of plain and literal interpretation
will have to be followed. We find that in case the interpretation as sought to
be placed by Shri Rohatgi is to be accepted, it will do complete violence to
the language of Section 11 of the said Act. If it is held that
under Section 11 of the said Act, a prior contractor is entitled to
continue if his performance is found to be satisfactory and if there is nothing
against him, then it will be providing something in Section 11 of the
said Act which the statute has not provided for. It will also lead to making
the words “may elect, to adopt and continue” redundant and otiose.
25. It is a settled principle of
law that when, upon a plain and literal interpretation of the words used in a
statute, the legislative intent could be gathered, it is not permissible to add
words to the statute. Equally, such an interpretation which would make some
terms used in a statute otiose or meaningless, has to be avoided. We therefore
find that if an interpretation as sought to be placed by EMTA is to be
accepted, the same would be wholly contrary to the principle of literal
interpretation. There are number of authorities in support of the said
proposition. However, we refrain from referring to them in view of the
following observations made by this Court in a recent judgment in Ajit
Mohan v. Delhi Legislative Assembly [Ajit Mohan v. Delhi Legislative
Assembly, (2022) 3 SCC 529 :2021 SCC OnLine SC 456] : (SCC para 240)
“240. … In our view if the
proposition of law is not doubted by the Court, it does not need a precedent
unless asked for. If a question is raised about a legal proposition, the
judgment must be relatable to that proposition — and not multiple judgments.”
As
such, the contention in that regard is found to be without merit.”
31.
Upon a plain reading of Section 63 of the Act, it would reveal
that the power of the Appropriate Commission thereunder is, notwithstanding
anything contained in Section62.
32.
It can thus be seen that the intention of the legislature is to empower the
Appropriate Commission to adopt the tariff if such tariff has been determined
through a transparent process of bidding in accordance with the guidelines
issued by the Central Government.
33.
The legislative purpose appears to be that when the power is being produced
through a process of bidding it has to be done in a transparent manner. Another
requirement is that the same must be done in accordance with the guidelines
issued by the Central Government.
34.
This Court in the case of Energy Watchdog (supra) has held that when
there are no guidelines, then the Central Commission can exercise power
under Section 79(1)(b) of the Act. The provisions of Section
86(1)(b) of the Act are analogous with Section 79(1)(b) of the
said Act.
35.
A plain reading of Section 63 of the Act would not show that the
legislature intended to restrict the invocation of the jurisdiction of the
State Commission only by the Discoms or generating companies. In our view,
the interpretation as placed by the APTEL is adding words in the provisions
of Section 63 of the Act which the legislature did not intend to.
36.
As already stated herein above, when a provision in the statute upon its plain
reading is capable of giving a meaning to it as intended by the legislature,
then it will not be permissible for the courts to add, alter, or delete the
words to the said provision. In any case, upon a plain reading of the
provisions of Section 63 of the Act, the meaning which we gather does
not result in any absurdity. In such a situation, addition of words in the
statute by judicial interpretation is wholly impermissible.
37.
Apart from that, we are of the view that APTEL could not have read the
provisions of Section 63 of the Act in isolation. The provisions
of Section 63 will have to be read in harmony with the provisions
of Section 86(1)(b) of the Act, which reads thus:
“86. Functions of the State
Commission.-(1) The State Commission shall discharge the following functions,
namely:-
(a) ……………………………………………
(b) regulate electricity purchase
and procurement process of distribution licensees including the price at
which electricity shall be procured from the generating companies or
licensees or from other sources through agreements for purchase of power for
distribution and supply within the State;”
38.
A perusal of the provision of Section 86(1)(b) of the Act would
reveal that a duty is cast upon the State Commission to regulate electricity
purchase and procurement process of distribution licensees including the price
at which electricity shall be procured from the generating companies or
licensees or from other sources through agreements for purchase of power for
distribution and supply within the State.
39.
