Indian Judgements

Indian Judgements

Arbitration: Non signatory also Referered to arbitration as “veritable parties”

In Indiacan Education Private Limited vs. Ministry of Rural Development & Ors., the Delhi High Court appointed a Sole Arbitrator to adjudicate a dispute involving unpaid dues for a skill development project in Jammu and Kashmir. The Court addressed critical jurisdictional and contractual issues, ruling that although the Ministry of Rural Development (MoRD) and a state agency were not signatories to the primary Memorandum of Understanding (MoU), they could be referred to arbitration as “veritable parties” due to their direct involvement in the project’s sanctioning, funding, and administration. Furthermore, the Court held that despite the MoU being signed in Hyderabad, the presence of the sanctioning Ministry in Delhi and the accrual of cause of action there conferred territorial jurisdiction upon the Delhi High Court.

  1. Factual Background

The petitioner, Indiacan Education, was appointed as a Project Implementation Agency under the Deen Dayal Upadhyaya Grameen Kaushalya Yojna (DDU scheme) by the MoRD (Respondent No. 1) to provide skill development training in J&K. An MoU was executed on April 2, 2016, between the petitioner and the National Institute of Rural Development (NIRD) (Respondent No. 2), which acted as a monitoring and “pass-through” agency for funds provided by the MoRD. In 2018, the MoRD transferred the project’s administration to Respondent No. 3, a J&K state agency. The dispute arose because the petitioner allegedly completed the project milestones but did not receive the final installments of payments, totaling over ₹1.66 crores.

  1. Territorial Jurisdiction

The respondents argued that the Delhi High Court lacked jurisdiction as the MoU was signed in Hyderabad and the work was performed in J&K. Since the arbitration clause in the MoU was silent on the “seat” or “venue,” the Court applied principles from the Code of Civil Procedure (CPC).

  • The Court found that the MoRD (Respondent No. 1), which exercised ultimate financial and administrative control, had its head office in New Delhi.
  • Crucial project documents, including the original and revised sanction letters, were issued from Delhi.
  • Consequently, a material part of the cause of action arose in Delhi, satisfying the requirements for the Court to entertain the petition.
  1. Impleading Non-Signatories

A primary point of contention was whether the MoRD (R1) and the J&K agency (R3) could be compelled to arbitrate despite not being signatories to the MoU.

  • “Veritable Parties” Doctrine: Drawing on Supreme Court precedents like Cox and Kings and Hindustan Petroleum, the Court noted that a non-signatory’s conduct and relationship with the signatory parties can signify an intent to be bound.
  • Prima Facie Finding: The Court observed that the MoRD sanctioned the project, provided the grant-in-aid, and had the power to terminate the MoU or blacklist the petitioner. Respondent No. 3 was also involved in the project’s transition and was expected to honor the existing MoU.
  • Tribunal’s Role: While the Court was prima facie satisfied that these were “veritable parties,” it left the final determination of whether they are indeed bound by the arbitration agreement to the Arbitral Tribunal based on full evidence.
  1. Limitation and Acknowledgment of Debt

The respondents claimed the petition was time-barred as the request for funds dated back to 2017. The Court rejected this, finding that various communications from the respondents between 2018 and 2025 stated that the payment release was “under process” or recommended for approval. These were held to be acknowledgments of liability under Section 18 of the Limitation Act, creating a fresh cause of action and bringing the petition within the legal time limit.

  1. Final Directions

The Court allowed the petition and appointed Mr. Varun Chopra, Advocate, as the Sole Arbitrator. The Court clarified that all merits-based contentions, including jurisdictional objections and the arbitrability of claims, remain open for adjudication by the Arbitrator.

2026 DHC 5289

Indiacan Education Private Limited vs. Ministry of Rural Development (D.O.J. 02.07.2026)

2026 DHC 5289 click here to view full text of judgment

Next Story

Bail Granted in Rape Case: No evidence to prima facie connect the petitioner

In Jaswant Kumar Rao vs. State Govt. of NCT of Delhi, the Delhi High Court granted regular bail to an accused charged under Sections 376D and 506 of the IPC for allegedly filming a rape and circulating the footage. Justice Girish Kathpalia observed that, apart from the statement of the prosecutrix, there was no evidence to prima facie connect the petitioner to the filming of the incident. The Court highlighted several weaknesses in the prosecution’s case, including a significant delay in reporting the incident, the failure of forensic evidence to identify the petitioner’s voice in the video clip, and a lack of interest shown by the investigation agency, which failed to file a status report. Consequently, the Court found no justification for continued detention and ordered the petitioner’s release.

