This judgment delivered by the Delhi High Court addresses a petition filed under Section 29A(5) of the Arbitration and Conciliation Act, 1996, seeking a one-year extension of the Arbitral Tribunal’s mandate. The delay in the arbitral proceedings was primarily caused by pending matters before the NCLT, Cuttack, regarding the maintainability of the respondent’s counter-claim under the Insolvency and Bankruptcy Code moratorium. With both parties mutually consenting to the extension and the proceedings currently at the final arguments stage, the High Court allowed the petition and extended the mandate by one year.
- Statutory Provision: The petition was preferred under Section 29A(5) of the Arbitration and Conciliation Act, 1996, to extend the mandate of the learned Arbitral Tribunal by an additional year.
- Reason for Delay: Arbitral proceedings faced delays due to prolonged proceedings before the NCLT, Cuttack, concerning the maintainability of the respondent’s counter-claim under Section 14 of the Insolvency and Bankruptcy Code, 2016, which was only cleared to be pursued via an order dated April 17, 2025.
- Current Stage: The arbitration proceedings are currently at the stage of final arguments, with the respondent having concluded its submissions and the petitioner pending its rejoinders.
- Consent of Parties: Counsel for the respondent submitted that there was no objection to the extension, meaning both parties were ad idem (in agreement) regarding the extension of the mandate.
- Court Order: Hon’ble Mr. Justice Om Prakash Shukla extended the mandate of the Arbitral Tribunal for a further period of one year effective from August 31, 2026, to conclude the proceedings and render the award, thereby disposing of the petition.
2026 DHC 6969
M/S. ARSS Infrastructure Projects Ltd v. Steel Authority of India Limited (D.O.J. 20.08.2026)