It could thus be seen that the duty cast upon the State Commission is to
regulate:
(i) the electricity purchase and
procurement process of distribution licensees;
(ii) the price at which
electricity shall be procured from the generating companies or licensees, or;
(iii) from other sources through
agreements for purchase of power for distribution and supply within the State.
40.
The legislative intent behind Section 86(1)(b) of the Act is to
empower the State Commission to regulate all matters regarding the
electricity purchase and procurement processes.
41.
As held by this Court in the case of Jaipur Vidyut Vitran Nigam Limited
and others v. MB Power (Madhya Pradesh) Limited and others[(2024) 8 SCC 513], the State Commission
is not a mere post office, but a duty is cast upon it to balance the interests
of consumers on one hand and that of generators or Discoms on the other hand.
If the provisions of Section 63 of the Act are read in harmony with
the provisions of Section 86(1)(b) of the Act, the legislative intent
that could be gathered is that the State Commission while exercising its powers
under Section 63 of the Act shall adopt the tariff when it has been
determined in the bidding process. However, while adopting the same it will
have to be satisfied that the same is done in a transparent manner. It will
also have to be examined as to whether the interests of the generators/Discoms
on one hand are balanced with the interests of the consumers.
42.
In our view, reading the Section 63 of the Act in the manner in which
it has been interpreted by the APTEL, would impose unnecessary restrictions on
the powers and duties of the State Commission under Section 86(1)(b) of
the Act, which are of a very wide amplitude.
43. In
this respect, we may refer to the judgment of this Court in the case
of Sanjay Ramdas Patil v. Sanjay and others[(2021) 10 SCC 306] wherein this Court after referring to the
earlier judgments of this Court has observed thus:
“25. In Balasinor Nagrik Coop.
Bank Ltd. v. Babubhai Shankerlal Pandya [Balasinor Nagrik Coop. Bank Ltd. v.
Babubhai Shankerlal Pandya, (1987) 1 SCC 606] , this Court observed thus : (SCC
p. 608, para 4)
“4. … It is an elementary rule
that construction of a section is to be made of all parts together. It is not
permissible to omit any part of it. For, the principle that the statute must be
read as a whole is equally applicable to different parts of the same section.”
26. Again in Mohan Kumar
Singhania v. Union of India [Mohan Kumar Singhania v. Union of India, 1992 Supp
(1) SCC 594 : 1992 SCC (L&S) 455] , this Court observed thus : (SCC p. 624,
para
67) “67. We think, it is not
necessary to proliferate this judgment by citing all the judgments and
extracting the textual passages from the various textbooks on the principles of
Interpretation of Statutes. However, it will suffice to say that while
interpreting a statute the consideration of inconvenience and hardships should be
avoided and that when the language is clear and explicit and the words used are
plain and unambiguous, we are bound to construe them in their ordinary sense
with reference to other clauses of the Act or the Rules as the case may be, so
far as possible, to make a consistent enactment of the whole statute or series
of statutes/rules/regulations relating to the subject-matter.
Added to this, in construing a
statute, the Court has to ascertain the intention of the law-making authority
in the backdrop of the dominant purpose and the underlying intendment of the
said statute and that every statute is to be interpreted without any violence
to its language and applied as far as its explicit language admits consistent
with the established rule of interpretation.”
27. In Sultana Begum v.
Prem Chand Jain [Sultana Begum v. Prem Chand Jain, (1997) 1 SCC 373] ,
this Court observed thus : (SCC pp. 381-82, para 15) “15. On a conspectus of
the case-law indicated above, the following principles are clearly discernible:
(1) It is the duty of the courts
to avoid a head-on clash between two sections of the Act and to construe
the provisions which appear to be in conflict with each other in such a manner
as to harmonise them.
(2) The provisions of one section
of a statute cannot be used to defeat the other provisions unless the court, in
spite of its efforts, finds it impossible to effect reconciliation between
them.