  1. Factual Allegations

The petitioner sought regular bail in FIR No. 338/2024 (PS Geeta Colony) involving allegations of gang-rape and criminal intimidation. The prosecutrix alleged that in October 2023, she was raped by her neighbor, Raj. The specific allegation against the present petitioner, Jaswant Kumar Rao, was that he filmed the act of rape and circulated the video clip. While the alleged rapist (Raj) remained at large, the petitioner was arrested on September 30, 2024.

  1. Arguments for the Petitioner

Counsel for the petitioner argued for bail on the following grounds:

  • Lack of Evidence: There is no legally admissible evidence connecting the petitioner to the filming of the alleged incident.
  • Forensic Results: A forensic examination of the video clip failed to identify the voice in the recording as that of the petitioner.
  • Delay in Reporting: There was an unexplained and inordinate delay in reporting the matter; the incident allegedly occurred in October 2023 but was only reported in July 2024.
  • Refusal of Medical Exam: The prosecutrix refused to undergo a medical examination or submit the clothes she was allegedly wearing at the time of the incident.
  1. Prosecution and Prosecutrix’s Stand
  • State’s Position: The State did not deny that the forensic report failed to link the petitioner to the video. The Investigating Officer (IO) further submitted that the petitioner’s mobile phone could not be recovered as he had allegedly destroyed it.
  • Victim’s Justification: Counsel for the prosecutrix argued that she had supported the prosecution’s case in her chief-examination. The delay in reporting was attributed to societal pressure, and the refusal of a medical exam was justified on the grounds that the incident had occurred nearly a year prior to the report.
  1. Court’s Reasoning and Analysis

The Court noted a “lack of interest” from the investigation agency, evidenced by its failure to file a status report. In its analysis of the evidence, the Court found:

  • Transmission Trail: The prosecution failed to track the transmission of the video to connect the petitioner to the act of filming.
  • Hostile Witness: A key witness (PW5), to whom the petitioner had allegedly transmitted the video, did not support the prosecution’s case during his testimony.
  • Lack of Prima Facie Case: The Court concluded that, besides the prosecutrix’s statement, there was no evidence to establish even a prima facie case that the petitioner filmed the rape.
  1. Final Order

The Court determined there was no reason to further deprive the petitioner of his liberty. The bail application was allowed, and the petitioner was ordered to be released upon:

  • Furnishing a personal bond of ₹10,000/-.
  • Providing one surety in the like amount to the satisfaction of the Trial Court.

The Court directed that a copy of the order be immediately transmitted to the Jail Superintendent to inform the accused.

2026 DHC 5389

Jaswant Kumar Rao vs. State Govt. of NCT of Delhi(D.O.J. 06.07.2026)

2026 DHC 5389 click here to view full text of judgment

Next Story

Limitation: Revision Petition Dismissed as Barred by Limitation

In Rajinder Kumar Gupta vs. Sushila Devi Jain (since deceased) through her LR, the Delhi High Court dismissed a revision petition challenging a 2020 eviction order due to an inexcusable delay in filing. Justice Amit Sharma ruled that the petitioner-tenant could not claim the benefit of Section 14 of the Limitation Act for the time spent pursuing a “wrong remedy” (an appeal against a review dismissal) because that proceeding did not seek the “same relief” as the revision against the original eviction order. The Court held that even after accounting for COVID-19 limitation extensions, the petitioner failed to challenge the eviction order immediately after his review application was dismissed, rendering the present petition time-barred by 180 days.

Summary of Judgment

  1. Factual and Procedural Background

The case originated from an eviction petition filed by the late Sushila Devi Jain regarding a shop in Yusuf Sarai, New Delhi. The landlady sought the premises for the bona fide requirement of her grandson, a CA graduate, to establish his professional office. On July 6, 2020, the Rent Controller passed an eviction order against the petitioner.

