In the case of India International Convention and Exhibition Centre Limited vs. Larsen and Toubro Limited, the Delhi High Court set aside an interim order passed by a Majority Arbitral Tribunal that had directed the petitioner (IICECL) to release approximately ₹227.18 crores to the respondent contractor (L&T),. Justice Harish Vaidyanathan Shankar held that while an Arbitral Tribunal has the power to grant monetary relief under Section 17 of the Arbitration Act, such a power must be exercised sparingly and only when a “higher threshold” of scrutiny is met,,. The Court found the tribunal’s reasoning to be internally inconsistent, particularly as it granted relief for certain stage payments while acknowledging that the underlying disputes regarding “negative variations” and contract price reconciliation required a full trial,
- Factual Context
The dispute arose from an Engineering, Procurement and Construction (EPC) contract dated January 30, 2018, for the development of the India International Convention and Expo Centre (IICC) in Dwarka, New Delhi,. During the execution of the project, significant conflicts emerged between IICECL (a government-backed Special Purpose Vehicle) and L&T regarding scope changes, negative variations, and delays,. L&T eventually invoked arbitration, raising claims of approximately ₹3,000 crores, while IICECL raised counter-claims of approximately ₹1,056 crores.
- The Impugned Interim Order
During the pendency of the arbitration, L&T moved an application under Section 17 of the Arbitration and Conciliation Act, seeking the release of amounts certified under various Stage Payment (SP) certificates. On April 3, 2026, a Majority Arbitral Tribunal directed IICECL to release ₹227,18,46,552/- in respect of stage payments SP-69 and SP-70 as an interim measure. IICECL challenged this before the High Court, contending that the tribunal had effectively granted a substantive portion of the final relief under the guise of an interim protective measure,.
- Core Legal Issues and Arguments
- Petitioner (IICECL): Argued that Section 17 is preservative and protective, not a mechanism to prejudge contested monetary claims or fasten substantive liability before evidence is led,. They contended the tribunal ignored caveats in the engineer’s certifications which made payments subject to the final reconciliation of the contract price,.
- Respondent (L&T): Maintained that the amounts for SP-69 and SP-70 had already undergone a formal contractual certification mechanism and stood admitted and payable,. They argued that withholding these funds caused an “irreparable injury” to their cash flow in a large-scale infrastructure project,.
- Court’s Analysis and Reasoning
The High Court conducted an exhaustive review of the tribunal’s application of the “triple test” for interim relief:
- Prima Facie Case: The Court found an “apparent inconsistency” in the tribunal’s findings. The tribunal had correctly held that SP-68 involved complex disputes requiring a full trial, yet it proceeded to find a prima facie case for SP-69 and SP-70 despite them being subject to similar caveats regarding contract price reconciliation,.
- Balance of Convenience: The Court observed that the project had already been substantially completed, inaugurated, and operationalized, hosting major events. Furthermore, approximately 80% of the revised contract price had already been paid to L&T. In this context, the Court could not discern how the balance of convenience decisively favored the contractor over the employer,.
- Irreparable Injury: The Court rejected the argument that a mere monetary delay constitutes irreparable harm in this instance. Since the project was already functional, the “cash flow” argument for the purpose of completing the works lacked sufficient force to justify the mandatory release of nearly ₹227 crores as an interim measure,.
- Final Conclusion
The Court concluded that the Majority Arbitral Tribunal had traveled beyond the permissible limits of Section 17 and had failed to satisfy the heightened threshold required for mandatory interim monetary directions,. Consequently, the appeal was allowed, and the tribunal’s interim order for payment was set aside. The Court clarified that this judgment does not constitute an expression on the ultimate merits of the claims or counter-claims pending before the tribunal.
2026 DHC 5249
India International Convention And Exhibition Centre Limited V. Larsen And Toubro Limited (D.O.J. 01.07.2026)