(3) It has to be borne in mind by
all the courts all the time that when there are two conflicting provisions in
an Act, which cannot be reconciled with each other, they should be so
interpreted that, if possible, effect should be given to both. This is the
essence of the rule of “harmonious construction”.
(4) The courts have also to keep
in mind that an interpretation which reduces one of the provisions as a “dead
letter” or “useless lumber” is not harmonious construction.
(5) To
harmonise is not to destroy any statutory provision or to render it otiose.”
(emphasis
in original)
28. In Jagdish Singh v.
Lt. Governor [Jagdish Singh v. Lt. Governor, (1997) 4 SCC 435] , this Court
observed thus : (SCC p. 441, para 7)
“7. … It is a cardinal principle
of construction of a statute or the statutory rule that efforts should be
made in construing the different provisions, so that, each provision will have
its play and in the event of any conflict a harmonious construction should be
given. Further a statute or a rule made thereunder should be read as a whole
and one provision should be construed with reference to the other provision so
as to make the rule consistent and any construction which would bring any
inconsistency or repugnancy between one provision and the other should be
avoided. One rule cannot be used to defeat another rule in the same rules
unless it is impossible to effect harmonisation between them.
The well-known principle of
harmonious construction is that effect should be given to all the provisions,
and therefore, this Court has held in several cases that a construction that
reduces one of the provisions to a “dead letter” is not a harmonious
construction as one part is being destroyed and consequently court should avoid
such a construction.”
29. In CIT v. Hindustan
Bulk Carriers [CIT v. Hindustan Bulk Carriers, (2003) 3 SCC 57] , this
Court observed thus : (SCC pp. 73-74, paras 16-21)
“16. The courts will have to reject that
construction which will defeat the plain intention of the legislature even
though there may be some inexactitude in the language used. (See Salmon v.
Duncombe [Salm on v. Duncombe, (1886) LR 11 AC 627 (PC) : 55 LJPC 69 : 55 LT
446] , AC at. 634, Curtis v. Stovin [Curtis v. S tovin, (1889) LR 22 QBD 513
(CA) : 58 LJQB 174 : 60 LT 772] referred to in S. Teja Singh case
[CIT v. S. Teja Singh, AIR 1959 SC 352 : (1959) 35 ITR 408] .)
17. If the choice is between two
interpretations, the narrower of which would fail to achieve the manifest
purpose of the legislation, we should avoid a construction which would reduce
the legislation to futility, and should rather accept the bolder construction,
based on the view that Parliament would legislate only for the purpose of
bringing about an effective result. (See Nokes v. Doncaster Amalgamated
Collieries Ltd. [Nokes v. Doncaster Amalgamated Collieries Ltd., 1940 AC 1014 :
(1940) 3 All ER 549 (HL) : 109 LJKB 865 : 163 LT 343] referred to in Pye v.
Minister for Lands for New South Wales [Pye v. Minister for Lands for New South
Wales, (1954) 1 WLR 1410 : (1954) 3 All ER 514 (PC)] .) The principles
indicated in the said cases were reiterated by this Court in Mohan Kumar
Singhania v. Union of India [Mohan Kumar Singhania v. Union of India, 1992 Supp
(1) SCC 594 : 1992 SCC (L&S) 455] .
18. The statute must be read as a
whole and one provision of the Act should be construed with reference to other
provisions in the same Act so as to make a consistent enactment of the whole
statute.
19. The court must ascertain the
intention of the legislature by directing its attention not merely to the
clauses to be construed but to the entire statute; it must compare the clause
with other parts of the law and the setting in which the clause to be interpreted
occurs. (See R.S. Raghunath v. State of Karnataka [R.S. Raghunath v.
State of Karnataka, (1992) 1 SCC 335 : 1992 SCC (L&S) 286] .) Such a
construction has the merit of avoiding any inconsistency or repugnancy either
within a section or between two different sections or provisions of the same
statute. It is the duty of the court to avoid a head-on clash between two
sections of the same Act. (See Sultana Begum v. Prem Chand Jain [Sultana
Begum v. Prem Chand Jain, (1997) 1 SCC 373] .)