  1. Post-Eviction Litigation

Following the eviction order, the petitioner engaged in a series of legal challenges:

  • Review Petition: Filed on July 27, 2020, seeking a review of the eviction judgment based on alleged new evidence. This petition was eventually dismissed on September 25, 2025.
  • Appeal before Tribunal: The petitioner then challenged the dismissal of the review petition via an appeal (RC ARCT 13/2025) before the Rent Control Tribunal. He eventually withdrew this appeal on March 27, 2026, to file the current revision petition.
  • Current Revision: Filed on March 24, 2026, seeking to quash the original 2020 eviction order and the 2025 review dismissal.
  1. Arguments for Condonation of Delay

The petitioner sought to condone the significant delay in filing the revision by arguing:

  • The period from March 2020 to February 2022 should be excluded per Supreme Court orders regarding COVID-19.
  • The time spent pursuing the review and the subsequent appeal should be excluded under Section 14 of the Limitation Act, as he was allegedly prosecuting his remedies in “good faith” based on legal advice.
  • The limitation for a revision under Section 25B(8) of the DRCA should be three years under Article 137 of the Limitation Act.
  1. Court’s Analysis and Findings

The Court rejected the petitioner’s plea for condonation based on the following legal determinations:

  • Commencement of Limitation: Citing Supreme Court precedent (DSR Steel Pvt. Ltd.), the Court noted that when a review petition is dismissed, there is no “merger” of orders; the aggrieved party must challenge the original decree within the stipulated time.
  • Inapplicability of Section 14: The Court held that the appeal filed before the Tribunal was for a “distinct and separate” relief (challenging the review dismissal) compared to the current petition (challenging the eviction order). Therefore, the time spent on that appeal could not be excluded because it was not for the “same relief”.
  • Calculation of Delay: The Court found that even if the period taken to dispose of the review application was excluded, the petitioner failed to challenge the eviction order immediately after the review was dismissed on September 25, 2025. Instead, he waited until March 2026, making the petition time-barred by 180 days.
  1. Final Decision

The Court concluded that the petitioner offered no valid explanation for why the eviction judgment was not challenged immediately after the review dismissal. Consequently, the application for condonation of delay was dismissed, leading to the dismissal of the revision petition regarding the original eviction order. The matter was listed for future hearing only regarding secondary prayers related to execution proceedings.

2026 DHC 5386

Rajinder Kumar Gupta vs. Sushila Devi Jain(D.O.J. 06.07.2026)

2026 DHC 5386 click here to view full text of judgment

Next Story

Eviction Petition Fails: landlord failed to establish a genuine bona fide requirement f

In the case of Brij Mohan Batta vs. Tara Chand Garg & Anr., the Delhi High Court dismissed a revision petition filed by a landlord seeking the eviction of a tenant from a commercial shop in Kirti Nagar. Justice Amit Sharma upheld the decision of the Additional Rent Controller (ARC), ruling that the landlord failed to establish a genuine bona fide requirement for the premises. Although the landlord claimed he needed the shop to settle his two “unemployed” sons in a catering business, the Court found the claim to be concocted, as evidence proved the sons were already gainfully employed running a gift and packaging business at another location.

  1. Nature of the Petition

The petitioner (landlord) filed this revision petition under Section 25B(8) of the Delhi Rent Control Act (DRCA) to set aside an ARC order dated July 8, 2024, which had dismissed his eviction petition against the respondents (tenants). During the pendency of the high court proceedings, the original petitioner passed away and was represented by his legal heirs.

  1. Landlord’s Case for Eviction

The original petitioner sought eviction from Shop No. 3/14-A, Kirti Nagar, which had been let out in 1970. He asserted a bona fide requirement under Section 14(1)(e) of the DRCA, claiming:

  • He was running a catering business from an adjoining shop but was unable to manage it alone due to age.
  • His two sons, Nitin and Ankush Batta, were unemployed and needed the demised premises to run their own business.
  • He had no other suitable alternate accommodation available.
  1. Tenant’s Defense and Evidence

The respondents argued that the landlord’s requirement was forged and fabricated. They provided evidence to show:

  • The sons were already successfully running a business named “Om Vaneesa Creations” (dealing in gift items and theme packaging) from the ground floor of another property in East Punjabi Bagh.
  • They placed photographs on record showing a business banner for “Om Vaneesa Creations” that featured the mobile number of one of the petitioner’s sons.
  • The landlord possessed other vacant shops at the East Punjabi Bagh property that could be used if necessary.
  1. Reasoning of the Lower Court (ARC)

The ARC dismissed the eviction petition after finding that the landlord had not come to the court with clean hands. The ARC noted that the landlord admitted the phone number on the business banner belonged to his son but failed to produce his brother (the alleged owner of that shop) as a witness to rebut the claim that his sons were running that business. The ARC concluded the need for the Kirti Nagar shop was fabricated solely to evict the tenants.

