This civil appeal challenged a judgment of the Bombay High Court which had dismissed a writ petition filed by the appellant against a massive Goods and Services Tax (GST) demand notice on technical grounds of an alternate remedy. The Supreme Court reviewed the matter on merits, addressing the tax treatment of turnkey Engineering-Procurement-Construction (EPC) contracts for Solar Power Generating (SPG) systems executed between July 1, 2017, and December 31, 2018. The Supreme Court held that the mandatory imposition of a 70:30 value split (goods vs. services) and the invocation of extended limitation periods for periods prior to January 1, 2019, were completely arbitrary and unsustainable in law. Consequently, the Court allowed the appeal, set aside the adjudication orders, and reinforced that SPG systems affixed to civil foundations for operational stability remain movable property rather than works contracts.
- Background and Dispute: The appellant was engaged in setting up SPG systems across the country on a turnkey EPC basis. Tax authorities issued show-cause notices demanding CGST and SGST totaling over ₹53 crores for the period between July 1, 2017, and December 31, 2018, forcing the appellant to pay tax under a mandatory 70:30 valuation ratio (5% on 70% goods and 18% on 30% services).
- High Court’s Flawed Approach: The Bombay High Court dismissed the appellant’s writ petition in a cursory manner, relegating it to statutory appeals without examining arguable substantive points. The Supreme Court held this dismissal unjustified and proceeded to resolve the issue on merits.
- Tax Regime Prior to January 1, 2019: Under Notification No. 1/2017-Central Tax (Rate), renewable energy devices and SPG systems as a whole were subjected to a concessional flat rate of 5% (2.5% CGST + 2.5% SGST) to promote green energy.
- Optional Nature of the 70:30 Scheme: The 70:30 valuation ratio regime was introduced prospectively via Notification No. 24/2018, effective from January 1, 2019. A subsequent circular issued in October 2021 merely provided an option for assessees to adopt this ratio for past transactions voluntarily, but did not impose a compulsory mandate across the board. The revenue authorities erred in treating this option as a mandatory rule for pre-2019 periods.
- Movable vs. Immovable Property (Works Contract Test): Applying established jurisprudence (Bharti Airtel, Solid and Correct Engineering Works), the Court evaluated the nature of annexation and functionality. Because SPG systems can be easily detached and relocated without damaging the underlying civil foundation (which merely provides wobble-free stability), they do not constitute immovable property. Hence, composite EPC contracts for SPG systems do not qualify as “works contracts” under Section 2(119) of the CGST Act.
- Unjustified Invocation of Extended Limitation: The Court ruled that invoking extended limitation periods under Section 74 of the CGST Act alleging fraud or wilful misstatement was entirely unsustainable, as the dispute arose entirely out of a change in regulatory interpretation rather than any suppression by the taxpayer.
- Final Verdict: The Supreme Court allowed the appeal, set aside the impugned adjudication and summary orders, and invalidated the coercive tax demands.