20. Whenever it is possible to do
so, it must be done to construe the provisions which appear to conflict so that
they harmonise. It should not be lightly assumed that Parliament had given with
one hand what it took away with the other.
21. The provisions of one section
of the statute cannot be used to defeat those of another unless it is
impossible to effect reconciliation between them.
Thus a construction that reduces
one of the provisions to a “useless lumber” or “dead letter” is not a
harmonised construction. To harmonise is not to destroy.”
30. It could thus be seen that it
is more than well settled that it is the duty of the Court to construe the
statute as a whole and that one provision of the Act has to be construed with
reference to other provisions so as to make a consistent enactment of the whole
statute. It is the duty of the Court to avoid a head-on clash between two
sections and construe the provisions which appear to be in conflict with each
other in such a manner so as to harmonise them. It is further equally settled
that while interpreting a particular statutory provision, it should not result
into making the other provision a “useless lumber” or a “dead letter”. While
construing the provisions, the Court will have to ascertain the intention of
the law- making authority in the backdrop of dominant purpose and the
underlying intendment of the statute.”
44.
We are, therefore, of the considered view that when the provisions
of Section 63 of the Act are read in harmony with the provisions
of Section 86(1)(b) of the Act, the powers of the State Commission
cannot be curtailed by interpreting that the same can be invoked only by the
Discoms or the generating companies.
45.
It will further be relevant to refer to the provisions of Section
174 and 175 of the Act, which read thus:
“174. Act to have overriding
effect.- Save as otherwise provided in section 173, the provisions of this
Act shall have effect notwithstanding anything inconsistent therewith contained
in any other law for the time being in force or in any instrument having effect
by virtue of any law other than this Act.
175. Provisions of this Act to be
in addition to and not in derogation of other laws.- The provisions of this Act
are in addition to and not in derogation of any other law for the time being in
force.”
46.
A perusal of Section 174 of the Act would reveal that, save as
otherwise provided in Section 173, the provisions of the Act shall have
effect notwithstanding anything inconsistent therewith contained in any other
law for the time being in force
or
in any instrument having effect by virtue of any law other than the Act.
47. Section
175 of the Act provides that the provisions of the said Act are in
addition to and not in derogation of any other law for the time being in force.
48.
In our view, there is no inconsistency between the provisions of Section
63 of the Act and Rule 15 of the SWM Rules 2016. The provisions of Rule 15
of the SWM Rules 2016, which are enacted under the Environment
(Protection) Act, 1986, mandate the appellant to undertake WTE project(s).
49.
It can thus be seen that insofar as the WTE projects are concerned, the
provisions under the Act will have to be read in addition to the provisions
under Rule 15 of the SWM Rules 2016 and not in derogation thereof.
50.
Apart from that, Rule 6.4 of the Tariff Policy, which is notified in compliance
with the mandate of Section 63 of the Act, the distribution licensees
are mandated to compulsorily procure 100% of the power produced from all the
WTE plants in the State in the ratio of their procurement of power from all
sources including their own. Not only that, the Appropriate Commission is also
required to provide suitable regulatory framework for encouraging such
other emerging renewable energy technologies.
51.
It will also be relevant to refer to the provisions of Section
86(1)(e) of the Act, which read thus:
“86. Functions of the State
Commission.-(1) The State Commission shall discharge the following functions,
namely:-
(a) ……………………………………………
(e) promote cogeneration and
generation of electricity from renewable sources of energy by providing
suitable measures for connectivity with the grid and sale of electricity from
such sources, a percentage of the total consumption of electricity in the area
of a distribution licensee;”
52.
It can thus be seen that the provisions of Section 86(1)(e) of the
Act read with Rule 6.4 of the Tariff Policy provide for promoting cogeneration
and generation of electricity from renewable sources of energy by providing
suitable measures for connectivity with the grid and sale of electricity from
such sources, a percentage of the total consumption of electricity in the area
of a distribution licensee.
