In this civil appeal, the Supreme Court addressed whether a Public Interest Litigation (PIL) is an appropriate legal remedy to challenge the validity of a tender process involving the inter-se comparative assessment of competing private bidders. The Supreme Court held that the High Court erred in entertaining the PIL, noting that the petitioner acted as the alter ego of an unsuccessful bidder and that the monetary magnitude of the work (Rs. 23 crores) did not justify claims of public resource wastage. Considering that a portion of the road construction work was already completed and upon receiving an undertaking from the appellant to finish the remaining work without compromising quality, the Supreme Court set aside the High Court’s directive to re-tender and granted the appellant three months to complete the project.
- Background of the Dispute: The Himachal Pradesh High Court had allowed a PIL (CWPIL No. 30 of 2024) on December 24, 2024, quashing the award of work for the upgradation of the Matiana-Mahori to Chhaila road (under PMGSY package No. HP-09-694) in favor of the appellant (Respondent No. 5 in the PIL) and ordering a re-tender.
- Maintainability of PIL: The Supreme Court expressed strong reservations about utilizing a PIL to adjudicate tender validity disputes and comparative claims between private bidders, particularly when the project cost was relatively modest and the original complainant (an unsuccessful bidder) had already withdrawn its complaint.
- Factors Before the High Court: The High Court’s decision had originally been influenced by issues concerning official contradictions over complaints, the nature of the appellant’s prior work experience (whether as a sub-contractor or prime contractor), and the use of alternate operating names.
- Supreme Court Directions & Relief:
- Taking note of the appellant’s affidavit stating that 3 kilometers of road construction along with retaining and breast walls were already completed, the Court allowed the appellant to finish the remainder of the project.
- The appellant was granted a period of three months to complete the entire allotted work at the original rates of March 15, 2024, subject to official verification of quality.
- If the work is uncompleted within this timeframe, the official respondents are directed to re-tender the work at prevailing market rates.
- Previous interim orders restraining third-party rights were modified accordingly, and the matter was listed for the first week of December 2026 for the filing of a compliance report.
2026 INSC 1037
O.P. Mehta v. Mohinder Kalta & Ors. (D.O.J. 23.09.2026)