  1. High Court’s Findings and Analysis
  • Limited Scope of Revision: The Court emphasized that its powers under Section 25B(8) of the DRCA are supervisory in nature and not as wide as an appellate court. It can only interfere if the lower court’s order suffers from a jurisdictional error or grave illegality.
  • Failure to Rebut Evidence: The High Court found that once the tenants raised a triable issue regarding the sons’ existing business, the onus shifted to the landlord to displace that presumption. The landlord failed to prove that his sons intended to wind up their current business or that the East Punjabi Bagh premises were unsuitable.
  • Appreciation of Evidence: The Court held that the ARC’s reliance on the photographs and the son’s visiting card—which shared the same contact details—was legally sound.
  1. Final Conclusion

Finding no error apparent on the face of the record or perversity in the ARC’s judgment, the High Court dismissed the revision petition and upheld the refusal to grant an eviction order

2026 DHC 5385

Brij Mohan Batta vs. Tara Chand Garg & Anr.(D.O.J. 06.07.2026)

2026 DHC 5385 click here to view full text of judgment

Next Story

Eviction Upheld as landlord had established a genuine bona fide requirement

In Shalimar Paints Ltd & Anr. vs. M/S Phelps and Company Pvt Ltd, the Delhi High Court upheld an eviction order against a tenant occupying a prime commercial space in Connaught Place. Justice Amit Sharma dismissed the revision petition, ruling that the respondent-landlord had established a genuine bona fide requirement to expand its art business wing, “The Biv”. The Court reaffirmed that a landlord is the best judge of their own requirements and the tenant cannot dictate how the landlord should utilize available space or adjust their business operations. The Court found no merit in the tenant’s claims regarding alternate accommodation or forged documents, concluding that the Rent Controller’s decision to refuse “leave to defend” was legally sound.

  1. Factual Background

The petitioners (tenants) challenged an order dated November 6, 2025, passed by the Rent Controller, which had dismissed their application for leave to defend and passed an eviction order for property No. 9-A, First Floor, Inner Circle, Connaught Place. The respondent (landlord), a private company, sought the premises under Section 14(1)(e) of the Delhi Rent Control (DRC) Act for the expansion of its art business, which involves curating and exhibiting paintings and artifacts.

  1. Landlord’s Bona Fide Requirement

The landlord argued that its current operations on the third floor and terrace were unsuitable due to lack of adequate space for displays and meetings, and because that area was only accessible via the “middle circle,” which has lower commercial visibility and footfall. They intended to remove a common wall between an existing director’s office and the tenanted premises to create a larger gallery and storage area.

  1. Tenant’s Grounds for Defense

The petitioners raised several triable issues in their leave to defend application:

  • Alternate Accommodation: They alleged the landlord concealed approximately 7,500 sq. ft. of available commercial space on the upper floors.
  • Mala Fide Intentions: They claimed the landlord’s actual goal was to evict them and re-let the property at a higher rent.
  • Forged Documents: The tenants alleged that certain challans/invoices submitted by the landlord to prove its art business activities were fabricated, pointing to inconsistencies in serial numbers and dates.
  • Legal Maintainability: They argued that a company cannot seek eviction under Section 14(1)(e) and must instead invoke Section 22 of the DRC Act.
  1. Court’s Findings and Analysis
  • Landlord as the Best Judge: The Court emphasized the settled legal principle that a tenant cannot dictate terms to a landlord regarding the suitability of alternate premises. The landlord’s preference for the first floor due to its strategic entrance from the inner circle was deemed a valid business decision.
  • Suitability of Upper Floors: The Court noted that the third floor was already utilized for co-working operations and suffered from diminished foot traffic and visibility, making it an unsuitable alternative for a high-end art gallery.
  • Genuineness of Challans: Upon perusal, the Court found that the continuity of item numbers across different dates supported the validity of the invoices. It held that minor date inconsistencies did not create a triable issue regarding the landlord’s bona fide intent.
  • Legal Status of Companies: The Court dismissed the challenge regarding Section 22 of the DRC Act, noting that it is well-settled that a body corporate is not barred from invoking Section 14(1)(e).
  • Limited Scope of Revision: Under Section 25B(8), the High Court’s role is not to act as an appellate body but to ensure the Rent Controller’s order is “according to law”. Finding no illegality or jurisdictional error, the Court declined to interfere.
  1. Final Conclusion

The revision petition was dismissed. The Court directed the petitioners to vacate and hand over peaceful possession of the premises forthwith, noting that the statutory six-month grace period under the DRC Act had already lapsed.

2026 DHC 5384

Shalimar Paints Ltd & Anr. vs. M/S Phelps and Company Pvt Ltd,(D.O.J. 06.07.2026)

2026 DHC 5384 click here to view full text of judgment

Hi Judgments Online