53.
We are of the considered view that the APTEL has failed to take into
consideration all these aspects of the matters.
54.
In any case, the APTEL has grossly erred in treating the present Appellant-MCD
as a total stranger. The WTE project was on Design, Build, Finance and Operate
basis. The ownership of the said Project was always to be with the
Appellant-MCD and the operation of the facility is required to be transferred
back to the Appellant-MCD after 25 years. The reasoning given by the APTEL,
that if the application of the Appellant-MCD for adoption of tariff was held to
be tenable, then it would amount to permitting any stranger to apply
under Section 63 of the Act, is factually not correct. The APTEL
failed to take into consideration that the Appellant-MCD was establishing the
said Project in order to perform its statutory obligations. The plain reading
of Section 63 of the Act would reveal that the Appropriate Commission
has to adopt the tariff only after being satisfied that such a tariff has been
determined through a transparent process of bidding in accordance with the
guidelines issued by the Central Government.
55.
The DERC, after taking into consideration all the relevant factors, had granted
its approval to the tariff with certain conditions. The relevant factors which
were taken into consideration by the DERC while granting the approval were:
(i) the mandate of Rule 15 of the SWM Rules
2016;
(ii) the financial evaluation
report which was sent by the Bidding Evaluation Committee;
(iii) the certificate on the
conformity that the bidding process had been completed by following the
transparent process; and
(iv) that there was a mandate
under the NTP to the effect that the entire power generated by the WTE project
was to be procured by the Discoms.
However,
the same has been upset by the APTEL only on a hyper-technical ground.
56.
The APTEL also failed to take into consideration that the WTE project in
question was in the larger public interest thereby providing for disposal of
the huge quantity of waste generated in the city of Delhi.
57.
Since we are inclined to allow the appeals of the appellant on the aforesaid
grounds, we do not find it necessary to go into the contention of the appellant
with regard to locus of the Respondent No.1 in filing the appeals before the
APTEL.
58.
In the result, we pass the following order:
(i) the appeals are allowed;
(ii) the Impugned common final judgment and
order of the Appellate Tribunal for Electricity at New Delhi dated 31st August
2023 passed in DFR No. 245 of 2023 and DFR No. 247 of 2023 is quashed and set
aside;
(iii) the orders of the Delhi
Electricity Regulatory Commission dated 6th March 2023 in Petition No. 65 of
2022 and 7th March 2023 in Petition No. 72 of 2022 are affirmed.
59.
Pending application(s), if any, shall stand disposed of.
The
core issue in this judgment revolves around determining whether the Municipal
Corporation of Delhi (MCD) is entitled to make an application for adoption of
tariff under Section 63 of the Electricity Act, 2003, for a Waste to Energy
(WTE) project.
The
MCD claims that it has a statutory obligation under the Solid Waste Management
Rules, 2016, and Rule 15(v) of the SWM Rules 2016 to proceed with the setting
up of the WTE project. It also argues that Section 63 of the Electricity Act,
2003, allows for a tariff-based mechanism, and that the DERC has exercised its
regulatory powers under Section 86(1)(b) to approve the bidding process and
adopt the tariff.
However,
the Respondent, Mr. Gagan Narang, contests this claim, arguing that the APTEL
has rightly held that the MCD is not entitled to make an application for
adoption of tariff under Section 63 of the Act, as this provision is only
applicable to Discoms or generating companies.
The
key issue in dispute is whether the MCD, as a "local authority" under
Section 2(41) of the Act, can invoke the provisions of Section 63 of the Act.
If the MCD is deemed to be a "local authority", then it may be
entitled to make an application for adoption of tariff under Section 63 of the
Act.
The
judgment will ultimately turn on a determination of whether the MCD has the
authority to make an application for adoption of tariff under Section 63 of the
Act, and whether the DERC has jurisdiction to entertain and adjudicate upon the
petition filed by the MCD.
------